6.5 Contract Terminations for Convenience & Default (FAR Part 49)

FAC-C Professional Contracting Certification Exam

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: Contracting System & FAR Foundations

1.1 FAC-C Professional Exam Logistics & Certification Path 1.2 FAR Structure, System Architecture & Authority 1.3 Ethics, Standards of Conduct & Conflict of Interest (FAR Part 3) 1.4 Protection of Privacy & Freedom of Information (FAR Part 24) 1.5 Foreign Acquisition, Buy American & Trade Agreements (FAR Part 25) 1.6 Government Property Administration & Liability (FAR Part 45)

2 Chapter 2: Acquisition Planning & Market Research

2.1 Acquisition Planning & Strategy Development (FAR Part 7) 2.2 Market Research Techniques & Commercial Determinations (FAR Part 10 & 12) 2.3 Describing Agency Needs & Performance Work Statements (FAR Part 11) 2.4 Publicizing Contract Actions & Synopsis Rules (FAR Part 5) 2.5 Competition Requirements & Justifications for Other Than Full and Open Competition (FAR Part 6) 2.6 Organizational Conflicts of Interest (OCI) Identification & Mitigation (FAR Subpart 9.5)

3 Chapter 3: Commercial & Simplified Acquisition

3.1 Commercial Products & Services Acquisition (FAR Part 12) 3.2 Simplified Acquisition Procedures (SAP) & Micro-Purchases (FAR Part 13) 3.3 Commercial Streamlined Evaluation & Award Protocols (FAR 12.6 & 13.106) 3.4 Governmentwide Commercial Purchase Card & Electronic Micro-Purchases (FAR 13.301) 3.5 Blanket Purchase Agreements, SF 44 & Imprest Funds 3.6 Fast Payment Procedures & Unpriced Purchase Orders (FAR 13.4 & 13.2)

4 Chapter 4: Solicitations, Contracting Methods & Contract Types

4.1 Sealed Bidding Procedures & Execution (FAR Part 14) 4.2 Contracting by Negotiation & Source Selection (FAR Part 15) 4.3 Fixed-Price Contract Types (FFP, FPIF, FPEA) (FAR Part 16) 4.4 Cost-Reimbursement Contract Types (CPFF, CPIF, CPAF) (FAR Part 16) 4.5 Indefinite-Delivery Contracts & Task/Delivery Orders (RFO Subpart 16.5) 4.6 Time-and-Materials, Labor-Hour & Letter Contracts (FAR Subpart 16.6)

5 Chapter 5: Cost & Price Analysis, Small Business & Negotiations

5.1 Proposal Evaluation & Competitive Range Determination (FAR 15.306) 5.2 Price Analysis Techniques & Commercial Pricing (FAR 15.404-1) 5.3 Cost Analysis, Certified Cost/Pricing Data & TAA (FAR 15.403 & 15.404) 5.4 Small Business Programs & Set-Aside Rules (FAR Part 19) 5.5 Pre-Negotiation Objectives & Competitive Negotiations (FAR 15.406) 5.6 Contract Financing & Advance/Progress Payments (FAR Part 32)

6 Chapter 6: Contract Administration, Modifications, Disputes & Protests

6.1 Post-Award Orientation, COR Delegation & Quality Assurance (FAR Part 42 & 46) 6.2 Contract Modifications, Scope & Change Orders (FAR Part 43) 6.3 Subcontract Management & Consent to Subcontract (FAR Part 44) 6.4 Contract Options, Extensions & Performance Evaluation (RFO Parts 17 & 42) 6.5 Contract Terminations for Convenience & Default (FAR Part 49) 6.6 Bid Protests, Disputes, Appeals & Contract Closeout (RFO Parts 33 & 4)

6.5 Contract Terminations for Convenience & Default (FAR Part 49)

Key Takeaways Explain This Topic AI

Termination for Convenience (T4C - FAR Subpart 49.2/49.3) allows the Government to terminate performance in whole or in part when in the Government's interest, reimbursing performance costs, reasonable profit on work done, and settlement expenses without anticipatory profit.

Termination for Default (T4D - FAR Subpart 49.4) is a drastic government remedy for contractor failure to deliver on time, make progress, or perform contract terms, making the contractor liable for excess re-procurement costs.

Under FAR 49.607, a Cure Notice providing at least 10 calendar days is mandatory prior to issuing a T4D for failure to make progress or perform contract provisions, whereas a Show Cause Notice is used when delivery dates have passed.

If a Termination for Default is determined to be improper, wrongful, or excusable under FAR 52.249-14, it automatically converts to a Termination for Convenience.

Commercial item acquisitions under FAR 12.403 utilize streamlined Termination for Convenience and Termination for Cause procedures instead of standard FAR Part 49 clauses.

Last updated: July 2026

6.5 Contract Terminations for Convenience & Default (FAR Part 49)

Contract termination represents the complete or partial cancellation of contract performance prior to its scheduled expiration date. Because government needs change and contractor performance varies, FAR Part 49 (Termination of Contracts) establishes the legal rights, administrative protocols, cost settlement principles, and notice requirements governing contract terminations across the federal government.

