Study guide

13.1 Construction Lien Overview & Claimants

Florida HVAC Contractor License Class A/B

Track your progress as you read

Finished sections get a check mark.

1 Introduction & Exam Overview

1.1 Current Exam Facts & License Classes 1.2 Exam Format, Open-Book Rules & Pearson VUE 1.3 Eligibility, Experience Paths & Financial Responsibility

2 Establishing the Contracting Business

2.1 Business Organizational Structure 2.2 Business Plan, Marketplace & License Scope 2.3 Professionals, Fixed Assets & Bonding

3 Insurance for Florida HVAC Contractors

3.1 Obtaining Insurance (GL, Workers' Compensation & Bonds) 3.2 Coverages, Limits & Policy Language 3.3 Maintaining Insurance & CILB Certificate-Holder Rules

4 Overhead, Staffing & Markets

4.1 Developing the Business, Staffing & Markets 4.2 Determining Business Overhead (FICA, FUTA, SUTA, Workers' Comp, Rent & Utilities) 4.3 Determining Outsourced Services

5 Bids, Proposals & Estimating

5.1 Preparing Bids and Proposals 5.2 AIA Documents, Offers & Contract Components 5.3 Labor Productivity, Overhead & Project Costing

6 Purchasing, Invoices, Draws & Safety Programs

6.1 Purchasing Materials, UCC & Inventory (FIFO) 6.2 Invoices, Draw Requests & Percentage of Completion 6.3 Developing a Safety Program (OSHA, SDS & Drug Testing)

7 Managing Contracts

7.1 Contract Law, Scope & Completion Schedules 7.2 Florida Lien Law Inside Contracting 7.3 Mediation, Arbitration, Tort Law & Risk

8 Managing Trade Operations

8.1 Scheduling Trade Operations (CPM, RFI & Submittals) 8.2 OSHA Records, Document Retainage & Penalties 8.3 Takeoffs, Equipment Lease vs Purchase & Inventory

9 Accounting I: Receivables, Payables & Cash

9.1 Managing Accounts Receivable 9.2 Managing Accounts Payable & Discounts 9.3 Cash Flow, Banking & Financial Ratios

10 Accounting II: Taxes, Job Cost & Payroll

10.1 Filing Tax Forms & Returns 10.2 Tracking Job Costs 10.3 Payroll, Employment Taxes & Garnishments

11 Managing Human Resources

11.1 Hiring, I-9, Background Checks & Discrimination 11.2 HR Policies, OSHA & Drug-Test Chain of Custody 11.3 Evaluating Employees

12 Florida Contractor Law: Chapter 489 & 61G4

12.1 Chapter 489: Certified vs Registered & Qualifying Agents 12.2 61G4 Board Rules, Advertising & Discipline 12.3 Qualifying Agent Duties, Supervision & Additional Entities

13 Florida Construction Lien Law (Chapter 713)

13.1 Construction Lien Overview & Claimants 13.2 Notices to Owner, Time Limits & Perfecting Liens 13.3 Payment Bonds, Waivers & Claims of Lien

14 Financial Responsibility, CE & Federal Rules

14.1 Financial Responsibility & the 660 FICO Rule 14.2 Continuing Education & Biennial Renewal 14.3 Federal Employment, Immigration, OSHA & Environmental Rules

15 Plans, Specs & Equipment Selection

15.1 Reading Plans, Specifications, Symbols & Scales 15.2 Recommending Plan Changes & Equipment Types 15.3 EER, SEER, ARI Listings & Cost Effectiveness

16 Energy Codes, Loads & Thermal Resistance

16.1 Florida Energy Codes, R-Values & U-Factors 16.2 Determining HVAC Heating & Cooling Loads 16.3 Applying Energy Conservation, Fan Curves & Pump Curves

17 HVAC System & Duct Design

17.1 Designing HVAC Systems (Psychrometrics, Enthalpy & Airflow) 17.2 Designing Duct Systems & Insulation 17.3 Selecting Equipment, Location & Codes

18 Piping, Pumps, Boilers, Controls & Rigging Design

18.1 Pipe Sizing, Valves, Fittings, Sealants & Layout 18.2 Control Requirements, Fan Motors, CFM & Compressor Capacity 18.3 Pumps, Boilers, Steam, Fuel & Pipe Insulation 18.4 Grease Ducts, Live Loads, Rigging & Mechanical Equipment

