Study guide
28.1 Wiring Single-Phase & Three-Phase Equipment
Florida HVAC Contractor License Class A/B
Track your progress as you read
Finished sections get a check mark.
1 Introduction & Exam Overview
1.1 Current Exam Facts & License Classes 1.2 Exam Format, Open-Book Rules & Pearson VUE 1.3 Eligibility, Experience Paths & Financial Responsibility
2 Establishing the Contracting Business
2.1 Business Organizational Structure 2.2 Business Plan, Marketplace & License Scope 2.3 Professionals, Fixed Assets & Bonding
3 Insurance for Florida HVAC Contractors
3.1 Obtaining Insurance (GL, Workers' Compensation & Bonds) 3.2 Coverages, Limits & Policy Language 3.3 Maintaining Insurance & CILB Certificate-Holder Rules
4 Overhead, Staffing & Markets
4.1 Developing the Business, Staffing & Markets 4.2 Determining Business Overhead (FICA, FUTA, SUTA, Workers' Comp, Rent & Utilities) 4.3 Determining Outsourced Services
5 Bids, Proposals & Estimating
5.1 Preparing Bids and Proposals 5.2 AIA Documents, Offers & Contract Components 5.3 Labor Productivity, Overhead & Project Costing
6 Purchasing, Invoices, Draws & Safety Programs
6.1 Purchasing Materials, UCC & Inventory (FIFO) 6.2 Invoices, Draw Requests & Percentage of Completion 6.3 Developing a Safety Program (OSHA, SDS & Drug Testing)
7 Managing Contracts
7.1 Contract Law, Scope & Completion Schedules 7.2 Florida Lien Law Inside Contracting 7.3 Mediation, Arbitration, Tort Law & Risk
8 Managing Trade Operations
8.1 Scheduling Trade Operations (CPM, RFI & Submittals) 8.2 OSHA Records, Document Retainage & Penalties 8.3 Takeoffs, Equipment Lease vs Purchase & Inventory
9 Accounting I: Receivables, Payables & Cash
9.1 Managing Accounts Receivable 9.2 Managing Accounts Payable & Discounts 9.3 Cash Flow, Banking & Financial Ratios
10 Accounting II: Taxes, Job Cost & Payroll
10.1 Filing Tax Forms & Returns 10.2 Tracking Job Costs 10.3 Payroll, Employment Taxes & Garnishments
11 Managing Human Resources
11.1 Hiring, I-9, Background Checks & Discrimination 11.2 HR Policies, OSHA & Drug-Test Chain of Custody 11.3 Evaluating Employees
12 Florida Contractor Law: Chapter 489 & 61G4
12.1 Chapter 489: Certified vs Registered & Qualifying Agents 12.2 61G4 Board Rules, Advertising & Discipline 12.3 Qualifying Agent Duties, Supervision & Additional Entities
13 Florida Construction Lien Law (Chapter 713)
13.1 Construction Lien Overview & Claimants 13.2 Notices to Owner, Time Limits & Perfecting Liens 13.3 Payment Bonds, Waivers & Claims of Lien
14 Financial Responsibility, CE & Federal Rules
14.1 Financial Responsibility & the 660 FICO Rule 14.2 Continuing Education & Biennial Renewal 14.3 Federal Employment, Immigration, OSHA & Environmental Rules
15 Plans, Specs & Equipment Selection
15.1 Reading Plans, Specifications, Symbols & Scales 15.2 Recommending Plan Changes & Equipment Types 15.3 EER, SEER, ARI Listings & Cost Effectiveness
16 Energy Codes, Loads & Thermal Resistance
16.1 Florida Energy Codes, R-Values & U-Factors 16.2 Determining HVAC Heating & Cooling Loads 16.3 Applying Energy Conservation, Fan Curves & Pump Curves
17 HVAC System & Duct Design
17.1 Designing HVAC Systems (Psychrometrics, Enthalpy & Airflow) 17.2 Designing Duct Systems & Insulation 17.3 Selecting Equipment, Location & Codes
18 Piping, Pumps, Boilers, Controls & Rigging Design
18.1 Pipe Sizing, Valves, Fittings, Sealants & Layout 18.2 Control Requirements, Fan Motors, CFM & Compressor Capacity 18.3 Pumps, Boilers, Steam, Fuel & Pipe Insulation 18.4 Grease Ducts, Live Loads, Rigging & Mechanical Equipment
19 Sheet Metal Duct Fabrication
19.1 Fabricating Rectangular & Round Ducts 19.2 Seams, Locks, Taping, Mastics & Liners 19.3 Fittings, Outlets & Grilles 19.4 Kitchen Hoods, Exhausts & Drain Pans
