Study guide
19.2 Six Sigma DMAIC Methodology and Quality Function Deployment
FE Industrial and Systems Study Guide Exam
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Exam Overview, CBT Strategy & Handbook Navigation
1.1 FE Industrial Exam Structure, CBT Logistics, and Pacing 1.2 Using the NCEES FE Reference Handbook and Approved Calculators
2 Chapter 2: Mathematics for Industrial Engineers
2.1 Analytic Geometry, Coordinate Systems, and Trigonometry 2.2 Calculus: Differential, Integral, and Series Approximations 2.3 Linear Algebra: Matrix Operations, Systems of Equations, and Vectors
3 Chapter 3: Engineering Sciences Core
3.1 Thermodynamics Fundamentals and Fluid Flow Principles 3.2 Statics, Dynamics, and Mechanics of Materials Core 3.3 Electrical Circuits, DC/AC Analysis, and Power in Industrial Systems
4 Chapter 4: Ethics and Professional Practice
4.1 NCEES Model Rules of Professional Conduct and Technical Society Ethics 4.2 Engineering Licensure, Public Welfare, and Professional Liability 4.3 Engineering Contracts, Intellectual Property, and Conflicts of Interest
5 Chapter 5: Engineering Economics
5.1 Time Value of Money, Discount Factors, and Equivalence 5.2 Evaluating Alternatives: Present Worth, Equivalent Annual Cost, and IRR 5.3 Incremental Rate of Return, Replacement Analysis, and Break-Even 5.4 Depreciation Methods, MACRS, Income Taxes, and Inflation
6 Chapter 6: Probability Foundations & Distributions
6.1 Basic Probability Concepts, Conditional Probability, and Bayes' Theorem 6.2 Discrete Probability Distributions 6.3 Continuous Probability Distributions
7 Chapter 7: Statistical Inference, Regression & Design of Experiments
7.1 Sampling Distributions, Central Limit Theorem, and Confidence Intervals 7.2 Hypothesis Testing: Means, Proportions, and Variances 7.3 Linear Regression, Correlation Analysis, and Design of Experiments (ANOVA)
8 Chapter 8: Data, Logic, Modeling & Linear Programming
8.1 Optimization Modeling: Decision Variables, Objectives, and Constraints 8.2 Linear Programming: Graphical Solutions and Simplex Fundamentals 8.3 Duality, Sensitivity Analysis, and Integer Linear Programming 8.4 Data, Logic Development, and Analytics
9 Chapter 9: Stochastic Models & Simulation
9.1 Queuing Theory: Little's Law, M/M/1, and Multi-Server Systems 9.2 Discrete-Time Markov Chains: Transition Matrices and Steady-State Probabilities 9.3 Discrete-Event Simulation Principles and Monte Carlo Modeling
10 Chapter 10: Engineering Management, Project Planning & Performance Measurement
10.1 Organizational Structure, Leadership, and Worker Motivation Theories 10.2 Project Management: WBS, Critical Path Method (CPM), PERT, and Crashing 10.3 Earned Value Management (EVM), Decision Trees, and Risk Preference 10.4 Performance Measurement: Productivity, KPIs, Wage Systems, and the Balanced Scorecard
11 Chapter 11: Manufacturing & Production Systems
11.1 Manufacturing Processes, Material Processing, and Tolerancing 11.2 Assembly Line Balancing, Takt Time, Cycle Time, and Throughput 11.3 Sustainable Manufacturing, Waste Minimization, and Life-Cycle Assessment
12 Chapter 12: Production Planning, Inventory Control & Sequencing
12.1 Demand Forecasting Methods and Forecast Error Tracking 12.2 Aggregate Planning, Master Production Scheduling (MPS), and MRP 12.3 Deterministic Inventory Models: EOQ, EPQ, and Safety Stock 12.4 Job Sequencing, Dispatching Rules, and Flow Shop Scheduling
13 Chapter 13: Lean Systems & Theory of Constraints
13.1 Lean Foundations: Value Stream Mapping, Seven Wastes, and 5S 13.2 Pull Systems, Kanban, Just-In-Time (JIT), and SMED Setup Reduction 13.3 Theory of Constraints: Bottleneck Identification and Drum-Buffer-Rope
14 Chapter 14: Facilities Planning & Material Handling
14.1 Facility Location Analysis: Qualitative Factor Rating and Centroid Method 14.2 Facility Layout Design and Flow Analysis 14.3 Material Handling Equipment, Warehousing, and AS/RS
15 Chapter 15: Supply Chain Design & Logistics
15.1 Supply Chain Network Architecture and Transportation Modes 15.2 Distribution Strategies, Cross-Docking, and Vehicle Routing 15.3 The Bullwhip Effect, Risk Pooling, and Supply Chain Coordination
16 Chapter 16: Human Factors & Cognitive Ergonomics
16.1 Cognitive Engineering, Human-Machine Interface, Displays, and Controls 16.2 Anthropometric Principles, Percentile Design, and Biomechanical Posture 16.3 Environmental Ergonomics: Industrial Noise, Lighting, and Heat Stress
17 Chapter 17: Physical Ergonomics & Workplace Safety
17.1 Physical Ergonomics: The NIOSH Manual Lifting Equation 17.2 Cumulative Trauma Disorders and Postural Assessment 17.3 Workplace Safety: OSHA Standards, Hazard Analysis, and Control Hierarchy
18 Chapter 18: Work Design & Measurement
18.1 Methods Engineering, Process Charting, and Principles of Motion Economy 18.2 Direct Stopwatch Time Study: Observed Time, Performance Rating, and Allowances 18.3 Predetermined Time Systems, Work Sampling, and Learning Curves