19 Sheet Metal Duct Fabrication

19.1 Fabricating Rectangular & Round Ducts 19.2 Seams, Locks, Taping, Mastics & Liners 19.3 Fittings, Outlets & Grilles 19.4 Kitchen Hoods, Exhausts & Drain Pans

20 Split, Package & Heat Pump Installation

20.1 Installing Split & Package Air Conditioners 20.2 Installing Split & Package Heat Pumps 20.3 Air-Cooled vs Water-Cooled Systems

21 Large Systems, Chillers & Towers

21.1 Installing by Tonnage & Class A vs Class B Limits 21.2 Chilled Water, Water Towers & Secondary Coolant 21.3 Centrifugal, Absorption & Ammonia Systems

22 Refrigeration, Coolers, Ventilation & Controls Install

22.1 Low, Medium & Ultra-Low Temperature Systems & EPA Rules 22.2 Walk-In & Reach-In Coolers 22.3 Ventilation, Exhaust, Makeup Air, Grease Ducts & Kitchen Exhaust 22.4 Geothermal, Pneumatic & DDC Controls, TAB & Smoke Tests

23 Condensers, Compressors & Air Handlers

23.1 Installing Air-Cooled & Water-Cooled Condensers 23.2 Hermetic, Semi-Hermetic & Centrifugal Compressors 23.3 Air Handlers, Evaporators, Heat Exchangers, Receivers & Heat Strips

24 Duct, Fans, Filters & Terminals

24.1 Installing Sheet Metal, Fiberglass & Flexible Duct 24.2 Fans, Blowers, Motors, Grilles, Registers & Fire Dampers 24.3 Filters, Flues, Warm-Air, Gas & Fuel-Oil Appliances

25 Refrigerant Piping & Joining

25.1 Refrigerant Piping, Copper Tubing & Pipe Sizing 25.2 Brazing, Welding, Flaring, Swaging & Soldering 25.3 Steel Pipe, Plastic Pipe, Threading & Oxy-Acetylene 25.4 Hangers, Supports, Horizontally Supported Piping & Pressure Testing

26 Metering Devices & Line Components

26.1 TXVs, Capillary Tubes, Reversing Valves & Metering Devices 26.2 Liquid, Suction & Heat-Pump Dryers, Filters & Oil Traps 26.3 Receivers, Heat Strips, Gas/Oil Appliances & Related Accessories

27 Controls Installation

27.1 Pressure, Temperature, Humidity & Bellows Controls 27.2 Thermostats, Humidistats, Pneumatic & Solid-State Controls 27.3 Transformers, Capacitors, Contactors, Relays & Safety Disconnects 27.4 Defrost Components, Starters, Solenoids & Limit Switches

28 Motors, Wiring & Electrical Installation

28.1 Wiring Single-Phase & Three-Phase Equipment 28.2 Motor Types, Protection, Controllers, Belts & Pulleys 28.3 Geothermal Loops, Surge Protectors, Phase Monitors & Plastic Pipe

29 Diagnostic Analysis: Refrigeration

29.1 Pressure-Enthalpy Diagrams & Operating Pressures 29.2 Air Volumes, Enthalpy, Wet-Bulb & Dry-Bulb 29.3 Leak Detection & Refrigeration Test Instruments

30 Diagnostic Analysis: Electrical & Instruments

30.1 Current Draw, Voltage, Power & Motor Terminals 30.2 Testing Relays, Capacitors, Starters, Transformers & Defrost Stats 30.3 Using Amprobes, Velometers, Pitot Tubes, Manometers & Gauges

31 Recovery, Repair & Calibration

31.1 Nitrogen & Gas Regulators, Recovery & Retrofit 31.2 Repairing Hermetic, Semi-Hermetic, Centrifugal Compressors & Blowers 31.3 Calibrating Thermostats, Pressure Switches & Pneumatic Controls 31.4 Superheat, Safety Cutouts, Defrost Clocks & Freezer Controls

