13.1 Time Value of Money and Project Selection
NCEES Fundamentals of Engineering FE
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Mathematics
1.1 Analytic Geometry, Algebra, and Trigonometry 1.2 Calculus and Differential Equations 1.3 Numerical Methods and Measurement Error
2 Chapter 2: Probability and Statistics
2.1 Probability Distributions, Central Tendency, and Regression 2.2 Hypothesis Testing, ANOVA, and Statistical Quality Control
3 Chapter 3: Engineering Sciences
3.1 Mechanics and Dynamics 3.2 Electrical Circuits and Laws
4 Chapter 4: Materials Science
4.1 Material Properties and Compatibilities 4.2 Corrosion, Polymers, Ceramics, and Composites
5 Chapter 5: Chemistry and Biology
5.1 Stoichiometry, Analytical Chemistry, and Chemical Equilibrium 5.2 Organic Chemistry and Nomenclature 5.3 Biological Systems and Kinetics
6 Chapter 6: Fluid Mechanics and Dynamics
6.1 Fluid Properties, Dimensionless Numbers, and Flow Regimes 6.2 Bernoulli Equation and Mechanical Energy Balances 6.3 Flow Measurement and Fluid Machinery 6.4 Compressible and Non-Newtonian Flows
7 Chapter 7: Thermodynamics
7.1 Thermodynamic Properties, Ideal Gas, and State Equations 7.2 Laws of Thermodynamics and Cyclic Processes 7.3 Vapor-Liquid Equilibrium (VLE) and Phase Equilibrium 7.4 Chemical Equilibrium, Heats of Reaction, and Mixing
8 Chapter 8: Material and Energy Balances
8.1 Steady-State Material Balances 8.2 Unsteady-State Mass Balances 8.3 Steady-State Energy Balances 8.4 Unsteady-State Energy Balances
9 Chapter 9: Heat Transfer
9.1 Conduction, Convection, and Radiation Fundamentals 9.2 Heat Transfer Coefficients, Fouling, and Overall U 9.3 Heat Exchanger Design
10 Chapter 10: Mass Transfer and Separation
10.1 Diffusion Fundamentals 10.2 Gas Absorption, Stripping, and Liquid-Liquid Extraction 10.3 Distillation and McCabe-Thiele Method 10.4 Continuous Contact Methods, Membrane Separations, and Evaporative Operations
11 Chapter 11: Solids Handling
11.1 Particle Properties and Solid Processing 11.2 Solids Transportation and Storage
12 Chapter 12: Chemical Reaction Engineering
12.1 Reaction Kinetics and Performance Metrics 12.2 Ideal Reactor Design 12.3 Multiple Reactions, Catalysis, and Heterogeneous Kinetics
13 Chapter 13: Economics
13.1 Time Value of Money and Project Selection 13.2 Profitability Analysis, Depreciation, and Break-Even
14 Chapter 14: Process Design
14.1 Process Flowsheets and Instrumentation 14.2 Equipment Selection, Sizing, and Cost Estimation 14.3 Process Optimization, Sustainability, and Inherently Safer Design
15 Chapter 15: Process Control
15.1 Process Dynamics and Transfer Functions 15.2 Feedback Control Loops, PID Tuning, and Control Hardware
16 Chapter 16: Safety, Health, and Environment
16.1 Flammability, Toxicity, and Industrial Hygiene 16.2 Hazard Identification and Risk Analysis 16.3 Overpressure Relief, Reactivity Hazards, and Waste Regulations
17 Chapter 17: Ethics and Professional Practice
17.1 Professional Codes of Ethics and Public Welfare 17.2 Intellectual Property, Contracts, and Professional Liability
13.1 Time Value of Money and Project Selection
Key Takeaways Explain This Topic AI
Time Value of Money (TVM) is the core principle of engineering economics, establishing equivalence between cash flows at different times.
Compounding interest formulas and factors (P/F, F/P, P/A, A/P, P/G, A/G) allow conversion of discrete cash flows to a common temporal basis.