19 Chapter 19: Quality Management, Six Sigma & Analytical Tools
19.1 Quality Philosophies, Total Quality Management, and Cost of Quality 19.2 Six Sigma DMAIC Methodology and Quality Function Deployment 19.3 The Seven Basic Quality Tools, Root Cause Analysis, and Taguchi Loss Function
20 Chapter 20: Statistical Process Control
20.1 Statistical Process Control Principles, Variation, and Run Rules 20.2 Variable Control Charts: X-bar & R, X-bar & S, and Individual-Moving Range 20.3 Attribute Control Charts: Defectives (p, np) and Defects (c, u)
21 Chapter 21: Process Capability & Acceptance Sampling
21.1 Process Capability Indices and Defect Levels 21.2 Acceptance Sampling Concepts and Operating Characteristic Curves 21.3 Sampling Risks, AQL, LTPD, and Standard Sampling Plans
22 Chapter 22: Systems Engineering & Life-Cycle Management
22.1 The Systems Engineering V-Model, Stakeholder Requirements, and Functional Architecture 22.2 Configuration Management, Interface Control, and Verification & Validation 22.3 Life-Cycle Costing, Maintainability, and System Availability
23 Chapter 23: Reliability Engineering & Risk Analysis
23.1 Reliability Mathematics, Hazard Rates, and the Bathtub Curve 23.2 System Reliability Configurations: Series, Parallel, and k-out-of-n Systems 23.3 Failure Modes and Effects Analysis and Fault Tree Analysis
19.2 Six Sigma DMAIC Methodology and Quality Function Deployment
Key Takeaways Explain This Topic AI
Six Sigma defines statistical quality by establishing process specification limits at ±6 standard deviations (±6σ) from the process mean; incorporating an empirical long-term mean drift of 1.5σ, a Six Sigma process generates at most 3.4 Defects Per Million Opportunities (DPMO).
The Six Sigma organizational hierarchy establishes distinct functional roles: Champions/Process Owners (strategic project selection and resource provisioning), Master Black Belts (methodological mentoring and enterprise training), Black Belts (full-time project execution and advanced statistical analytics), and Green Belts (part-time project leads within functional areas).
The DMAIC methodology executes quality improvement through five disciplined phases: Define (Project Charter, VOC, CTQ Tree, SIPOC), Measure (Process Mapping, Gage R&R, baseline capability), Analyze (Root Cause Analysis, ANOVA, regression), Improve (DOE, FMEA, Poka-Yoke, piloting), and Control (SPC control charts, SOPs, control plans).
Design for Six Sigma (DFSS) using the DMADV framework (Define-Measure-Analyze-Design-Verify) is applied when engineering new products/processes or when an existing process exhibits an inherent capability bottleneck that cannot be resolved through incremental DMAIC.
Quality Function Deployment (QFD) utilizes the House of Quality (HoQ) matrix to translate customer requirements (WHATs) into prioritized engineering parameters (HOWs) while resolving technical trade-offs across the correlation roof.
Last updated: September 2026
Pioneered by Bill Smith and Bob Galvin at Motorola in the mid-1980s and popularized across global manufacturing by Jack Welch at General Electric, Six Sigma is a disciplined, data-driven methodology that combines advanced statistical analytics with structured project management to eliminate defects, drive down process variation, and maximize operational profitability.
1. Six Sigma Statistical Foundations and the 1.5 σ 1.5\sigma 1.5 σ Shift
To understand Six Sigma on the FE exam, engineers must distinguish between theoretical short-term capability and empirical long-term performance. Six Sigma Distribution with 1.5σ Shift
- Centered Mean
- (μ_0)
- │
- Shifted Mean │
- (μ_s) │
- │ │
- ▼ ▼
- ┌─┐
- / \ │
- / \ │
- / │ \ │
- / │ \ │
- _/ │ \_│_
- ─────────/───────┼───────\───┬───────────────────►
- LSL USL │
- │
- ◄──────── 4.5σ ──────►
- (Shifted distance to nearest limit)
- The Normal Distribution Derivation
Assume a quality characteristic Y Y Y is normally distributed with mean μ \mu μ and standard deviation σ \sigma σ , bounded by Upper and Lower Specification Limits ( U S L USL U S L and L S L LSL L S L ):
Theoretical Centered Process : If the process mean is centered exactly halfway between specification limits placed at μ ± 6 σ \mu \pm 6\sigma μ ± 6 σ (so U S L − μ = 6 σ USL - \mu = 6\sigma U S L − μ = 6 σ and μ − L S L = 6 σ \mu - LSL = 6\sigma μ − L S L = 6 σ ), the probability of producing a defective part falling outside the specification limits is: P ( Defect ) = 2 × [ 1 − Φ ( 6.0 ) ] ≈ 2 × ( 9.866 × 10 − 10 ) = 1.973 × 10 − 9 P(\text{Defect}) = 2 \times \left[ 1 - \Phi(6.0) \right] \approx 2 \times (9.866 \times 10^{-10}) = 1.973 \times 10^{-9} P ( Defect ) = 2 × [ 1 − Φ ( 6.0 ) ] ≈ 2 × ( 9.866 × 1 0 − 10 ) = 1.973 × 1 0 − 9 This corresponds to approximately 2 parts per billion , i.e. 0.002 Defects Per Million Opportunities .