20 Split, Package & Heat Pump Installation
20.1 Installing Split & Package Air Conditioners 20.2 Installing Split & Package Heat Pumps 20.3 Air-Cooled vs Water-Cooled Systems
21 Large Systems, Chillers & Towers
21.1 Installing by Tonnage & Class A vs Class B Limits 21.2 Chilled Water, Water Towers & Secondary Coolant 21.3 Centrifugal, Absorption & Ammonia Systems
22 Refrigeration, Coolers, Ventilation & Controls Install
22.1 Low, Medium & Ultra-Low Temperature Systems & EPA Rules 22.2 Walk-In & Reach-In Coolers 22.3 Ventilation, Exhaust, Makeup Air, Grease Ducts & Kitchen Exhaust 22.4 Geothermal, Pneumatic & DDC Controls, TAB & Smoke Tests
23 Condensers, Compressors & Air Handlers
23.1 Installing Air-Cooled & Water-Cooled Condensers 23.2 Hermetic, Semi-Hermetic & Centrifugal Compressors 23.3 Air Handlers, Evaporators, Heat Exchangers, Receivers & Heat Strips
24 Duct, Fans, Filters & Terminals
24.1 Installing Sheet Metal, Fiberglass & Flexible Duct 24.2 Fans, Blowers, Motors, Grilles, Registers & Fire Dampers 24.3 Filters, Flues, Warm-Air, Gas & Fuel-Oil Appliances
25 Refrigerant Piping & Joining
25.1 Refrigerant Piping, Copper Tubing & Pipe Sizing 25.2 Brazing, Welding, Flaring, Swaging & Soldering 25.3 Steel Pipe, Plastic Pipe, Threading & Oxy-Acetylene 25.4 Hangers, Supports, Horizontally Supported Piping & Pressure Testing
26 Metering Devices & Line Components
26.1 TXVs, Capillary Tubes, Reversing Valves & Metering Devices 26.2 Liquid, Suction & Heat-Pump Dryers, Filters & Oil Traps 26.3 Receivers, Heat Strips, Gas/Oil Appliances & Related Accessories
27 Controls Installation
27.1 Pressure, Temperature, Humidity & Bellows Controls 27.2 Thermostats, Humidistats, Pneumatic & Solid-State Controls 27.3 Transformers, Capacitors, Contactors, Relays & Safety Disconnects 27.4 Defrost Components, Starters, Solenoids & Limit Switches
28 Motors, Wiring & Electrical Installation
28.1 Wiring Single-Phase & Three-Phase Equipment 28.2 Motor Types, Protection, Controllers, Belts & Pulleys 28.3 Geothermal Loops, Surge Protectors, Phase Monitors & Plastic Pipe
29 Diagnostic Analysis: Refrigeration
29.1 Pressure-Enthalpy Diagrams & Operating Pressures 29.2 Air Volumes, Enthalpy, Wet-Bulb & Dry-Bulb 29.3 Leak Detection & Refrigeration Test Instruments
30 Diagnostic Analysis: Electrical & Instruments
30.1 Current Draw, Voltage, Power & Motor Terminals 30.2 Testing Relays, Capacitors, Starters, Transformers & Defrost Stats 30.3 Using Amprobes, Velometers, Pitot Tubes, Manometers & Gauges
31 Recovery, Repair & Calibration
31.1 Nitrogen & Gas Regulators, Recovery & Retrofit 31.2 Repairing Hermetic, Semi-Hermetic, Centrifugal Compressors & Blowers 31.3 Calibrating Thermostats, Pressure Switches & Pneumatic Controls 31.4 Superheat, Safety Cutouts, Defrost Clocks & Freezer Controls
32 Mechanical Service & Cleaning
32.1 Belts, Pulleys, Motor Rotation & Seized Compressors 32.2 Crankcase & Evaporator Pressure Regulators & Unloaders 32.3 Cleaning Towers, Condensers, Foreign Matter & Condensate Drains
33 Jobsite Safety & Equipment
33.1 PPE: Hearing, Head, Eye, Face & Respiratory Protection 33.2 Lockout/Tagout, Warning Signs, Toxic Materials & Ventilation 33.3 Rigging, Hoists, Cranes, Forklifts, Backhoes & Excavation 33.4 Ladders, Scaffolds, Tools & Air Compressors
34 Energy Management
34.1 Envelope, Duct Pressure & Blower-Door Testing 34.2 Efficient Equipment, Zoning, ERVs, Wi-Fi Thermostats & Green Buildings 34.3 Energy Forms, R/U Factors, Window Heat Gain & Florida Load Calcs
35 Indoor Air Quality
35.1 Ventilation, Filtration, Humidity, UV & Air Cleaners 35.2 Contaminants, Source Control, TAB & Human Health Effects
28.1 Wiring Single-Phase & Three-Phase Equipment
Key Takeaways Explain This Topic AI
