Study guide
10.2 Tracking Job Costs
Florida HVAC Contractor License Class A/B
Track your progress as you read
Finished sections get a check mark.
1 Introduction & Exam Overview
1.1 Current Exam Facts & License Classes 1.2 Exam Format, Open-Book Rules & Pearson VUE 1.3 Eligibility, Experience Paths & Financial Responsibility
2 Establishing the Contracting Business
2.1 Business Organizational Structure 2.2 Business Plan, Marketplace & License Scope 2.3 Professionals, Fixed Assets & Bonding
3 Insurance for Florida HVAC Contractors
3.1 Obtaining Insurance (GL, Workers' Compensation & Bonds) 3.2 Coverages, Limits & Policy Language 3.3 Maintaining Insurance & CILB Certificate-Holder Rules
4 Overhead, Staffing & Markets
4.1 Developing the Business, Staffing & Markets 4.2 Determining Business Overhead (FICA, FUTA, SUTA, Workers' Comp, Rent & Utilities) 4.3 Determining Outsourced Services
5 Bids, Proposals & Estimating
5.1 Preparing Bids and Proposals 5.2 AIA Documents, Offers & Contract Components 5.3 Labor Productivity, Overhead & Project Costing
6 Purchasing, Invoices, Draws & Safety Programs
6.1 Purchasing Materials, UCC & Inventory (FIFO) 6.2 Invoices, Draw Requests & Percentage of Completion 6.3 Developing a Safety Program (OSHA, SDS & Drug Testing)
7 Managing Contracts
7.1 Contract Law, Scope & Completion Schedules 7.2 Florida Lien Law Inside Contracting 7.3 Mediation, Arbitration, Tort Law & Risk
8 Managing Trade Operations
8.1 Scheduling Trade Operations (CPM, RFI & Submittals) 8.2 OSHA Records, Document Retainage & Penalties 8.3 Takeoffs, Equipment Lease vs Purchase & Inventory
9 Accounting I: Receivables, Payables & Cash
9.1 Managing Accounts Receivable 9.2 Managing Accounts Payable & Discounts 9.3 Cash Flow, Banking & Financial Ratios
10 Accounting II: Taxes, Job Cost & Payroll
10.1 Filing Tax Forms & Returns 10.2 Tracking Job Costs 10.3 Payroll, Employment Taxes & Garnishments
11 Managing Human Resources
11.1 Hiring, I-9, Background Checks & Discrimination 11.2 HR Policies, OSHA & Drug-Test Chain of Custody 11.3 Evaluating Employees
12 Florida Contractor Law: Chapter 489 & 61G4
12.1 Chapter 489: Certified vs Registered & Qualifying Agents 12.2 61G4 Board Rules, Advertising & Discipline 12.3 Qualifying Agent Duties, Supervision & Additional Entities
13 Florida Construction Lien Law (Chapter 713)
13.1 Construction Lien Overview & Claimants 13.2 Notices to Owner, Time Limits & Perfecting Liens 13.3 Payment Bonds, Waivers & Claims of Lien
14 Financial Responsibility, CE & Federal Rules
14.1 Financial Responsibility & the 660 FICO Rule 14.2 Continuing Education & Biennial Renewal 14.3 Federal Employment, Immigration, OSHA & Environmental Rules
15 Plans, Specs & Equipment Selection
15.1 Reading Plans, Specifications, Symbols & Scales 15.2 Recommending Plan Changes & Equipment Types 15.3 EER, SEER, ARI Listings & Cost Effectiveness
16 Energy Codes, Loads & Thermal Resistance
16.1 Florida Energy Codes, R-Values & U-Factors 16.2 Determining HVAC Heating & Cooling Loads 16.3 Applying Energy Conservation, Fan Curves & Pump Curves
17 HVAC System & Duct Design
17.1 Designing HVAC Systems (Psychrometrics, Enthalpy & Airflow) 17.2 Designing Duct Systems & Insulation 17.3 Selecting Equipment, Location & Codes
18 Piping, Pumps, Boilers, Controls & Rigging Design