The Empirical Long-Term 1.5 σ 1.5\sigma 1.5 σ Shift : In real-world industrial environments, processes do not remain permanently centered. Ambient temperature swings, lot-to-lot raw material variations, machine tool wear, hydraulic viscosity changes, and operator shifts cause the process mean to drift over time. Empirical studies across manufacturing operations conducted by Motorola revealed that over the long term, process means exhibit an average drift of approximately 1.5 σ 1.5\sigma 1.5 σ .
The Long-Term Six Sigma Standard : When the mean drifts by 1.5 σ 1.5\sigma 1.5 σ toward a specification limit, the distance from the shifted mean to the nearest specification limit drops from 6 σ 6\sigma 6 σ to: Z nearest = 6.0 σ − 1.5 σ = 4.5 σ Z_{\text{nearest}} = 6.0\sigma - 1.5\sigma = 4.5\sigma Z nearest = 6.0 σ − 1.5 σ = 4.5 σ Evaluating the standard normal tail probability at Z = 4.5 Z = 4.5 Z = 4.5 : P ( Z > 4.5 ) = 1 − Φ ( 4.5 ) ≈ 3.3976 × 10 − 6 ≈ 3.4 × 10 − 6 P(Z > 4.5) = 1 - \Phi(4.5) \approx 3.3976 \times 10^{-6} \approx 3.4 \times 10^{-6} P ( Z > 4.5 ) = 1 − Φ ( 4.5 ) ≈ 3.3976 × 1 0 − 6 ≈ 3.4 × 1 0 − 6 Multiplying by 10 6 10^6 1 0 6 yields the universal benchmark of Six Sigma quality: 3.4 Defects Per Million Opportunities (DPMO) .
Fundamental Defect Metrics
Industrial engineers monitor Six Sigma quality using three core metrics:
Defects per Unit ( D P U DPU D P U ) : The average number of defects observed per unit inspected: D P U = D U DPU = \frac{D}{U} D P U = U D where D D D is the total count of defects discovered, and U U U is the total number of units sampled.
Total Opportunities ( T O P TOP TOP ) : The cumulative number of defect opportunities across the entire sample: T O P = U × O TOP = U \times O TOP = U × O where O O O is the number of distinct Critical-to-Quality (CTQ) defect opportunities present on a single unit.
Defects Per Million Opportunities ( D P M O DPMO D PMO ) : D P M O = D U × O × 10 6 = D P U O × 10 6 DPMO = \frac{D}{U \times O} \times 10^6 = \frac{DPU}{O} \times 10^6 D PMO = U × O D × 1 0 6 = O D P U × 1 0 6
Sigma Level ( Z short-term Z_{\text{short-term}} Z short-term ) Distance to Nearest Spec ( Z long-term Z_{\text{long-term}} Z long-term ) Long-Term DPMO (with 1.5σ Shift) Equivalent Process Yield
- 2 σ 2\sigma 2 σ 0.5 σ 0.5\sigma 0.5 σ 308,537 69.146%
- 3 σ 3\sigma 3 σ 1.5 σ 1.5\sigma 1.5 σ 66,807 93.319%
- 4 σ 4\sigma 4 σ 2.5 σ 2.5\sigma 2.5 σ 6,210 99.379%
- 5 σ 5\sigma 5 σ 3.5 σ 3.5\sigma 3.5 σ 233 99.977%
- 6 σ 6\sigma 6 σ 4.5 σ 4.5\sigma 4.5 σ 3.4 99.99966%
- 2. Six Sigma Organizational Governance and Belt Hierarchy
Six Sigma institutionalizes quality improvement by embedding dedicated, trained practitioners across defined organizational tiers: Six Sigma Organizational Belt Architecture
- ┌────────────────────────┐
- │ Executive Leadership │ (Strategic vision & resource sponsor)
- └───────────┬────────────┘
- ▼
- ┌────────────────────────┐
- │ Champion / Owner │ (Business unit head; removes roadblocks)
- └───────────┬────────────┘
- ▼
- ┌────────────────────────┐
- │ Master Black Belt │ (Enterprise methodology expert & coach)
- └───────────┬────────────┘
- ▼
- ┌────────────────────────┐
- │ Black Belt │ (Full-time team leader & statistical analyst)
- └───────────┬────────────┘
- ▼
- ┌────────────────────────┐
- │ Green Belt │ (Part-time departmental project execution)
- └───────────┬────────────┘
- ▼
- ┌────────────────────────┐
- │ Yellow / White Belts │ (Shop-floor contributors & data collectors)
- └────────────────────────┘
Executive Leadership / Sponsors : Senior executive officers who establish enterprise strategic quality objectives, allocate capital, and hold business unit leaders accountable for results.
