Study guide
14.2 Equipment Selection, Sizing, and Cost Estimation
NCEES Fundamentals of Engineering FE
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Mathematics
1.1 Analytic Geometry, Algebra, and Trigonometry 1.2 Calculus and Differential Equations 1.3 Numerical Methods and Measurement Error
2 Chapter 2: Probability and Statistics
2.1 Probability Distributions, Central Tendency, and Regression 2.2 Hypothesis Testing, ANOVA, and Statistical Quality Control
3 Chapter 3: Engineering Sciences
3.1 Mechanics and Dynamics 3.2 Electrical Circuits and Laws
4 Chapter 4: Materials Science
4.1 Material Properties and Compatibilities 4.2 Corrosion, Polymers, Ceramics, and Composites
5 Chapter 5: Chemistry and Biology
5.1 Stoichiometry, Analytical Chemistry, and Chemical Equilibrium 5.2 Organic Chemistry and Nomenclature 5.3 Biological Systems and Kinetics
6 Chapter 6: Fluid Mechanics and Dynamics
6.1 Fluid Properties, Dimensionless Numbers, and Flow Regimes 6.2 Bernoulli Equation and Mechanical Energy Balances 6.3 Flow Measurement and Fluid Machinery 6.4 Compressible and Non-Newtonian Flows
7 Chapter 7: Thermodynamics
7.1 Thermodynamic Properties, Ideal Gas, and State Equations 7.2 Laws of Thermodynamics and Cyclic Processes 7.3 Vapor-Liquid Equilibrium (VLE) and Phase Equilibrium 7.4 Chemical Equilibrium, Heats of Reaction, and Mixing
8 Chapter 8: Material and Energy Balances
8.1 Steady-State Material Balances 8.2 Unsteady-State Mass Balances 8.3 Steady-State Energy Balances 8.4 Unsteady-State Energy Balances
9 Chapter 9: Heat Transfer
9.1 Conduction, Convection, and Radiation Fundamentals 9.2 Heat Transfer Coefficients, Fouling, and Overall U 9.3 Heat Exchanger Design
10 Chapter 10: Mass Transfer and Separation
10.1 Diffusion Fundamentals 10.2 Gas Absorption, Stripping, and Liquid-Liquid Extraction 10.3 Distillation and McCabe-Thiele Method 10.4 Continuous Contact Methods, Membrane Separations, and Evaporative Operations
11 Chapter 11: Solids Handling
11.1 Particle Properties and Solid Processing 11.2 Solids Transportation and Storage
12 Chapter 12: Chemical Reaction Engineering
12.1 Reaction Kinetics and Performance Metrics 12.2 Ideal Reactor Design 12.3 Multiple Reactions, Catalysis, and Heterogeneous Kinetics
13 Chapter 13: Economics
13.1 Time Value of Money and Project Selection 13.2 Profitability Analysis, Depreciation, and Break-Even
14 Chapter 14: Process Design
14.1 Process Flowsheets and Instrumentation 14.2 Equipment Selection, Sizing, and Cost Estimation 14.3 Process Optimization, Sustainability, and Inherently Safer Design
15 Chapter 15: Process Control
15.1 Process Dynamics and Transfer Functions 15.2 Feedback Control Loops, PID Tuning, and Control Hardware
16 Chapter 16: Safety, Health, and Environment
16.1 Flammability, Toxicity, and Industrial Hygiene 16.2 Hazard Identification and Risk Analysis 16.3 Overpressure Relief, Reactivity Hazards, and Waste Regulations
17 Chapter 17: Ethics and Professional Practice
17.1 Professional Codes of Ethics and Public Welfare 17.2 Intellectual Property, Contracts, and Professional Liability
14.2 Equipment Selection, Sizing, and Cost Estimation
Key Takeaways Explain This Topic AI
Vapor-liquid separators are sized using the Souders-Brown equation to calculate the maximum allowable vapor velocity, preventing liquid entrainment.
Pump sizing requires determining total dynamic head, hydraulic power, and motor brake power, accounting for mechanical efficiencies.
To avoid cavitation, the Net Positive Suction Head Available (NPSHA) must exceed the Net Positive Suction Head Required (NPSHR) by a safe margin.
Heat exchangers are designed using the fundamental heat transfer equation Q = U * A * F * LMTD, incorporating fouling resistances.