18.1 Pipe Sizing, Valves, Fittings, Sealants & Layout 18.2 Control Requirements, Fan Motors, CFM & Compressor Capacity 18.3 Pumps, Boilers, Steam, Fuel & Pipe Insulation 18.4 Grease Ducts, Live Loads, Rigging & Mechanical Equipment
19 Sheet Metal Duct Fabrication
19.1 Fabricating Rectangular & Round Ducts 19.2 Seams, Locks, Taping, Mastics & Liners 19.3 Fittings, Outlets & Grilles 19.4 Kitchen Hoods, Exhausts & Drain Pans
20 Split, Package & Heat Pump Installation
20.1 Installing Split & Package Air Conditioners 20.2 Installing Split & Package Heat Pumps 20.3 Air-Cooled vs Water-Cooled Systems
21 Large Systems, Chillers & Towers
21.1 Installing by Tonnage & Class A vs Class B Limits 21.2 Chilled Water, Water Towers & Secondary Coolant 21.3 Centrifugal, Absorption & Ammonia Systems
22 Refrigeration, Coolers, Ventilation & Controls Install
22.1 Low, Medium & Ultra-Low Temperature Systems & EPA Rules 22.2 Walk-In & Reach-In Coolers 22.3 Ventilation, Exhaust, Makeup Air, Grease Ducts & Kitchen Exhaust 22.4 Geothermal, Pneumatic & DDC Controls, TAB & Smoke Tests
23 Condensers, Compressors & Air Handlers
23.1 Installing Air-Cooled & Water-Cooled Condensers 23.2 Hermetic, Semi-Hermetic & Centrifugal Compressors 23.3 Air Handlers, Evaporators, Heat Exchangers, Receivers & Heat Strips
24 Duct, Fans, Filters & Terminals
24.1 Installing Sheet Metal, Fiberglass & Flexible Duct 24.2 Fans, Blowers, Motors, Grilles, Registers & Fire Dampers 24.3 Filters, Flues, Warm-Air, Gas & Fuel-Oil Appliances
25 Refrigerant Piping & Joining
25.1 Refrigerant Piping, Copper Tubing & Pipe Sizing 25.2 Brazing, Welding, Flaring, Swaging & Soldering 25.3 Steel Pipe, Plastic Pipe, Threading & Oxy-Acetylene 25.4 Hangers, Supports, Horizontally Supported Piping & Pressure Testing
26 Metering Devices & Line Components
26.1 TXVs, Capillary Tubes, Reversing Valves & Metering Devices 26.2 Liquid, Suction & Heat-Pump Dryers, Filters & Oil Traps 26.3 Receivers, Heat Strips, Gas/Oil Appliances & Related Accessories
27 Controls Installation
27.1 Pressure, Temperature, Humidity & Bellows Controls 27.2 Thermostats, Humidistats, Pneumatic & Solid-State Controls 27.3 Transformers, Capacitors, Contactors, Relays & Safety Disconnects 27.4 Defrost Components, Starters, Solenoids & Limit Switches
28 Motors, Wiring & Electrical Installation
28.1 Wiring Single-Phase & Three-Phase Equipment 28.2 Motor Types, Protection, Controllers, Belts & Pulleys 28.3 Geothermal Loops, Surge Protectors, Phase Monitors & Plastic Pipe
29 Diagnostic Analysis: Refrigeration
29.1 Pressure-Enthalpy Diagrams & Operating Pressures 29.2 Air Volumes, Enthalpy, Wet-Bulb & Dry-Bulb 29.3 Leak Detection & Refrigeration Test Instruments
30 Diagnostic Analysis: Electrical & Instruments
30.1 Current Draw, Voltage, Power & Motor Terminals 30.2 Testing Relays, Capacitors, Starters, Transformers & Defrost Stats 30.3 Using Amprobes, Velometers, Pitot Tubes, Manometers & Gauges
31 Recovery, Repair & Calibration
31.1 Nitrogen & Gas Regulators, Recovery & Retrofit 31.2 Repairing Hermetic, Semi-Hermetic, Centrifugal Compressors & Blowers 31.3 Calibrating Thermostats, Pressure Switches & Pneumatic Controls 31.4 Superheat, Safety Cutouts, Defrost Clocks & Freezer Controls
32 Mechanical Service & Cleaning
32.1 Belts, Pulleys, Motor Rotation & Seized Compressors 32.2 Crankcase & Evaporator Pressure Regulators & Unloaders 32.3 Cleaning Towers, Condensers, Foreign Matter & Condensate Drains