32 Mechanical Service & Cleaning

32.1 Belts, Pulleys, Motor Rotation & Seized Compressors 32.2 Crankcase & Evaporator Pressure Regulators & Unloaders 32.3 Cleaning Towers, Condensers, Foreign Matter & Condensate Drains

33 Jobsite Safety & Equipment

33.1 PPE: Hearing, Head, Eye, Face & Respiratory Protection 33.2 Lockout/Tagout, Warning Signs, Toxic Materials & Ventilation 33.3 Rigging, Hoists, Cranes, Forklifts, Backhoes & Excavation 33.4 Ladders, Scaffolds, Tools & Air Compressors

34 Energy Management

34.1 Envelope, Duct Pressure & Blower-Door Testing 34.2 Efficient Equipment, Zoning, ERVs, Wi-Fi Thermostats & Green Buildings 34.3 Energy Forms, R/U Factors, Window Heat Gain & Florida Load Calcs

35 Indoor Air Quality

35.1 Ventilation, Filtration, Humidity, UV & Air Cleaners 35.2 Contaminants, Source Control, TAB & Human Health Effects

13.1 Construction Lien Overview & Claimants

Key Takeaways Explain This Topic AI

Privity means a direct contract with the owner (F.S. 713.01(9)); F.S. 713.05 lienors in privity — the contractor, and a materialman or laborer in privity with the owner — are not required to serve a Notice to Owner.

Non-privity lienors under F.S. 713.06 (subcontractor, sub-subcontractor, materialman or laborer not in privity) have a lien only if they comply; laborers are excepted from the Notice to Owner prerequisite, and missing a required Notice to Owner is a complete defense.

F.S. 713.01(19) limits lienors to the contractor, subcontractor, sub-subcontractor, laborer, materialman, and a professional lienor under 713.03; F.S. 713.02(7) bars a lien for an unlicensed contractor, subcontractor, or sub-subcontractor.

F.S. 713.01(24) and (27) exclude political subdivisions, agencies, municipalities, and school-board property from Chapter 713 owner and real-property definitions — do not lien a public-school RTU job.

Specially fabricated HVAC equipment is 'furnish materials' under 713.01(14); materials specially fabricated off site but not incorporated must be separately stated in the claim of lien (713.08(1)(c)).

Last updated: August 2026

13.1 Construction Lien Overview & Claimants

Business & Finance (B&F) Area F — Complying with Government Regulations is 15% of 120 questions , roughly 18 items. Florida Statutes Chapter 713 , Part I (Construction Liens) sits on the 2026 B&F path through the Contractors Manual 2025 (used beginning February 1, 2026) and the statutes themselves. Chapter 12 told you who may contract. This chapter tells you who still gets paid when someone up the chain does not. A construction lien is a statutory charge on private real property that secures unpaid labor, services, or materials that improved that property. It is not a lawsuit by itself, not a collection letter, and not a right that attaches to a public-school rooftop.

The primary qualifying agent owns the financial side of the business unless a Financially Responsible Officer (FRO) is appointed. Leaving valid liens on an owner's property more than 75 days after the contractor was paid is a F.S. 489.129 disciplinary ground. Chapter 713 is therefore both a payment tool and a license-risk statute. Candidates who treat “lien” as one blob miss the exam. The statute splits who is in privity with the owner, who must serve a Notice to Owner (NTO) , and what property can even be liened.

Privity versus non-privity

Privity means a direct contract with the owner . F.S. 713.01(9) defines a direct contract as a contract between the owner and any other person. The HVAC contractor who signs with a clinic owner to replace two 12.5-ton splits is in privity. The sheet-metal shop that contracts only with that HVAC contractor is not in privity with the owner. The supply house that sells condensers to the HVAC contractor is not in privity with the owner. A person who personally performs on-site labor, furnishes no materials, and furnishes no labor of others is a laborer under F.S. 713.01(17) — whether the check comes from the owner or from a contractor — and is not an architect, landscape architect, engineer, or surveyor.