Nominal annual interest rates must be adjusted to effective interest rates when compounding frequency exceeds once per year.
Mutually exclusive projects with unequal lifespans are compared using the Annual Worth (AW) method to avoid repeat cycle calculations.
Capitalized cost represents the present worth of a project with an infinite lifespan, commonly used for public utilities and permanent structures.
Last updated: July 2026
13.1 Time Value of Money and Project Selection
Quick Answer: The Time Value of Money (TVM) is the core principle of engineering economics, stating that a dollar today is worth more than a dollar in the future due to its earning capacity (interest). The NCEES FE Reference Handbook provides standard formulas and interest tables for discrete cash flows. Project selection requires converting cash flows to a common basis using Present Worth (PW) , Future Worth (FW) , Annual Worth (AW) , or the Rate of Return (ROR) . For comparing projects with unequal lives, the Annual Worth (AW) method is the most efficient because it does not require repeating cycles to a Least Common Multiple (LCM) of lives.
Fundamental Principles of Time Value of Money
Engineering decisions almost always involve cash flows occurring at different times—such as capital investments today, annual operating expenses, periodic equipment replacements, and salvage values at the end of a project's life. To make valid comparisons, all cash flows must be moved to the same point in time. This process is called equivalence .
The relationship between present worth P P P and future worth F F F after n n n periods at interest rate i i i per period is: F = P ( 1 + i ) n F = P(1 + i)^n F = P ( 1 + i ) n
This is the single-payment compound-amount factor, denoted as ( F / P , i , n ) (F/P, i, n) ( F / P , i , n ) . Conversely, the present value of a future sum is: P = F ( 1 + i ) − n P = F(1 + i)^{-n} P = F ( 1 + i ) − n
This is the single-payment present-worth factor, denoted as ( P / F , i , n ) (P/F, i, n) ( P / F , i , n ) .
Nominal and Effective Interest Rates
When interest compounding frequency does not match the annual payment period, we distinguish between the nominal interest rate r r r and the effective annual interest rate i e i_e i e . The relationship is given by: i e = ( 1 + r m ) m − 1 i_e = \left(1 + \frac{r}{m}\right)^m - 1 i e = ( 1 + m r ) m − 1
where m m m is the number of compounding periods per year. If compounding is continuous, the effective interest rate is: i e = e r − 1 i_e = e^r - 1 i e = e r − 1
On the FE exam, always check the compounding period. If a problem states "12% compounded monthly," the rate per month is 12 % / 12 = 1 % 12\% / 12 = 1\% 12%/12 = 1% , and the number of periods in 3 years is 3 × 12 = 36 3 \times 12 = 36 3 × 12 = 36 .
Cash Flow Equivalence Factors
The FE Reference Handbook summarizes these standard discrete compounding factors. Below is a summary of the most critical factors:
To Find Given Factor Name Notation Formula
F F F P P P Single Payment Compound Amount ( F / P , i , n ) (F/P, i, n) ( F / P , i , n ) ( 1 + i ) n (1+i)^n ( 1 + i ) n
P P P F F F Single Payment Present Worth ( P / F , i , n ) (P/F, i, n) ( P / F , i , n ) ( 1 + i ) − n (1+i)^{-n} ( 1 + i ) − n
F F F A A A Uniform Series Compound Amount ( F / A , i , n ) (F/A, i, n) ( F / A , i , n ) ( 1 + i ) n − 1 i \frac{(1+i)^n - 1}{i} i ( 1 + i ) n − 1
P P P A A A Uniform Series Present Worth ( P / A , i , n ) (P/A, i, n) ( P / A , i , n ) ( 1 + i ) n − 1 i ( 1 + i ) n \frac{(1+i)^n - 1}{i(1+i)^n} i ( 1 + i ) n ( 1 + i ) n − 1