33 Jobsite Safety & Equipment
33.1 PPE: Hearing, Head, Eye, Face & Respiratory Protection 33.2 Lockout/Tagout, Warning Signs, Toxic Materials & Ventilation 33.3 Rigging, Hoists, Cranes, Forklifts, Backhoes & Excavation 33.4 Ladders, Scaffolds, Tools & Air Compressors
34 Energy Management
34.1 Envelope, Duct Pressure & Blower-Door Testing 34.2 Efficient Equipment, Zoning, ERVs, Wi-Fi Thermostats & Green Buildings 34.3 Energy Forms, R/U Factors, Window Heat Gain & Florida Load Calcs
35 Indoor Air Quality
35.1 Ventilation, Filtration, Humidity, UV & Air Cleaners 35.2 Contaminants, Source Control, TAB & Human Health Effects
10.2 Tracking Job Costs
Key Takeaways Explain This Topic AI
Direct HVAC job-cost codes include equipment, refrigerant, duct, piping, field labor, crane/rigging, and the mechanical permit; those dollars exist because the named contract exists, not because the shop exists.
Burdened labor is hourly wage plus employer FICA of 7.65% (6.2% Social Security + 1.45% Medicare), plus FUTA and Florida reemployment tax while each is still inside the $7,000 wage base, plus workers' compensation and benefits allocated to the hour.
Cost-to-cost percentage of completion is costs incurred to date divided by current estimated total cost — not divided by contract price — and that percentage times the contract price is earned revenue.
After an employee reaches $7,000 of calendar-year wages, drop FUTA and Florida reemployment tax from that hour's burden; after the Circular E Social Security wage base, drop the 6.2% but keep 1.45% Medicare (no Medicare cap).
A Class A 40-ton RTU set still uses the same job-cost codes as a Class B 4-ton changeout; Class B candidates need the crane-and-permit theory even though the Class B outline drops 25–100 and over-100-ton installs.
Last updated: August 2026
10.2 Tracking Job Costs
Area D's job costs item is accounting and mathematics . Builder's Guide to Accounting (2001) is the job-cost textbook on the B&F list; Circular E 2025 in the Contractors Manual 2025 supplies the payroll-tax percentages that turn a wage into a burdened hour. Section 4.2 taught overhead — the cost of staying open. Section 9.1 taught percentage-of-completion. This section is the job-cost ledger that feeds both: every dollar that exists because this contract exists .
If you dump crane rental, refrigerant, and the mechanical permit into shop supplies, two things happen. The job looks more profitable than it is, and overhead looks worse than it is. You then underbid the next 40-ton set and wonder why the checking account died. The qualifying agent still owns those financials under F.S. 489.1195 .
Direct job cost versus overhead
Direct job cost (cost of sales on a named job) is field labor on that job, materials incorporated into that job, the subcontract written for that address, job-specific equipment, job-specific rentals, permits and inspections for that address, sales or use tax paid as the consumer of those materials, and freight to the site.
Overhead (period cost of the shop) is rent, office salaries, advertising, shop utilities, general liability that is not job-billed, the unused service van, unused sheet-metal-brake depreciation, and CPE. Recover overhead through markup , not by hiding it inside Job 4412 so the changeout looks cheap.