Champions / Process Owners : Business unit directors who "own" the operating process. Champions define project boundaries, select Black Belts, approve project charters, secure resources, and eliminate organizational roadblocks across functional departments.
Master Black Belts (MBBs) : Elite technical experts who serve as full-time internal consultants, mentors, and instructors. MBBs advise executive leadership, train Black and Green Belts, and ensure statistical rigor across the enterprise portfolio.
Black Belts (BBs) : Dedicated, full-time project leaders who execute high-impact strategic DMAIC projects (typically targeting $100,000+ in annual financial savings). Black Belts mentor Green Belts and possess mastery of statistical techniques including Design of Experiments (DOE), multivariate regression, and non-parametric hypothesis testing.
Green Belts (GBs) : Part-time quality practitioners who lead localized departmental improvement projects while retaining their normal operational job duties (e.g., manufacturing engineers, maintenance supervisors).
Yellow Belts / White Belts : Operations personnel, technicians, and operators trained in baseline Six Sigma concepts, visual controls, 5S, and data collection protocols who serve as team members on DMAIC projects.
3. The DMAIC Roadmap in Depth
DMAIC (Define, Measure, Analyze, Improve, Control) is the closed-loop, five-phase problem-solving architecture applied to stabilize and optimize existing defective processes. The DMAIC Project Pipeline
- ┌──────────────┐ ┌──────────────┐ ┌──────────────┐ ┌──────────────┐ ┌──────────────┐
- │ Define │──►│ Measure │──►│ Analyze │──►│ Improve │──►│ Control │
- └──────────────┘ └──────────────┘ └──────────────┘ └──────────────┘ └──────────────┘
- Project - Value Stream - Root Cause - Design of Exp. - SPC Control
- Charter Mapping (Fishbone/5Why) (DOE Factorials) Charts
- VOC to CTQ - Gage R&R (MSA) - Hypothesis Tests - FMEA (RPN) - Standard SOPs
- SIPOC Macro - Baseline C_pk (t, ANOVA, χ²) - Poka-Yoke Fixture- Control Plan
- Diagram & Sigma Level - Regression - Pilot Trials - Hand-off
- Phase 1: Define
The objective is to establish project scope, identify customer requirements, and formulate the business case.
Project Charter : The contractual document bounding the project, containing:
Problem Statement : Quantifies the historical baseline metric, the performance gap, and the timeline without presuming root cause (e.g., "During Q1-Q3 2026, Line 4 scrap averaged 4.8%, resulting in an annualized loss of $340,000").
Business Case : Connects the project to corporate financial and strategic imperatives.
Goal Statement : SMART objective (e.g., "Reduce Line 4 scrap from 4.8% to under 1.5% by November 15, 2026, generating $230,000 in net savings").
Project Scope : Explicit boundaries identifying what is In-Scope and Out-of-Scope.
Voice of the Customer (VOC) and CTQ Tree : VOC captures qualitative, subjective customer feedback (e.g., "The hydraulic pump is too noisy"). The Critical to Quality (CTQ) Tree decomposes broad customer needs into measurable, specific engineering parameters with numerical tolerances (e.g., "Acoustic output ≤ 68 dBA \le 68\text{ dBA} ≤ 68 dBA at 1 meter under full hydraulic load").
SIPOC Diagram : A high-level process map bounding the system into five macro elements:
S uppliers → \to → I nputs → \to → P rocess (4 to 7 macro steps) → \to → O utputs → \to → C ustomers.
Phase 2: Measure
The objective is to quantify the current process baseline and validate the integrity of the measurement data.
Detailed Process Mapping : Deployment swimlane flowcharts identifying decision gates, queues, and operator handoffs.
Measurement System Analysis (MSA) / Gage R&R :
Before drawing conclusions from process data, engineers must verify that measurement error does not obscure true part variation. Total observed process variance ( σ total 2 \sigma^2_{\text{total}} σ total 2 ) decomposes into: σ total 2 = σ part-to-part 2 + σ measurement 2 \sigma^2_{\text{total}} = \sigma^2_{\text{part-to-part}} + \sigma^2_{\text{measurement}} σ total 2 = σ part-to-part 2 + σ measurement 2 σ measurement 2 = σ repeatability 2 + σ reproducibility 2 \sigma^2_{\text{measurement}} = \sigma^2_{\text{repeatability}} + \sigma^2_{\text{reproducibility}} σ measurement 2 = σ repeatability 2 + σ reproducibility 2
Repeatability (Equipment Variation, EV) : Variation observed when one appraiser measures the same identical part multiple times using the same gage.