Purchased costs scale with capacity via the cost exponent method (six-tenths rule) and with time via inflation indexes like the CEPCI.
Last updated: July 2026
Equipment Selection, Sizing, and Cost Estimation
Process equipment sizing and cost estimation are critical stages in design that bridge engineering calculations and economic feasibility. The FE Chemical exam requires candidates to apply fluid dynamics, thermodynamics, heat transfer, and economic formulas from the NCEES Reference Handbook to size vessels, pumps, and heat exchangers, and to estimate capital costs using exponents and cost indexes.
Process Vessel Sizing (Liquid-Vapor Separators)
Vapor-liquid separators (or knock-out drums) are designed to separate liquid droplets from a gas stream. Sizing a vertical separator is governed by the maximum allowable vapor velocity ( v m a x v_{max} v ma x ) to prevent liquid droplets from being entrained back into the gas stream. This velocity is calculated using the Souders-Brown equation: v m a x = C ρ L − ρ V ρ V v_{max} = C \sqrt{\frac{\rho_L - \rho_V}{\rho_V}} v ma x = C ρ V ρ L − ρ V
where:
v m a x v_{max} v ma x is the maximum allowable vapor velocity (ft/s or m/s).
ρ L \rho_L ρ L is the liquid density at operating conditions (lb/ft³ or kg/m³).
ρ V \rho_V ρ V is the vapor density at operating conditions (lb/ft³ or kg/m³).
C C C is an empirical sizing coefficient (typically ranging from 0.1 to 0.35 ft/s, depending on tray spacing or presence of a mesh demister pad).
To design a vessel, the actual vapor velocity is typically set between 75% and 85% of v m a x v_{max} v ma x . The minimum cross-sectional area ( A A A ) of the vessel is determined from the volumetric vapor flow rate ( Q V Q_V Q V ) under operating conditions: A = Q V v a c t u a l A = \frac{Q_V}{v_{actual}} A = v a c t u a l Q V
From the cross-sectional area, the separator diameter ( D D D ) is computed as D = 4 A / π D = \sqrt{4A / \pi} D = 4 A / π . The height of the separator must accommodate liquid holdup (typically sized for 5–10 minutes of liquid surge volume) and sufficient vapor disengagement height above the feed nozzle. The aspect ratio (height-to-diameter, H / D H/D H / D ) of vertical vessels is typically designed to be between 3.0 and 4.0.
Pump Selection and Sizing
Pump sizing requires calculating the total dynamic head ( H p H_p H p ) that the pump must provide to move a liquid from a source vessel to a destination vessel: H p = ( z 2 − z 1 ) + P 2 − P 1 ρ g + h f + v 2 2 − v 1 2 2 g H_p = (z_2 - z_1) + \frac{P_2 - P_1}{\rho g} + h_f + \frac{v_2^2 - v_1^2}{2g} H p = ( z 2 − z 1 ) + ρ g P 2 − P 1 + h f + 2 g v 2 2 − v 1 2
where z z z is elevation, P P P is pressure, h f h_f h f is the sum of friction losses in the piping and fittings, and v v v is fluid velocity. The hydraulic power (or fluid power) transferred to the fluid is: P h y d = m ˙ g H p = Q ρ g H p = Q Δ P P_{hyd} = \dot{m} g H_p = Q \rho g H_p = Q \Delta P P h y d = m ˙ g H p = Qρ g H p = Q Δ P
The brake horsepower ( P b r a k e P_{brake} P b r ak e ), which is the shaft power required from the motor, accounts for pump efficiency ( η p \eta_p η p ): P b r a k e = P h y d η p P_{brake} = \frac{P_{hyd}}{\eta_p} P b r ak e = η p P h y d
To prevent cavitation (the formation and violent collapse of vapor bubbles at low-pressure regions inside the pump), the Net Positive Suction Head Available ( N P S H A NPSHA NPS H A ) at the pump inlet must exceed the Net Positive Suction Head Required ( N P S H R NPSHR NPS H R ) specified by the pump manufacturer: N P S H A = H s p + H s − H f − H v p NPSHA = H_{sp} + H_s - H_f - H_{vp} NPS H A = H s p + H s − H f − H v p
where:
H s p H_{sp} H s p is the absolute pressure head at the feed reservoir surface.
H s H_s H s is the static suction head (positive if the reservoir liquid level is above the pump centerline, negative if below).
H f H_f H f is the friction loss head in the suction line piping and fittings.
