6.3 Bidding Procedures & Surety Bonds
Florida General Contractor Study Guide Exam
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Florida Licensing Law & Business Organization
1.1 DBPR, CILB & Licensing Classifications 1.2 Business Structures & Qualifying Agent Duties 1.3 Tax Laws, Payroll & Business Insurance 1.4 Florida Workers' Compensation Law 1.5 Financial Management & WIP Accounting 1.6 Business Planning, Outsourced Services & Professional Advisors 1.7 Human Resources Management 1.8 Equipment, Tools & Inventory Management
2 Chapter 2: Florida Construction Contracts & Lien Law
2.1 Florida Construction Contract Law & AIA Documents 2.2 Subcontractor Management & Procurement 2.3 Construction Change Orders, RFIs & Claims 2.4 Florida Construction Lien Law Fundamentals 2.5 Lien Enforcement, Transfers, Releases & Final Affidavits 2.6 Payment Applications, Draw Schedules & Schedule of Values
3 Chapter 3: Florida Building Code & Structural Systems
3.1 Florida Building Code Overview & Administration 3.2 Foundations, Excavation & Site Preparation 3.3 Concrete & Masonry Construction Standards 3.4 Structural Steel & Wood Framing 3.5 Building Envelope, Roofing & Waterproofing 3.6 Innovative Construction Techniques
4 Chapter 4: Construction Project Management & Scheduling
4.1 Construction Scheduling & Critical Path Method 4.2 Project Submittals, Shop Drawings & Document Control 4.3 Quality Control, Inspections & Certificate of Occupancy 4.4 Environmental Compliance & Stormwater Permitting 4.5 Sustainable Construction & LEED Coordination 4.6 Construction Plan Reading, Specifications & Engineering Math
5 Chapter 5: Jobsite Safety & OSHA Construction Standards
5.1 OSHA 29 CFR 1926 & Multi-Employer Worksite Policy 5.2 Fall Protection, Scaffolding & Ladder Safety 5.3 Excavation, Trenching & Heavy Equipment Safety 5.4 Hazard Communication, Electrical Safety & PPE
6 Chapter 6: Estimating, Bidding & Building Standards
6.1 Quantity Takeoff & Material Estimating 6.2 Cost Estimating, Overhead Allocation & Profit Markup 6.3 Bidding Procedures & Surety Bonds 6.4 Florida Energy Conservation & Accessibility Codes
6.3 Bidding Procedures & Surety Bonds
Key Takeaways Explain This Topic AI
Public bidding requires competitive solicitation with formal sealed bids awarded to the lowest responsive and responsible bidder.
Addenda issued during bidding modify original plans or specifications and must be formally acknowledged on bid submission forms to avoid disqualification.
Surety bonds involve a three-party legal contract (Principal, Obligee, Surety), distinct from two-party insurance policies, backed by full contractor indemnity.
Bid bonds (5%-10%) guarantee that the low bidder will execute the contract, while Performance (100%) and Payment (100%) bonds guarantee project completion and vendor payment.
Under Florida's Little Miller Act (F.S. 255.05), subcontractors not in privity must serve a written Notice to Contractor within 45 days of starting work to preserve bond claims.
Last updated: July 2026
Bidding Procedures & Surety Bonds
Public and private construction procurement relies on formal bidding procedures to establish project pricing and select contractors. Additionally, project owners—especially public entity owners—require Surety Bonds to guarantee performance and protect subcontractors against financial default.
1. Public vs. Private Bidding Procedures
Construction bidding is governed by formal protocols designed to ensure fair competition and fiscal integrity.
Key Bidding Steps & Terminology
Invitation for Bids (IFB) / Request for Proposals (RFP) : Public advertisements or private notices specifying project scope, instructions, pre-qualification requirements, and bid submission deadlines.
Pre-Bid Conference & Site Walkthrough : Mandatory or optional meetings where potential bidders inspect jobsite conditions and submit requests for clarification.
Addenda : Written legal instruments issued by the owner or architect during the bidding period that modify, clarify, or extend project contract documents. All addenda must be explicitly acknowledged on the bid form. Failure to acknowledge an addendum makes the bid non-responsive and subject to automatic rejection. BID SELECTION EVALUATION
- |
- +--------------------------+--------------------------+
- | |
- RESPONSIVE BIDDER RESPONSIBLE BIDDER
- Submitted on time • Financial capacity & net worth
- Completed all bid form fields • Adequate bonding capacity
- Acknowledged all addenda • Technical experience & licensing
- Included valid bid security • Satisfactory safety record (EMR)
- Award Criteria
Public agency contracts in Florida (under F.S. 255.20) must generally be awarded to the lowest responsive and responsible bidder :
Responsive Bidder : A contractor whose bid complies fully with all material terms of the solicitation documents.
Responsible Bidder : A contractor who possesses the financial capability, technical competence, equipment, bonding capacity, and integrity to complete the work.