A cost can be direct on Monday and overhead on Tuesday. The shop's nitrogen bottle used for every brazing job is overhead (or a small allocated shop-supply rate). A nitrogen tube rented for one hospital braze-out is a job cost. The test is not the account name on the vendor's invoice. The test is: would this dollar have been spent if this contract did not exist?
HVAC cost codes the exam expects you to recognize
Use a chart of cost codes so every invoice and time card hits the same buckets. Typical Florida HVAC codes:
Cost code What hits it Direct job cost?
- Equipment Condensing unit, air handler, RTU, furnace, coil, packaged heat pump, thermostat as furnished Yes
- Refrigerant Factory charge, additional R-410A or R-32, recovered or reclaimed amounts charged to the job Yes
- Duct Rectangular, round, flex, liner, mastic, tape, hangers, turning vanes Yes
- Piping / copper ACR tubing, fittings, insulation, condensate piping in the HVAC scope Yes
- Labor Field technicians and helpers on that job , at the burdened rate Yes
- Crane / rigging Mobile crane to set an RTU or chiller, boom, flaggers required for that pick Yes
- Permit / fees Mechanical permit, after-hours inspection, sidewalk closure for the crane Yes
Electrical (HVAC) Disconnect, whip, circuit to the existing dedicated disconnect (license-scope limits still apply) Yes if in the contract
- Controls Low-voltage, stats, communicating controls furnished with the system Yes
- Subcontract TAB, insulation sub, sheet-metal shop, licensed electrical beyond HVAC exceptions Yes
- Equipment rental Boom lift, extra recovery machine, chiller-barrel plugs for that shutdown Yes
- Shop overhead Office manager, advertising, shop rent, unused inventory shrink No
Class A work over 25 tons cooling or 500,000 Btu heating in any one system ( F.S. 489.105 ) is where crane and large-equipment codes dominate. A Class B candidate still needs the theory: the Class B outline drops 25–100 and over-100-ton install items, not the idea that a crane is a job cost. Setting a 4-ton condensing unit with two techs and a hand truck still has equipment, refrigerant, labor, and permit codes.
Burdened labor (the math)
Do not cost jobs at the technician's straight-time wage . Burdened labor is the wage plus the employer costs that move with that hour.
Burdened rate = hourly wage + employer FICA ( 6.2% Social Security + 1.45% Medicare = 7.65% until the Social Security wage base printed in Circular E 2025 ) + FUTA + Florida reemployment tax (while each is still inside the $7,000 wage base) + workers' compensation allocated to that class + employer-paid benefits that attach to hours (health insurance, paid-time-off accrual if the shop burdens it).
Worked example — W-2 installer, $28.00 per hour, wages still under the Social Security wage base. This hour is still inside the $7,000 FUTA and reemployment bases. The shop's workers' compensation allocation to this class is $3.20 per hour (use your policy; the exam will give the figure — do not invent an NCCI rate). New-employer reemployment tax 2.7% . Full FUTA credit, effective 0.6% .
- Employer FICA = 0.0765 × 28.00 = $2.14
- FUTA = 0.006 × 28.00 = $0.17
- SUTA = 0.027 × 28.00 = $0.76
- WC = $3.20
- Burdened rate = 28.00 + 2.14 + 0.17 + 0.76 + 3.20 = $34.27 per hour
After the employee has earned $7,000 in the calendar year, drop FUTA and Florida reemployment tax from the burden — they are $0 on later hours. After the Circular E Social Security wage base, drop the 6.2% but keep 1.45% Medicare (there is no Medicare wage cap). Additional Medicare tax of 0.9% on employee wages over $200,000 (single filer threshold) is employee-only ; it is withheld, not an employer job-cost burden.