A A A F F F Sinking Fund ( A / F , i , n ) (A/F, i, n) ( A / F , i , n ) i ( 1 + i ) n − 1 \frac{i}{(1+i)^n - 1} ( 1 + i ) n − 1 i
A A A P P P Capital Recovery ( A / P , i , n ) (A/P, i, n) ( A / P , i , n ) i ( 1 + i ) n ( 1 + i ) n − 1 \frac{i(1+i)^n}{(1+i)^n - 1} ( 1 + i ) n − 1 i ( 1 + i ) n
Arithmetic and Geometric Gradients
An arithmetic gradient is a series where the cash flow increases by a constant amount G G G each period (e.g., $100, $150, $200). The present worth of an arithmetic gradient is: P = G ( P / G , i , n ) = G [ ( 1 + i ) n − i n − 1 i 2 ( 1 + i ) n ] P = G(P/G, i, n) = G \left[ \frac{(1+i)^n - in - 1}{i^2(1+i)^n} \right] P = G ( P / G , i , n ) = G [ i 2 ( 1 + i ) n ( 1 + i ) n − in − 1 ]
A geometric gradient occurs when cash flows increase by a constant percentage g g g each period (e.g., fuel cost increasing by 5% annually). The present worth is calculated as: P = A 1 [ 1 − ( 1 + g ) n ( 1 + i ) − n i − g ] ( for i ≠ g ) P = A_1 \left[ \frac{1 - (1+g)^n(1+i)^{-n}}{i - g} \right] \quad (\text{for } i \neq g) P = A 1 [ i − g 1 − ( 1 + g ) n ( 1 + i ) − n ] ( for i = g ) P = A 1 ⋅ n ( 1 + i ) − 1 ( for i = g ) P = A_1 \cdot n(1 + i)^{-1} \quad (\text{for } i = g) P = A 1 ⋅ n ( 1 + i ) − 1 ( for i = g )
where A 1 A_1 A 1 is the cash flow at the end of Year 1.
Project Selection Metrics
To choose among competing alternatives, engineers evaluate:
Present Worth (PW) : Converts all cash flows to the present time ( t = 0 t = 0 t = 0 ). A project is viable if P W ( i ) ≥ 0 PW(i) \ge 0 P W ( i ) ≥ 0 at the Minimum Attractive Rate of Return (MARR).
Annual Worth (AW) : Converts all cash flows to an equivalent uniform annual series. It is useful for comparing projects because A W = P W ( A / P , i , n ) AW = PW(A/P, i, n) A W = P W ( A / P , i , n ) .
Future Worth (FW) : Evaluates cash flows at the end of the project life ( t = n t = n t = n ).
Rate of Return (ROR) : The interest rate at which the present worth of net cash flows equals zero (i.e., P W ( R O R ) = 0 PW(ROR) = 0 P W ( ROR ) = 0 ). A project is acceptable if R O R ≥ M A R R ROR \ge MARR ROR ≥ M A RR .
Capitalized Cost
Capitalized cost is the present worth of an asset or project that is assumed to have an infinite life. This concept is typically applied to public works (e.g., dams, bridges) or permanent endowments. For a series of annual expenses A A A stretching to infinity, the capitalized cost is: C a p i t a l i z e d C o s t = A i Capitalized\ Cost = \frac{A}{i} C a p i t a l i ze d C os t = i A
If the project involves a recurring replacement cost C C C every k k k periods, the capitalized cost is: C a p i t a l i z e d C o s t = P i n i t i a l + A i + C ( 1 + i ) k − 1 Capitalized\ Cost = P_{initial} + \frac{A}{i} + \frac{C}{(1+i)^k - 1} C a p i t a l i ze d C os t = P ini t ia l + i A + ( 1 + i ) k − 1 C
where P i n i t i a l P_{initial} P ini t ia l is the first-time cost and C C C is the replacement cost (less any salvage value) that occurs every k k k periods.
Comparison of Alternatives with Unequal Lives
When comparing mutually exclusive alternatives, the comparison must cover the same timeframe to be valid.
Equal Lives
For alternatives with the same lifespan, we directly compare their P W PW P W , A W AW A W , or F W FW F W at the MARR. The option with the highest algebraically worth (least negative for cost-only projects, or highest positive for revenue-generating projects) is selected.