2. Fundamentals of Surety Bonding
A Surety Bond is a legal instrument that guarantees a contractor will fulfill specific contractual obligations. It is fundamentally different from traditional commercial insurance.
- The Tri-Partite Surety Relationship
- A surety bond involves three distinct parties: OBLIGEE (Project Owner)
- /
- /
- Bond Protection Contract Obligation
- /
- /
- SURETY (Bonding Co.) <--- Indemnity Agreement ---> PRINCIPAL (General Contractor)
Principal : The General Contractor who purchases the bond and promises to perform the contract.
Obligee : The Project Owner (or public agency) protected by the bond.
Surety : The financial institution (bonding company) that guarantees the principal’s performance.
Comparison: Surety Bonds vs. Insurance Policies
- Feature Commercial Insurance Surety Bond
- Party Structure Two-party agreement (Insured & Insurer) Three-party agreement (Principal, Obligee, Surety)
- Loss Expectation Actuarial losses anticipated and pooled Zero-loss expectation based on pre-qualification
Indemnity / Reimbursement Insurer covers loss; no repayment required Principal must fully reimburse (indemnify) surety
- Premium Purpose Fee for risk transfer Fee for credit extension / financial guarantee
- Underwriting: The 3 Cs of Surety Credit
Surety underwriters evaluate a contractor's bonding capacity based on three primary criteria:
Character : Business reputation, integrity, references, and track record of paying obligations.
Capacity : Technical experience, plant equipment, key staff competency, and current work-in-progress (WIP).
Capital : Financial strength, net working capital, current financial ratio, and corporate net worth.
- 3. Types of Construction Surety Bonds BID BOND PERFORMANCE BOND PAYMENT BOND
- (5% to 10% of Bid) (100% of Contract) (100% of Contract)
- Guarantees GC will • Guarantees project completion • Guarantees payment to
- sign contract & provide if GC defaults. subcontractors & material
final bonds. suppliers (prevents liens).
A. Bid Bond
Purpose : Guarantees that if the contractor is awarded the contract, they will execute the agreement and supply required performance and payment bonds.
Penal Sum : Typically 5% to 10% of the total bid proposal price.
Default Penalty : If the low bidder refuses to execute the contract, the surety must pay the Obligee the difference between the low bid and the next lowest bid, up to the maximum penal sum of the bond.
B. Performance Bond
Purpose : Protects the owner against financial loss if the contractor defaults or fails to perform the work according to plans and specifications.
Penal Sum : Usually 100% of the contract price.
Surety Options upon Default : If the contractor defaults, the surety may:
Financial financing: Assist the principal to complete work.
Takeover: Assume control and complete the project using a replacement contractor.
Tender: Select a new contractor to contract directly with the owner.
Pay out: Pay the owner the net cost of completion up to the penal sum limit.
C. Payment Bond
Purpose : Guarantees that the contractor will pay all valid claims from subcontractors, material suppliers, and laborers working on the project.
Penal Sum : Usually 100% of the contract price.
Significance : On public projects where mechanics' liens cannot attach to public property, payment bonds serve as the exclusive financial protection for subcontractors.
D. Maintenance / Warranty Bond
Purpose : Guarantees against defects in workmanship or materials for a specified period (typically 1 to 2 years) following substantial completion.
4. The Miller Act & Florida Little Miller Act (F.S. 255.05)
Because public property owned by government entities cannot be subjected to mechanics' liens under Florida Lien Law (F.S. 713), statutory bonding acts were enacted to protect sub-tier claimants.
Federal Miller Act (40 U.S.C. 3131-3134)
Requires performance and payment bonds on all federal public works contracts exceeding $150,000.
Florida Little Miller Act (Florida Statutes § 255.05)
Mandates that any contractor entering into a public building or public works contract with the State of Florida, county, city, or public board exceeding statutory thresholds must execute and record a 100% Payment and Performance Bond before commencing work.
Statutory Notice & Lawsuit Deadlines under F.S. 255.05
Subcontractors and suppliers who are not in privity of contract with the General Contractor must adhere strictly to statutory notice timeframes to maintain rights against the payment bond: DAY 0 DAY 45 DAY 90 1 YEAR
- +-----------------------+-----------------------+-----------------------+
- First Work Notice to Contractor Last Work Lawsuit Deadline
- Furnished Served Notice of Nonpayment Action on Bond
- Served Filed in Court
- Statutory Instrument Applicable Party Mandatory Deadline / Timeframe
- Recording & Copy General Contractor Record bond in public records & provide copy to sub before work starts
Notice to Contractor Sub/Supplier not in privity Served within 45 days of beginning first labor, services, or materials
Notice of Nonpayment Sub/Supplier unpaid Served within 90 days after last furnishing labor, services, or materials
Action on Bond (Lawsuit) All Bond Claimants Filed within 1 year after complete performance/delivery of materials
Exam Key Point: A subcontractor in direct privity with the general contractor is exempt from serving a Notice to Contractor, but must still comply with serving a Notice of Nonpayment within 90 days and instituting litigation within 1 year.