F.S. 489.105(3)(f) and (g) let Class A and Class B replace, disconnect, or reconnect power wiring on the line or load side of a dedicated existing electrical disconnect on single-phase systems; repair or replace dedicated HVAC-circuit wiring, disconnects, breakers, or fuses with a circuit-breaker lock; and install low-voltage HVAC control wiring. Electrical power wiring beyond those grants is not HVAC work.
Ohm's law is V = I × R. Single-phase power is P = V × I (watts). Three-phase power is P = 1.73 × V × I × power factor. Nameplate MCA is the smallest circuit the listing allows; MOCP is the largest overcurrent device.
RLA is the hermetic-compressor nameplate current used to size the circuit; FLA is a fan, pump, or open motor at rated load; LRA is locked-rotor inrush, commonly four to eight times RLA or FLA.
Reverse a three-phase motor by swapping any two of the three power leads. The single-phase existing-disconnect grant does not cover three-phase power wiring — subcontract new 208/230/460-volt feeders and typical three-phase reconnects to a licensed electrical contractor.
Last updated: August 2026
28.1 Wiring Single-Phase & Three-Phase Equipment
Trade Area D ( Equipment Component Installation ) is 14 percent of both Class A and Class B . After condensers, compressors, ducts, piping, and the control parts in Chapter 27, the outline asks you to wire single-phase equipment , wire three-phase equipment , install single-phase equipment , and install three-phase equipment . The 2026 Air Conditioning CBT books that carry this cluster are Refrigeration & Air Conditioning Technology , 9th Edition (2021), and Florida Building Code — Mechanical, 2023 (including Section 301.10 , which sends mechanical electrical work to the adopted NFPA 70 ). F.S. 489.105 is the license fence that decides which of those wires an air-conditioning contractor may actually pull. Chapter 27.3 already selected transformers, capacitors, contactors, and the safety disconnect. This section is the circuit : Ohm's law, nameplate currents, single-phase versus three-phase, rotation, and when to call an electrician.
Quick Answer: V = I × R . Read RLA on hermetic compressors, FLA on fans and pumps, LRA at locked rotor. Land the circuit at or above MCA and protect at or below MOCP . Class A and Class B may work the line or load of a dedicated existing single-phase disconnect , repair a dedicated HVAC circuit with a breaker lock , and run low-voltage controls. Swap any two leads to reverse a three-phase motor. New three-phase building power is an electrical contractor.
F.S. 489.105 — the electrical fence before a lug is landed
Class A ( 489.105(3)(f) ) and Class B ( 489.105(3)(g) ) may:
Replace, disconnect, or reconnect power wiring on the line or load side of a dedicated existing electrical disconnect switch on single-phase electrical systems.
Repair or replace power wiring, disconnects, breakers, or fuses for dedicated HVAC circuits with proper use of a circuit-breaker lock .
Install, disconnect, and reconnect low-voltage heating, ventilating, and air-conditioning control wiring .
The same subsections then exclude electrical power wiring as a building trade. Unlimited Class A tonnage does not create unlimited electrical authority. The existing-disconnect grant is single-phase only . A 208/230/460-volt three-phase reconnect at a rooftop disconnect, a new feeder from switchgear, and a shared lighting homerun used as “the HVAC circuit” are the usual failures. The breaker lock is the statutory tool that keeps a dedicated HVAC circuit dedicated while you replace a burned whip, a fused disconnect, or the HVAC breaker itself. OSHA lockout/tagout (Chapter 33) still applies; the CILB card is not a substitute for LOTO.