Overtime: the Fair Labor Standards Act ( FLSA ) requires time-and-a-half on the wage after 40 hours in the workweek, then apply the percentages to the overtime wage. If Saturday premium is $42.00 per hour, employer FICA is 7.65% of $42.00 , not of $28.00.
Worked job — Class B 4-ton changeout, lump-sum $8,400 .
- Cost code Budget Actual
- Equipment $3,250 $3,100
- Refrigerant $160 $210
- Duct / flex / mastic $740 $920
- Copper / condensate $180 $210
- Labor 18 hrs × $34.27 = $617 22 hrs × $34.27 = $754
- Permit $165 $165
- Total direct $5,112 $5,359
Labor quantity variance = (22 − 18) × 34.27 = $137.08 unfavorable (duct modifications after the drywall was closed). Equipment price variance = 3,100 − 3,250 = $150 favorable . Net, the job ran $247 over the direct budget. Gross profit before overhead = 8,400 − 5,359 = $3,041 . If the shop's overhead-recovery target was 18% of contract (0.18 × 8,400 = $1,512 ), remaining contribution is about $1,529 . That is the number that pays rent. Costing labor at $28.00 would have understated labor by 22 × $6.27 = $138 and lied about margin.
Equipment, refrigerant, crane, permit — traps
Equipment on a named job is a job cost when it is purchased for that contract or issued from inventory to that job. A 40-ton RTU staged for Job 4412 is not inventory after it is committed; Builder's Guide wants it on the job. If you progress-bill stored equipment that is still at the vendor, you recreate the overbilling problem from section 9.1.
Refrigerant is not shop supplies. EPA Section 608 already tracks who added what; the job-cost code is how you know whether Job 4412 used 18 lb or 31 lb. Extra pounds are a change-order conversation, not a mystery in June.
Crane: setting a packaged unit with a rented crane is incurred because of that roof , not because you have a shop. Code it to the job. If you own a boom truck, some shops burden an internal rental rate to the job so equipment recovery is not lost in overhead — that internal rate is still a job cost.
Permit: the mechanical permit and inspection fees for that address are job costs. They are not sales tax (do not put them on DR-15 as collections) and they are not overhead. A Class A 80-ton schoolhouse job with after-hours inspections can have permit and fee costs in the thousands. Burying them in overhead makes every 3-ton changeout look expensive and every large set look cheap.
Percentage of completion eats job cost
Cost-to-cost percentage of completion (POC) = costs incurred to date ÷ current estimated total cost (not ÷ contract price). Earned revenue = POC × contract price.
Worked example — certified Class A, $180,000 lump-sum, one 35-ton unit (over Class B's 25-ton cap). Costs to date $72,000 . The estimator now forecasts $160,000 total because the crane came in high.
- POC = 72,000 / 160,000 = 45%
- Earned revenue = 0.45 × 180,000 = $81,000
- If billed $90,000 → $9,000 overbilling (a current liability)
Wrong denominator (72,000 / 180,000 = 40%) is the exam trap. Job-cost discipline is what makes the 45% true: if the crane is still sitting in overhead, costs to date are understated, POC is understated, and you underbill in the books while thinking you are conservative.
Committed costs (open purchase orders) are not yet costs incurred for POC until the work or materials are received, but they update the estimated total the moment you know the crane will be $1,850 instead of $900. That is why the job-cost ledger and the estimate have to talk to each other weekly, not at punch list.
Florida HVAC scenario
Suncoast Air, qualified by a certified Class A agent, sets a 40-ton RTU on a Sarasota medical office. Codes: equipment $28,400, crane $1,850, permit $410, duct $6,200, refrigerant $640, copper $1,100, burdened labor 86 hours × $34.27 = $2,947, electrical-within-scope $780. Direct total $42,327 on a $72,000 contract. A project manager who calls the crane overhead would show a fake $1,850 of extra gross and then fail to recover it on the next bid. Class B candidates will not install this 40-ton system, but they will be asked whether a crane and a permit are job costs.