Reproducibility (Appraiser Variation, AV) : Variation observed when different appraisers measure the same part using the same gage.
Gage R&R Acceptance Thresholds (%GRR) :
% G R R < 10 % \%GRR < 10\% % GRR < 10% : Excellent measurement system; fully acceptable.
10 % ≤ % G R R ≤ 30 % 10\% \le \%GRR \le 30\% 10% ≤ % GRR ≤ 30% : Marginally acceptable depending on application criticality and replacement cost.
% G R R > 30 % \%GRR > 30\% % GRR > 30% : Unacceptable; the measurement system must be recalibrated, redesigned, or fixtured before collecting process capability data.
Baseline Capability Assessment : Calculating C p C_p C p , C p k C_{pk} C p k , P p P_p P p , P p k P_{pk} P p k , and initial Z Z Z -bench baseline metrics.
Phase 3: Analyze
The objective is to identify, isolate, and statistically verify the vital few root causes ( X X X s) that govern process performance ( Y = f ( X 1 , X 2 , … , X k ) Y = f(X_1, X_2, \dots, X_k) Y = f ( X 1 , X 2 , … , X k ) ).
Root Cause Identification : Brainstorming potential causes using Ishikawa (Fishbone) diagrams and the 5 Whys technique.
Statistical Hypothesis Testing :
Comparing Two Means : Two-sample independent t t t -test or paired t t t -test.
Comparing Three or More Means : One-Way or Two-Way Analysis of Variance (ANOVA) using the F F F -test.
Categorical / Attribute Data : Chi-Square ( χ 2 \chi^2 χ 2 ) test for independence or goodness-of-fit.
Correlation and Multiple Linear Regression : Modeling the continuous mathematical relationship between process inputs (e.g., cutting temperature, feed rate) and the CTQ output.
Phase 4: Improve
The objective is to formulate, screen, optimize, and pilot breakthrough solutions.
Design of Experiments (DOE) : Full factorial ( 2 k 2^k 2 k ) or fractional factorial ( 2 k − p 2^{k-p} 2 k − p ) experimental designs that systematically manipulate input variables to quantify main effects and multi-factor interactions while minimizing experimental trial count.
Failure Modes and Effects Analysis (FMEA) : A structured engineering risk assessment tool that identifies potential failure mechanisms and calculates the Risk Priority Number (RPN) : R P N = Severity ( S ) × Occurrence ( O ) × Detection ( D ) RPN = \text{Severity } (S) \times \text{Occurrence } (O) \times \text{Detection } (D) RPN = Severity ( S ) × Occurrence ( O ) × Detection ( D ) where S S S , O O O , and D D D are scored on 1-to-10 integer scales ( 1 ≤ R P N ≤ 1 , 000 1 \le RPN \le 1,000 1 ≤ RPN ≤ 1 , 000 ). High RPN items mandate immediate engineering redesign, error-proofing, or detection enhancement.
Poka-Yoke Fixturing : Designing mechanical interlocks, asymmetric locating pins, and optical proximity sensors to make human operational error physically impossible.
Pilot Implementation : Executing a limited trial run to validate projected gains and verify that no unintended side-effects occur.
Phase 5: Control
The objective is to institutionalize improvements, update standards, and ensure sustained capability.
Statistical Process Control (SPC) : Deploying real-time variable control charts ( X ˉ − R \bar{X}-R X ˉ − R , X ˉ − s \bar{X}-s X ˉ − s ) or attribute control charts ( p p p , n p np n p , c c c , u u u ) on shop-floor terminals to detect special cause variation.
Standard Operating Procedures (SOPs) : Documenting validated work steps, tooling offsets, and preventative maintenance schedules.
Process Control Plan : A master document detailing measurement frequencies, sample sizes, control methods, and specific reaction plans (out-of-control action plans, OCAP) if an alarm triggers.
Formal Project Handoff : Securing executive sign-off and transferring operational accountability from the Black Belt to the designated Champion / Process Owner.
4. Design for Six Sigma (DFSS) and the DMADV Framework
While DMAIC focuses on incremental optimization of existing, operational processes, Design for Six Sigma (DFSS) is deployed to engineer brand-new products, services, or manufacturing processes from scratch. DMAIC vs. DMADV Decision Architecture
- Operating Process Problem
- │
Is the process currently operating?
- / \
- Yes / \ No ──► Deploy DMADV (DFSS)
- / \
- Can the process reach
- target capability (C_pk ≥ 1.5)
via incremental parameter tuning?
- / \
- Yes / \ No ──► Deploy DMADV (Re-architect system)
- / \
- ▼ ▼
- Deploy DMAIC Deploy DMADV
DFSS is governed by the DMADV roadmap:
Define : Establish customer requirements, product vision, and strategic business goals.
Measure : Identify customer CTQs, benchmark competitor capabilities, and assess technical risks.