F.S. 713.05 is the privity statute. A materialman or laborer in privity with the owner , or a contractor who complies with Part I, has a lien on the real property improved for money owed for labor, services, materials, or other items required by or furnished in accordance with the direct contract, plus unpaid finance charges. No lien under 713.05 is acquired until a claim of lien is recorded. Those privity lienors shall not be required to serve a notice to owner as provided in 713.06(2). A lienor other than a laborer or materialman who is in privity with the owner and claims under 713.05 shall furnish the contractor's affidavit required in 713.06(3)(d). That is why a direct HVAC contractor still has an affidavit duty even though the contractor never serves an NTO.

F.S. 713.06 is the non-privity statute. A materialman or laborer not in privity with the owner , or a subcontractor or sub-subcontractor who complies, has a lien on the real property improved for money owed under that person's contract and the direct contract. The total of all liens allowed under Part I for furnishing covered by any certain direct contract must not exceed the amount of the contract price fixed by that direct contract, except as provided in 713.06(3). Non-privity lienors, except laborers , must serve an NTO as a prerequisite to perfecting a lien and recording a claim of lien. Failure to serve the notice, or to serve it timely, is a complete defense to enforcement. The NTO is not itself a lien, cloud, or encumbrance, and serving it does not dispense with recording the claim of lien.

A lienor who starts as a subcontractor, sub-subcontractor, laborer, or materialman not in privity, and who later becomes in privity with the owner, has a 713.05 lien only for money owed for labor, services, or materials furnished after becoming in privity. That person may record one claim of lien covering both the privity work and the non-privity work (713.05).

Who may be a lienor — the closed list

F.S. 713.01(19) is exhaustive. A lienor is a contractor; a subcontractor; a sub-subcontractor; a laborer; a materialman who contracts with the owner, a contractor, a subcontractor, or a sub-subcontractor; or a professional lienor under F.S. 713.03 . No other person may have a lien under this part.

Lienor (713.01) Meaning Typical HVAC example Notice to Owner?

Contractor (713.01(8)) Person other than a materialman or laborer who contracts with the owner, or who takes over the entire remaining work Certified Class A shop with a direct contract to set an 80-ton chiller No — in privity (713.05)

Subcontractor (713.01(29)) Person other than a materialman or laborer who contracts with a contractor for any part of that contractor's contract Class B HVAC sub to a Division I general contractor Yes (713.06), unless a laborer

Sub-subcontractor (713.01(30)) Person other than a materialman or laborer who contracts with a subcontractor Insulation or controls firm hired by the HVAC sub Yes; also serve a copy on the contractor

Laborer (713.01(17)) Person who personally performs on-site labor or services and does not furnish materials or labor of others Helper brazing on the roof, paid hourly, no materials Excepted from the NTO prerequisite

Materialman (713.01(21)) Person who furnishes materials under contract to the owner, contractor, sub, or sub-sub on site, for direct delivery to the site, or (for specially fabricated materials) off site for the particular improvement, and who performs no labor in the installation Supply house delivering condensers; factory building a custom air handler Yes if not in privity with the owner

Professional lienor (713.03) Architect, landscape architect, interior designer, engineer, or surveyor under 713.03 Design-build engineering on a qualifying contract Follow 713.03, not the HVAC-sub NTO path

Unlicensed contractors, subcontractors, and sub-subcontractors have no lien (F.S. 713.02(7) ). F.S. 489.128 already makes a contract entered in violation of Chapter 489 unenforceable by that unlicensed contractor; 713.02(7) closes the lien door. Other persons' contract, lien, or bond rights are not destroyed by the unlicensed actor, and a surety cannot defend a bond claim solely because the principal was unlicensed.

F.S. 713.02(5) exempts an improvement whose direct contract price is $2,500 or less from all other provisions of Part I except 713.05. A tiny privity changeout can still support a 713.05 claim of lien; the NTO machinery of 713.06 does not run on that small direct contract. Do not tell the exam that every residential service call is “too small to lien” — the cutoff is the direct contract price , and 713.05 still applies.

Public property is not lienable

F.S. 713.01(24) defines owner as a person with a legal or equitable interest that can be sold by legal process who enters a contract for the improvement. The term does not include any political subdivision, agency, or department of the state, a municipality, or other governmental entity. F.S. 713.01(27) defines real property as the land improved and the improvements thereon, except property owned by the state or any county, municipality, school board , or governmental agency, commission, or political subdivision. You do not lien a public school RTU job. The remedy is a claim against the payment bond required by F.S. 255.05 , taught in section 13.3.