Terminations fall into two major statutory categories: Termination for Convenience (T4C) and Termination for Default (T4D) (or Termination for Cause for commercial items).

1. Termination for Convenience (T4C - FAR Subparts 49.2 & 49.3)

A Termination for Convenience (T4C) is a unique sovereign right that permits the Government to terminate performance of a contract, in whole or in part, whenever the Contracting Officer determines that termination is in the best interest of the Government (FAR 49.101).

Core Principles of T4C Settlement

No Anticipatory Profit: The contractor is NOT entitled to prospective, unearned, or anticipatory profits on unperformed work.

Allowable Costs: Under FAR 49.201 , the contractor is entitled to fair compensation comprising:

  • Direct and indirect costs incurred in performing work up to the effective date of termination;
  • A reasonable profit on work actually performed (unless the contract was operating at a loss);
  • Reasonable settlement expenses (accounting, legal, clerical costs incurred preparing the settlement proposal);

Acceptable subcontractor settlement costs.

Settlement Proposal Window: The contractor must submit a final Termination Settlement Proposal within 1 year from the effective date of termination, unless extended by the Termination Contracting Officer (TCO).

2. Termination for Default (T4D - FAR Subpart 49.4)

Termination for Default (T4D) is a severe legal remedy exercised when a contractor fails to perform contractual obligations under a non-commercial fixed-price contract. Under FAR 49.402-1 , the CO may terminate a contract for default if the contractor:

  • Fails to deliver supplies or perform services within the specified contract delivery schedule;
  • Fails to make progress so as to endanger performance of the contract;

Fails to perform any other provision of the contract.

Mandatory Notice Sequences: Cure Notice vs. Show Cause Notice (FAR 49.607) +-----------------------------------------------------------------------------------+

  • | T4D MANDATORY NOTICE SEQUENCES |
  • +-----------------------------------------------------------------------------------+
  • | SCENARIO A: Failure to Make Progress OR Failure to Perform Provision |
  • | Step 1: Issue CURE NOTICE providing at least 10 CALENDAR DAYS to cure defect. |
  • | Step 2: If uncured after 10 days, issue SHOW CAUSE NOTICE or T4D notice. |
  • | |
  • | SCENARIO B: Failure to Deliver on Schedule (Delivery Date Passed) |
  • | Step 1: NO Cure Notice required! Issue SHOW CAUSE NOTICE immediately. |
  • | Step 2: Issue Notice of Termination for Default on SF 30. |
  • +-----------------------------------------------------------------------------------+

Exam Critical: A Cure Notice is legally required ONLY when the termination is based on failure to make progress or failure to perform another contract provision, and there must remain at least 10 calendar days in the performance schedule. If the delivery date has already passed, no Cure Notice is required!

  • 3. Financial Consequences of Default & Excusable Delays
  • Liabilities of Defaulted Contractor

When a contract is terminated for default under FAR 52.249-8:

  • The Government pays contract price only for completed and accepted items;
  • The contractor forfeits all profit on unperformed work;

Excess Re-procurement Costs: The Government may re-procure similar supplies or services from another source and charge the defaulted contractor for all excess re-procurement costs incurred (FAR 49.402-6).

Excusable Delays (FAR 52.249-14)

A contractor cannot be terminated for default if performance failure arises from causes beyond the control and without the fault or negligence of the contractor. Excusable delay grounds include:

  • Acts of God or public enemy;
  • Sovereign acts of the Government (civil or military);
  • Fires, floods, epidemics, or quarantine restrictions;
  • Strikes or freight embargoes;

Unusually severe weather.

Default-to-Convenience Conversion Rule

Under FAR 52.249-8(g) , if a contract is terminated for default and it is subsequently determined that the contractor was not in default, or that the delay was excusable, the rights and obligations of the parties automatically convert to a Termination for Convenience (T4C) .

4. Commercial Item Terminations (FAR 12.403)

For commercial product and commercial service contracts governed by FAR Part 12, standard FAR Part 49 clauses do not apply. Instead, FAR 12.403 and clause FAR 52.212-4(l)/(m) govern terminations:

Termination Type Commercial Item Procedures (FAR 12.403) Standard Non-Commercial (FAR Part 49)

Convenience Contractor paid percentage of contract price reflecting percentage of work performed plus reasonable charges resulting from termination. Detailed cost-based settlement proposal under FAR 49.2/49.3.

Default / Cause Terminated for Cause . Government is not liable for unaccepted work and may charge excess re-procurement costs. Terminated for Default . Strict Cure Notice / Show Cause procedures apply under FAR 49.4.

Summary Table: T4C vs. T4D Comparison Matrix

  • Feature / Dimension Termination for Convenience (T4C) Termination for Default (T4D)
  • Government Motivation Agency best interest / changing needs Contractor failure to perform
  • Contractor Fault Required? NO YES
  • Notice Required? Written T4C Notice Cure Notice (10 days min) or Show Cause
  • Allowable Recovery Costs incurred + profit on work done + settlement costs Payment only for accepted items
  • Anticipatory Profit? STRICTLY NO STRICTLY NO
  • Excess Re-procurement Costs? NO YES (Assessed against contractor)