Analyze : Formulate innovative conceptual design architectures, evaluate design alternatives using decision matrices (Pugh Concept Selection), and model preliminary transfer functions.
Design : Develop detailed engineering specifications, optimize component tolerances, conduct robust parameter design (Taguchi methods), and simulate performance using finite element analysis (FEA).
Verify : Fabricate physical prototypes, conduct pilot production runs, validate Six Sigma capability under operational extremes, and hand off to full-scale manufacturing.
5. Quality Function Deployment (QFD) and the House of Quality
Developed by Yoji Akao in 1966 at Mitsubishi's Kobe Shipyard, Quality Function Deployment (QFD) is a structured product development methodology that translates qualitative customer demands into quantitative engineering characteristics.
The foundational graphical tool of QFD is the House of Quality (HoQ) : The House of Quality (HoQ)
- ┌───────────────┐
- │ 4. Roof: │ (Interrelationships
- │ Correlation │ between HOWs: ++, +, -, --)
- │ Matrix │
- └───┬───────┬───┘
- │ │
- ┌────────────┴───────┴────────────┐
- │ 2. Technical Characteristics │ (Direction of
- │ (HOWs: Engineering Specs) │ improvement: ▲, ▼, ⊙)
- ┌───────────────────┼─────────────────────────────────┼───────────────────┐
- │ 1. Customer │ 3. Interrelationship Matrix │ 5. Competitive │
- │ Requirements │ │ Assessment │
- │ (WHATs: Voice │ ● = Strong (9) │ (Benchmarking │
- │ of Customer) │ ○ = Moderate (3) │ 1 to 5 scale) │
- │ Customer │ ▲ = Weak (1) │ │
- │ Importance │ │ │
- │ Weights (w_i) │ │ │
- └───────────────────┴─────────────────────────────────┴───────────────────┘
- │ 6. Basement: Technical Targets │
- │ - Absolute Weight (W_j) │
- │ - Relative Weight (%) │
- │ - Engineering Target Values │
- └─────────────────────────────────┘
- Anatomy of the House of Quality
Customer Requirements (WHATs) : The left vertical wall lists customer expectations captured via VOC interviews, focus groups, and surveys. Each requirement is assigned a Customer Importance Weight ( w i w_i w i ), typically on a 1-to-5 or 1-to-10 scale.
Technical Characteristics (HOWs) : The second-story ceiling lists measurable engineering parameters under direct engineering design control. Each characteristic includes a direction of optimization:
- ↑ \uparrow ↑ (Maximize: e.g., tensile strength, battery life)
- ↓ \downarrow ↓ (Minimize: e.g., acoustic noise, curb weight, vibration)
- ⊙ \odot ⊙ (Target: e.g., nominal hydraulic line pressure, shut height)
Interrelationship Matrix : The central room links WHATs to HOWs using standard standardized numerical scoring conventions:
Strong Relationship : Weight R i j = 9 \text{Weight } R_{ij} = 9 Weight R ij = 9 (often symbolized by a solid circle ∙ \bullet ∙ )
Moderate Relationship : Weight R i j = 3 \text{Weight } R_{ij} = 3 Weight R ij = 3 (symbolized by an open circle ∘ \circ ∘ )
Weak Relationship : Weight R i j = 1 \text{Weight } R_{ij} = 1 Weight R ij = 1 (symbolized by an open triangle △ \triangle △ )
No Relationship : Weight R i j = 0 \text{Weight } R_{ij} = 0 Weight R ij = 0 (blank cell)
Correlation Roof : The triangular roof models technical trade-offs between engineering characteristics. It highlights synergies (positive correlations + + + , where improving Characteristic A also improves Characteristic B) and engineering conflicts (negative correlations − - − , where improving Characteristic A degrades Characteristic B, such as increasing armor plating thickness degrading fuel economy).
Competitive Assessment : The right wing benchmarks the firm's current product against primary marketplace competitors across each customer requirement.
Basement (Technical Priorities & Targets) : Industrial engineers calculate the Absolute Technical Importance Weight ( W j W_j W j ) for each engineering characteristic j j j : W j = ∑ i = 1 m w i ⋅ R i j W_j = \sum_{i=1}^m w_i \cdot R_{ij} W j = i = 1 ∑ m w i ⋅ R ij where w i w_i w i is the importance weight of customer requirement i i i , and R i j R_{ij} R ij is the relationship score between requirement i i i and engineering characteristic j j j . The Relative Percentage Weight ( RPW j \text{RPW}_j RPW j ) is: RPW j = W j ∑ k = 1 n W k × 100 % \text{RPW}_j = \frac{W_j}{\sum_{k=1}^n W_k} \times 100\% RPW j = ∑ k = 1 n W k W j × 100%
- 6. Step-by-Step Worked Engineering Calculations
- Worked Example 19.2.1: Six Sigma Defect Metrics and House of Quality Prioritization
Problem Statement : Part 1 : An automated printed circuit board (PCB) assembly facility manufactures 25,000 control boards for an avionics supplier. Quality engineers define five Critical-to-Quality (CTQ) defect opportunities per board: (1) solder bridging, (2) missing component, (3) reversed component polarity, (4) dry solder joint, and (5) board delamination. Following automated optical inspection and functional electrical testing, inspectors record a total of 45 defects across the entire lot.