H v p H_{vp} H v p is the vapor pressure head of the liquid at the inlet temperature.
To avoid cavitation, the safety margin N P S H A − N P S H R ≥ 2 to 3 feet NPSHA - NPSHR \ge 2 \text{ to } 3 \text{ feet} NPS H A − NPS H R ≥ 2 to 3 feet (or ∼ 0.6 to 1.0 meter \sim 0.6 \text{ to } 1.0 \text{ meter} ∼ 0.6 to 1.0 meter ) is maintained.
Heat Exchanger Sizing and Fouling
Heat exchangers are sized using the design equation: Q = U A F Δ T l m Q = U A F \Delta T_{lm} Q = U A F Δ T l m
where:
Q Q Q is the heat transfer duty (W or Btu/hr).
U U U is the overall heat heat transfer coefficient (W/m²·K or Btu/hr·ft²·°F).
A A A is the heat transfer area (m² or ft²).
F F F is the configuration correction factor (equal to 1.0 for true countercurrent flow, and less than 1.0 for multi-pass shell-and-tube exchangers).
Δ T l m \Delta T_{lm} Δ T l m is the log-mean temperature difference: Δ T l m = ( T h , i n − T c , o u t ) − ( T h , o u t − T c , i n ) ln ( T h , i n − T c , o u t T h , o u t − T c , i n ) \Delta T_{lm} = \frac{(T_{h,in} - T_{c,out}) - (T_{h,out} - T_{c,in})}{\ln \left( \frac{T_{h,in} - T_{c,out}}{T_{h,out} - T_{c,in}} \right)} Δ T l m = ln ( T h , o u t − T c , in T h , in − T c , o u t ) ( T h , in − T c , o u t ) − ( T h , o u t − T c , in )
The overall heat transfer coefficient ( U U U ) changes over time due to fouling (deposition of dirt, scale, or chemical products on tube walls). The fouling factor (or fouling resistance, R f R_f R f ) is incorporated into the calculation of U U U based on the initial clean coefficient ( U c l e a n U_{clean} U c l e an ): 1 U d i r t y = 1 U c l e a n + R f o + R f i \frac{1}{U_{dirty}} = \frac{1}{U_{clean}} + R_{fo} + R_{fi} U d i r t y 1 = U c l e an 1 + R f o + R f i
where R f o R_{fo} R f o and R f i R_{fi} R f i are the outer and inner fouling resistances.
Equipment Cost Sizing and Capacity Scaling
When sizing a new piece of equipment, historical cost data can be scaled to estimate the purchased cost of a different capacity using the cost exponent method: C B = C A ( S B S A ) n C_B = C_A \left( \frac{S_B}{S_A} \right)^n C B = C A ( S A S B ) n
where C A C_A C A is the cost of equipment A A A with capacity S A S_A S A , C B C_B C B is the cost of equipment B B B with capacity S B S_B S B , and n n n is the cost exponent. If n n n is not specified, n = 0.6 n = 0.6 n = 0.6 is used (representing the six-tenths rule for economy of scale).
Inflation Scaling using Cost Indexes
To account for changes in the value of money over time, cost indexes are applied to adjust historical costs to current costs: C c u r r e n t = C h i s t o r i c a l ( I c u r r e n t I h i s t o r i c a l ) C_{current} = C_{historical} \left( \frac{I_{current}}{I_{historical}} \right) C c u rre n t = C hi s t or i c a l ( I hi s t or i c a l I c u rre n t )
where I I I represents a cost index, most commonly the Chemical Engineering Plant Cost Index (CEPCI).
Bare Module Cost Estimation
The bare module cost ( C B M C_{BM} C BM ) represents the total installed cost of a piece of equipment, including piping, instrumentation, structure, electrical, and installation labor. It is calculated from the base purchased cost ( C p 0 C_{p}^0 C p 0 under standard conditions: carbon steel and ambient pressure) using the bare module factor ( F B M F_{BM} F BM ): C B M = C p 0 F B M C_{BM} = C_{p}^0 F_{BM} C BM = C p 0 F BM
If the equipment operates under high pressure or requires specialized materials (e.g., stainless steel), pressure ( F P F_P F P ) and material ( F M F_M F M ) correction factors are applied to find the actual purchased cost ( C p C_p C p ): C p = C p 0 F P F M C_p = C_{p}^0 F_P F_M C p = C p 0 F P F M