FBC Mechanical 301.10 still wants the electrical installation to match the listing and the adopted electrical code. HVAC reads the nameplate , lands what 489.105 allows, and subcontracts the rest. Class B’s 25-ton / 500,000 Btu cap (F.S. 489.105(3)(g) ) is a separate fence: a 20-ton 460-volt RTU can be inside Class B tons and still be outside Class B electrical scope for the three-phase feeder.
Ohm's law, power, and the currents on the nameplate
Ohm's law relates voltage ( V , volts), current ( I , amperes), and resistance ( R , ohms):
V = I × R I = V / R R = V / I V = I \times R \qquad I = V / R \qquad R = V / I V = I × R I = V / R R = V / I
Power in watts:
Single-phase: P = V × I P = V \times I P = V × I (true power also multiplies power factor ; resistive heat strips are near PF = 1).
Three-phase: P = 1.73 × V × I × PF P = 1.73 \times V \times I \times \text{PF} P = 1.73 × V × I × PF ( 1.73 is 3 \sqrt{3} 3 ).
Also: P = I 2 R P = I^{2}R P = I 2 R and P = V 2 / R P = V^{2}/R P = V 2 / R .
Mechanical horsepower on a motor nameplate is output . Electrical input watts ÷ 746 is not the same number unless efficiency is 100 percent.
Worked single-phase. A 240-volt heat strip draws 20 A . Resistance is (240 / 20 = 12) ohms. Power is 240 × 20 = 4,800 240 \times 20 = 4{,}800 240 × 20 = 4 , 800 W, which is 4.8 kW (about 16,400 Btu/h at 3,413 Btu/h per kW). If the measured current is 24 A on the same 240-volt circuit, something is wrong — shorted element, wrong voltage, or a failed limit — not “extra capacity.”
Worked three-phase. A 460-volt three-phase blower draws 10 A at PF 0.85 :
P = 1.73 × 460 × 10 × 0.85 ≈ 6,764 W ≈ 6.8 kW P = 1.73 \times 460 \times 10 \times 0.85 \approx 6{,}764\ \text{W} \approx 6.8\ \text{kW} P = 1.73 × 460 × 10 × 0.85 ≈ 6 , 764 W ≈ 6.8 kW
That is input. Do not stamp it on a bid as “9 horsepower” (6,764 / 746 ≈ 9) unless you have also applied efficiency .
Nameplate current words are not interchangeable:
Marking What it is Where you see it Field use
FLA (full-load amps) Current at rated load, voltage, and HP Fans, pumps, open motors Size overloads and compare running amps
RLA (rated-load amps) Hermetic-compressor listing current Compressors Circuit math and running-amp comparison — not FLA
LRA (locked-rotor amps) Current with the rotor stalled Compressors and motors Start inrush; typically 4–8× RLA/FLA
MCA (minimum circuit ampacity) Smallest conductor/circuit the listing allows HVAC equipment nameplate Do not land a circuit below MCA
MOCP (maximum overcurrent protection) Largest fuse or breaker the listing allows Same nameplate Do not protect above MOCP
A hermetic that shows RLA 16.7 / LRA 79 / MCA 21 / MOCP 35 is a 16.7-amp running listing, not a 16.7-amp fuse. LRA 79 is why a clamp meter “spikes” on start and why MOCP is larger than MCA. Typical listing math (UL / nameplate method, also the RAT story) puts MCA near 125 percent of compressor RLA plus other FLA . You still use the printed MCA and MOCP ; you do not invent a breaker from a forum “175 percent” rule that exceeds the stencil.
Running amps well above RLA with normal suction and head is a motor or capacitor problem (Chapter 27.3). Running amps well below RLA with a hot, short-cycling compressor can be an open start winding , a failed start device, or a single-phased three-phase machine — not a “light load bonus.”
Wiring and installing single-phase equipment
Florida residential and light-commercial splits are usually 240-volt single-phase : two ungrounded legs ( L1, L2 ), 240 V between them, and an equipment grounding conductor . A neutral appears when the cabinet also has 120-volt loads (some crankcase heaters, some transformers). Do not land a 240-volt compressor across one hot and a neutral . Do not use the ground as a neutral.