Calculate Defects per Unit ( D P U DPU D P U ).
Compute Total Opportunities ( T O P TOP TOP ).
Calculate Defects Per Million Opportunities ( D P M O DPMO D PMO ).
Determine the approximate long-term sigma level of the assembly process.
Part 2 : The avionics engineering team builds a House of Quality (HoQ) matrix to prioritize redesign efforts for the flight computer enclosure. Customer requirements, importance weights ( w i w_i w i ), and relationship scores ( R i j R_{ij} R ij ) across three engineering characteristics are tabulated below (using the standard 9-3-1 scoring rule):
Customer Requirement (WHAT) Importance ( w i w_i w i ) Characteristic 1: Wall Thickness ( R i 1 R_{i1} R i 1 ) Characteristic 2: Heat Sink Area ( R i 2 R_{i2} R i 2 ) Characteristic 3: Internal Fan Airflow ( R i 3 R_{i3} R i 3 )
- High Impact Durability 5 Strong (9) None (0) None (0)
- Low Internal Operating Temp 4 Weak (1) Strong (9) Strong (9)
- Low Acoustic Noise 3 None (0) Moderate (3) Strong (9)
Compute the absolute technical importance score ( W j W_j W j ) and relative percentage weight ( RPW j \text{RPW}_j RPW j ) for all three engineering characteristics.
Solution :
Part 1: Six Sigma Defect Analytics
Step 1: Calculate Defects per Unit ( D P U DPU D P U ) : D P U = D U = 45 defects 25 , 000 units = 0.0018 defects/unit DPU = \frac{D}{U} = \frac{45\text{ defects}}{25,000\text{ units}} = 0.0018\text{ defects/unit} D P U = U D = 25 , 000 units 45 defects = 0.0018 defects/unit
Step 2: Calculate Total Opportunities ( T O P TOP TOP ) : T O P = U × O = 25 , 000 units × 5 opportunities/unit = 125 , 000 opportunities TOP = U \times O = 25,000\text{ units} \times 5\text{ opportunities/unit} = 125,000\text{ opportunities} TOP = U × O = 25 , 000 units × 5 opportunities/unit = 125 , 000 opportunities
Step 3: Calculate Defects Per Million Opportunities ( D P M O DPMO D PMO ) : D P M O = D T O P × 10 6 = 45 125 , 000 × 1 , 000 , 000 = 0.00036 × 1 , 000 , 000 = 360 DPMO DPMO = \frac{D}{TOP} \times 10^6 = \frac{45}{125,000} \times 1,000,000 = 0.00036 \times 1,000,000 = 360\text{ DPMO} D PMO = TOP D × 1 0 6 = 125 , 000 45 × 1 , 000 , 000 = 0.00036 × 1 , 000 , 000 = 360 DPMO
Step 4: Determine Sigma Level :
Referencing standard Six Sigma conversion tables (with the standard 1.5 σ 1.5\sigma 1.5 σ shift):
- 4.5 σ → 1 , 350 DPMO 4.5\sigma \to 1,350\text{ DPMO} 4.5 σ → 1 , 350 DPMO
- 4.87 σ → 360 DPMO 4.87\sigma \to 360\text{ DPMO} 4.87 σ → 360 DPMO
5.0 σ → 233 DPMO 5.0\sigma \to 233\text{ DPMO} 5.0 σ → 233 DPMO The PCB assembly line operates at approximately 4.87 σ 4.87\sigma 4.87 σ , performing well above four-sigma capability ( 6 , 210 DPMO 6,210\text{ DPMO} 6 , 210 DPMO ) but slightly short of world-class five-sigma capability.