Unequal Lives
If the lifespans differ, comparing P W PW P W over their individual lives is a fatal error. We must use one of the following methods:
Least Common Multiple (LCM) of Lives : Repeat each project's cycle until they reach a common endpoint (e.g., for a 3-year and a 4-year project, the study period is 12 years). This assumes the projects can be renewed at identical costs.
Annual Worth (AW) Method : Calculate the equivalent annual worth over each project's individual life. Because the AW represents the equivalent annual cost/benefit of a single cycle, it is automatically valid for infinite cycles of renewal. This is the preferred and fastest method on the FE exam.
Lease vs. Buy vs. Make Decisions
In process plant design, engineers must choose between leasing equipment, purchasing it outright, or manufacturing a component in-house:
Lease : Reduces initial capital expenditure, keeps debt off the balance sheet, and provides flexibility. However, it usually results in higher operating cash outflows over time and offers no salvage value or depreciation tax shield.
Buy : Requires significant initial capital expenditure but results in lower operating costs, ownership of the asset (including salvage value), and tax benefits through depreciation.
Make (In-house Production) : Feasible when a chemical plant has excess utility capacity or raw material streams. The decision hinges on comparing the total cost of purchasing a chemical or service vs. the fixed capital investment and variable costs of producing it in-house. The break-even quantity is found where: T o t a l C o s t B u y = T o t a l C o s t M a k e ⇒ P r i c e × Q = F i x e d C o s t + V a r i a b l e C o s t × Q Total\ Cost_{Buy} = Total\ Cost_{Make} \Rightarrow Price \times Q = Fixed\ Cost + Variable\ Cost \times Q T o t a l C os t B u y = T o t a l C os t M ak e ⇒ P r i ce × Q = F i x e d C os t + Va r iab l e C os t × Q
- Worked Examples
- Example 1: Unequal Lives Comparison
Compare two heat exchangers at a MARR of 10%:
Exchanger A : Capital cost = $15,000, annual maintenance = $1,000, life = 3 years, salvage value = $3,000.
Exchanger B : Capital cost = $25,000, annual maintenance = $500, life = 6 years, salvage value = $5,000.
Solution using the Annual Worth (AW) method: For Exchanger A: A W A = − 15 , 000 ( A / P , 10 % , 3 ) − 1 , 000 + 3 , 000 ( A / F , 10 % , 3 ) AW_A = -15,000(A/P, 10\%, 3) - 1,000 + 3,000(A/F, 10\%, 3) A W A = − 15 , 000 ( A / P , 10% , 3 ) − 1 , 000 + 3 , 000 ( A / F , 10% , 3 )
From interest tables or formulas: ( A / P , 10 % , 3 ) = 0.1 ( 1.1 ) 3 ( 1.1 ) 3 − 1 = 0.4021 (A/P, 10\%, 3) = \frac{0.1(1.1)^3}{(1.1)^3 - 1} = 0.4021 ( A / P , 10% , 3 ) = ( 1.1 ) 3 − 1 0.1 ( 1.1 ) 3 = 0.4021 ( A / F , 10 % , 3 ) = 0.1 ( 1.1 ) 3 − 1 = 0.3021 (A/F, 10\%, 3) = \frac{0.1}{(1.1)^3 - 1} = 0.3021 ( A / F , 10% , 3 ) = ( 1.1 ) 3 − 1 0.1 = 0.3021 A W A = − 15 , 000 ( 0.4021 ) − 1 , 000 + 3 , 000 ( 0.3021 ) = − 6 , 031.50 − 1 , 000 + 906.30 = − $ 6 , 125.20 AW_A = -15,000(0.4021) - 1,000 + 3,000(0.3021) = -6,031.50 - 1,000 + 906.30 = -\text{\textdollar}6,125.20 A W A = − 15 , 000 ( 0.4021 ) − 1 , 000 + 3 , 000 ( 0.3021 ) = − 6 , 031.50 − 1 , 000 + 906.30 = − $ 6 , 125.20