A lessee who contracts for improvements is an owner (713.01 and 713.13(1)(a)3.) and must be listed as owner with a statement that the interest is a leasehold . HVAC contractors who contract with a tenant to set a package unit on a leased strip-center roof are liening the leasehold unless the fee owner has also contracted or authorized the improvement in a way that supports a lien on the fee. That is a fact pattern, not a loophole around public property: a school board is still not an “owner” under 713.01(24).

HVAC equipment and specially fabricated materials

F.S. 713.01(15) defines improve to include building, altering, repairing, furnishing materials, performing labor on the improvements, and equipping an improvement with fixtures or permanent apparatus . A rooftop unit, air handler, condensing unit, chiller, cooling tower, and ductwork that become part of the building's permanent HVAC plant are improvements. F.S. 713.01(16) defines improvement as any building, structure, construction, demolition, excavation, or any part thereof done on land for its permanent benefit.

F.S. 713.01(14) defines furnish materials to include materials incorporated in the improvement, including normal wastage; specially fabricated materials for incorporation in the improvement (not design work, submittals, or the like preliminary to actual fabrication); materials used for construction and not remaining, diminished by salvage value; and rental equipment , but not handtools . Delivery of materials to the site of the improvement is prima facie evidence of incorporation . That sentence is why a supply house that drops a 10-ton condenser at the curb has a lien path even if the installing contractor later walks off.

Special-order HVAC equipment is the high-yield application. A custom 40-ton packaged rooftop, a built-to-order air handler with a specified coil, or a chiller fabricated off site for a particular Fort Myers hospital is specially fabricated material . F.S. 713.08(1)(c) requires that materials specially fabricated at a place other than the site for incorporation in the improvement but not so incorporated , and the contract price or value thereof, be separately stated in the claim of lien. A supplier who special-orders an 80-ton chiller that never leaves the factory still has a statutory path, but the claim of lien must break that amount out. Class B candidates still need this theory; installing a 40-ton or 80-ton unit is Class A work under F.S. 489.105(3)(f)–(g) — Class B is limited to 25 tons of cooling and 500,000 Btu of heating in any one system . The lien statute does not expand the license.

Final furnishing (F.S. 713.01(12) ) is the last date the lienor furnishes labor, services, or materials. That date may not be measured by a certificate of occupancy or a certificate of final completion, and it does not include correction of deficiencies in the lienor's previously performed work or materials. Returning to fix a leaking condensate pan does not restart the 90-day claim-of-lien clock. For rental equipment, final furnishing is the date the equipment was last on the site and available for use.

Priority when the money is short

When the unpaid claims exceed what the owner still owes on the direct contract, F.S. 713.06(4) ranks payment: (1) liens of all laborers ; (2) liens of all persons other than the contractor ; (3) the lien of the contractor . A class is allowed in full before the next class gets anything. Inside a class that cannot be paid in full, claims are pro rata . If the same labor, services, or materials are covered by more than one class, they are allowed only in the earliest class; if covered by two lienors of the same class, only in the lien of the lienor farthest removed from the contractor. HVAC takeaway: unpaid helpers on the roof outrank the unpaid supply house, who outrank the unpaid prime contractor, all inside the direct-contract price cap.

Florida HVAC scenario

Elena's certified Class A company, Gulf Breeze Mechanical, signs a $186,000 direct contract with a private clinic owner in Pensacola to install a 40-ton rooftop — Class A work. Elena is in privity . She does not serve a Notice to Owner. She will need a contractor's final payment affidavit at least 5 days before any suit. She buys a special-order RTU from Panhandle Supply. Panhandle is a materialman not in privity and must serve a Notice to Owner within 45 days of commencing to furnish. Tomas, a registered Class B sub Elena hired for the under-25-ton split in the clinic annex, is a subcontractor not in privity and must serve his own Notice to Owner. The helper who only brazes is a laborer and is excepted from the NTO. If the same 40-ton RTU were instead a public school replacement, none of them liens the school board's real property. They look to the 255.05 bond.

Loading diagram... Privity, public property, and who must serve a Notice to Owner