Part 2: House of Quality Scoring Calculations
Step 1: Absolute Importance for Characteristic 1 (Wall Thickness, W 1 W_1 W 1 ) : W 1 = ( w 1 ⋅ R 11 ) + ( w 2 ⋅ R 21 ) + ( w 3 ⋅ R 31 ) W_1 = (w_1 \cdot R_{11}) + (w_2 \cdot R_{21}) + (w_3 \cdot R_{31}) W 1 = ( w 1 ⋅ R 11 ) + ( w 2 ⋅ R 21 ) + ( w 3 ⋅ R 31 ) W 1 = ( 5 × 9 ) + ( 4 × 1 ) + ( 3 × 0 ) = 45 + 4 + 0 = 49 W_1 = (5 \times 9) + (4 \times 1) + (3 \times 0) = 45 + 4 + 0 = 49 W 1 = ( 5 × 9 ) + ( 4 × 1 ) + ( 3 × 0 ) = 45 + 4 + 0 = 49
Step 2: Absolute Importance for Characteristic 2 (Heat Sink Area, W 2 W_2 W 2 ) : W 2 = ( w 1 ⋅ R 12 ) + ( w 2 ⋅ R 22 ) + ( w 3 ⋅ R 32 ) W_2 = (w_1 \cdot R_{12}) + (w_2 \cdot R_{22}) + (w_3 \cdot R_{32}) W 2 = ( w 1 ⋅ R 12 ) + ( w 2 ⋅ R 22 ) + ( w 3 ⋅ R 32 ) W 2 = ( 5 × 0 ) + ( 4 × 9 ) + ( 3 × 3 ) = 0 + 36 + 9 = 45 W_2 = (5 \times 0) + (4 \times 9) + (3 \times 3) = 0 + 36 + 9 = 45 W 2 = ( 5 × 0 ) + ( 4 × 9 ) + ( 3 × 3 ) = 0 + 36 + 9 = 45
Step 3: Absolute Importance for Characteristic 3 (Internal Fan Airflow, W 3 W_3 W 3 ) : W 3 = ( w 1 ⋅ R 13 ) + ( w 2 ⋅ R 23 ) + ( w 3 ⋅ R 33 ) W_3 = (w_1 \cdot R_{13}) + (w_2 \cdot R_{23}) + (w_3 \cdot R_{33}) W 3 = ( w 1 ⋅ R 13 ) + ( w 2 ⋅ R 23 ) + ( w 3 ⋅ R 33 ) W 3 = ( 5 × 0 ) + ( 4 × 9 ) + ( 3 × 9 ) = 0 + 36 + 27 = 63 W_3 = (5 \times 0) + (4 \times 9) + (3 \times 9) = 0 + 36 + 27 = 63 W 3 = ( 5 × 0 ) + ( 4 × 9 ) + ( 3 × 9 ) = 0 + 36 + 27 = 63
Step 4: Calculate Sum of Absolute Weights and Relative Percentages : W sum = W 1 + W 2 + W 3 = 49 + 45 + 63 = 157 W_{\text{sum}} = W_1 + W_2 + W_3 = 49 + 45 + 63 = 157 W sum = W 1 + W 2 + W 3 = 49 + 45 + 63 = 157 RPW 1 ( Wall Thickness ) = 49 157 × 100 % = 31.21 % \text{RPW}_1 (\text{Wall Thickness}) = \frac{49}{157} \times 100\% = 31.21\% RPW 1 ( Wall Thickness ) = 157 49 × 100% = 31.21% RPW 2 ( Heat Sink Area ) = 45 157 × 100 % = 28.66 % \text{RPW}_2 (\text{Heat Sink Area}) = \frac{45}{157} \times 100\% = 28.66\% RPW 2 ( Heat Sink Area ) = 157 45 × 100% = 28.66% RPW 3 ( Fan Airflow ) = 63 157 × 100 % = 40.13 % \text{RPW}_3 (\text{Fan Airflow}) = \frac{63}{157} \times 100\% = 40.13\% RPW 3 ( Fan Airflow ) = 157 63 × 100% = 40.13%
Engineering Conclusion : Internal Fan Airflow ranks as the highest technical priority (40.13%), heavily influencing both internal operating temperature and acoustic emissions.
7. NCEES Reference Handbook Tips & Realistic Exam Traps
The 1.5 σ 1.5\sigma 1.5 σ Shift Confusion : On the FE exam, questions may ask for the DPMO of a centered Six Sigma process versus a shifted Six Sigma process. Remember: 3.4 DPMO assumes the long-term 1.5 σ 1.5\sigma 1.5 σ shift ( Z = 4.5 Z = 4.5 Z = 4.5 ). A perfectly centered Six Sigma process ( Z = 6.0 Z = 6.0 Z = 6.0 ) produces a negligible 0.002 parts per billion (0.002 DPMO).
DPMO Denominator Trap : Never divide defects by units alone! If 10 defects are found in 1,000 units, the defect rate is not 10 / 1 , 000 × 10 6 10/1,000 \times 10^6 10/1 , 000 × 1 0 6 . You must multiply the number of units by the number of defect opportunities per unit ( O O O ): Correct: D P M O = D U × O × 10 6 \text{Correct: } DPMO = \frac{D}{U \times O} \times 10^6 Correct: D PMO = U × O D × 1 0 6
DMAIC vs. DMADV Selection : If an exam prompt describes designing a new product, introducing an unprecedented service, or completely re-engineering an obsolete assembly line that cannot meet customer specs through parameter adjustment, the correct answer is DMADV (DFSS) . If the prompt describes reducing scrap or cycle time on an existing active production line, choose DMAIC .
Gage R&R Percentage Criteria : Memorize the three ASQ/AIAG thresholds:
- < 10 % < 10\% < 10% = Acceptable
- 10 % to 30 % 10\% \text{ to } 30\% 10% to 30% = Marginally acceptable
- > 30 % > 30\% > 30% = Unacceptable (data cannot be trusted for process capability studies)
QFD Relationship Values : The standard convention for House of Quality cell scores is 9 (Strong), 3 (Moderate), and 1 (Weak) . Do not assume a linear 3-2-1 scale unless explicitly stated in the exam problem.