For Exchanger B: A W B = − 25 , 000 ( A / P , 10 % , 6 ) − 500 + 5 , 000 ( A / F , 10 % , 6 ) AW_B = -25,000(A/P, 10\%, 6) - 500 + 5,000(A/F, 10\%, 6) A W B = − 25 , 000 ( A / P , 10% , 6 ) − 500 + 5 , 000 ( A / F , 10% , 6 )
( A / P , 10 % , 6 ) = 0.1 ( 1.1 ) 6 ( 1.1 ) 6 − 1 = 0.2296 (A/P, 10\%, 6) = \frac{0.1(1.1)^6}{(1.1)^6 - 1} = 0.2296 ( A / P , 10% , 6 ) = ( 1.1 ) 6 − 1 0.1 ( 1.1 ) 6 = 0.2296 ( A / F , 10 % , 6 ) = 0.1 ( 1.1 ) 6 − 1 = 0.1296 (A/F, 10\%, 6) = \frac{0.1}{(1.1)^6 - 1} = 0.1296 ( A / F , 10% , 6 ) = ( 1.1 ) 6 − 1 0.1 = 0.1296 A W B = − 25 , 000 ( 0.2296 ) − 500 + 5 , 000 ( 0.1296 ) = − 5 , 740 − 500 + 648 = − $ 5 , 592 AW_B = -25,000(0.2296) - 500 + 5,000(0.1296) = -5,740 - 500 + 648 = -\text{\textdollar}5,592 A W B = − 25 , 000 ( 0.2296 ) − 500 + 5 , 000 ( 0.1296 ) = − 5 , 740 − 500 + 648 = − $ 5 , 592
Conclusion: Exchanger B has a lower equivalent annual cost ( − $ 5 , 592 -\text{\textdollar}5,592 − $ 5 , 592 vs. − $ 6 , 125.20 -\text{\textdollar}6,125.20 − $ 6 , 125.20 ) and is the preferred option.
Example 2: Capitalized Cost Calculation
A water treatment system has an initial installation cost of $50,000. Every 5 years, the filter membranes must be replaced at a cost of $12,000. The annual operating cost is $2,000. Calculate the capitalized cost of this system at a 6% annual interest rate.
Solution: The capitalized cost is the present worth of an infinite series of these expenses: C a p i t a l i z e d C o s t = I n i t i a l I n s t a l l a t i o n C o s t + P W o p e r a t i n g + P W r e p l a c e m e n t s Capitalized\ Cost = Initial\ Installation\ Cost + PW_{operating} + PW_{replacements} C a p i t a l i ze d C os t = I ni t ia l I n s t a ll a t i o n C os t + P W o p er a t in g + P W re pl a ce m e n t s P W o p e r a t i n g = A i = 2 , 000 0.06 = $ 33 , 333.33 PW_{operating} = \frac{A}{i} = \frac{2,000}{0.06} = \text{\textdollar}33,333.33 P W o p er a t in g = i A = 0.06 2 , 000 = $ 33 , 333.33 P W r e p l a c e m e n t s = C ( 1 + i ) k − 1 = 12 , 000 ( 1.06 ) 5 − 1 = 12 , 000 1.3382 − 1 = 12 , 000 0.3382 = $ 35 , 481.96 PW_{replacements} = \frac{C}{(1+i)^k - 1} = \frac{12,000}{(1.06)^5 - 1} = \frac{12,000}{1.3382 - 1} = \frac{12,000}{0.3382} = \text{\textdollar}35,481.96 P W re pl a ce m e n t s = ( 1 + i ) k − 1 C = ( 1.06 ) 5 − 1 12 , 000 = 1.3382 − 1 12 , 000 = 0.3382 12 , 000 = $ 35 , 481.96 C a p i t a l i z e d C o s t = 50 , 000 + 33 , 333.33 + 35 , 481.96 = $ 118 , 815.29 Capitalized\ Cost = 50,000 + 33,333.33 + 35,481.96 = \text{\textdollar}118,815.29 C a p i t a l i ze d C os t = 50 , 000 + 33 , 333.33 + 35 , 481.96 = $ 118 , 815.29