The equipment disconnect is listed, lockable , and within sight of the unit (Chapter 27.3). On a changeout , Class A or Class B may work line and load of that dedicated existing single-phase disconnect . Replace a burned whip (often liquidtight flexible conduit with strain relief), a fused pullout, or pitted lugs. Put the circuit-breaker lock on the dedicated HVAC breaker while the cover is off. If the outdoor unit is hanging on a shared 20-amp lighting circuit , that is not a dedicated HVAC circuit — stop and get the circuit made dedicated (electrical contractor if it is new building power).
Compressor terminals on a single-phase hermetic are C (common), S (start), R (run). Identify them with an ohmmeter on an isolated compressor:
Highest resistance is S to R (start winding plus run winding).
C to S is the start winding (higher than C to R).
C to R is the run winding (lowest).
Check: ( C – S ) + ( C – R ) = ( S – R ) (C\text{–}S) + (C\text{–}R) = (S\text{–}R) ( C – S ) + ( C – R ) = ( S – R ) .
A run capacitor sits between S and R (HERM to S, C to the capacitor common — dual cans also feed the fan). A start capacitor and start relay are intermittent (Chapter 27.3). Ground the cabinet to the green screw. Tape or listed connectors on low-voltage R, C, Y, G, W/O/B stay inside the HVAC grant.
Install the single-phase machine as Chapter 20 taught (pad, wind, clearances) and then land power: MCA circuit, MOCP device, within-sight disconnect, tight lugs, drip loop, strain relief, and a whip that is not a chewed NM cable lying in a puddle. Dual-voltage 115/230 motors must be jumpered for the actual site voltage — a 115-volt connection on 230 V is a one-time event.
Wiring and installing three-phase equipment — and when you subcontract
Three-phase HVAC in Florida is commonly 208 V , 230/240 V , or 460/480 V , three ungrounded conductors plus ground (a neutral only if 120/277-volt loads live in the same cabinet). Line-to-line voltage is what the motor nameplate must match. A 208-volt motor on 230 V runs hot; a 460-volt motor on 208 V will not start.
Dual-voltage three-phase motors (often 230/460 , nine leads) reconnect wye or parallel for low voltage and series for high voltage. Use the connection diagram on the motor, not a memory of “T4 to T5.” Wrong reconnect is a smoked winding, not a “high-voltage option.”
Rotation. A three-phase motor reverses if you swap any two of the three power leads . That is the exam sentence. Scroll compressors and some pumps are rotation-sensitive : reverse rotation makes noise, low oil pressure, and almost no capacity. Check rotation momentarily before leaving a new three-phase blower or compressor in auto. Swapping one lead does nothing useful. Swapping leads on single-phase does not reverse a PSC compressor; reverse a belt-driven single-phase fan by changing the mechanical drive or a reversing switch the listing provides, not by swapping L1 and L2 on a run-cap motor that is not built to reverse.
Single-phasing is the loss of one of the three legs. The motor may keep turning on the remaining phases while those windings overheat . Overloads in each phase (Chapter 27.4) and a phase monitor (Section 28.3) are the protections. Oversizing heaters “so it stops tripping” is how you buy a rewind.
Install a three-phase RTU, chiller, or tower fan as a machine inside Class A/B tonnage , but treat power wiring as the fence: specify MCA/MOCP, confirm the electrical contractor’s feeder and disconnect, land low-voltage controls yourself, bump rotation, and set the phase monitor. Do not pull a new 460-volt feeder from the switchgear on an HVAC ticket. Do not treat the single-phase existing-disconnect grant as a three-phase grant. Class B still owes this theory on a 40-ton 460-volt plant; Class B does not contract that plant as one system.
Florida HVAC scenario
Palm Coast Comfort, certified Class B in Volusia County, change-outs a 3-ton 240-volt single-phase split. The pad disconnect is dedicated and within sight. The helper may work line and load of that disconnect, replace the whip, lock the HVAC breaker, land 24-volt thermostat cable, and read the new nameplate: RLA 14.1, LRA 72, MCA 18.4, MOCP 30 . The existing 25-amp breaker is between MCA and MOCP — legal if the conductor still meets MCA. A clamp meter that shows 70 A for a few cycles on start is LRA , not a short. The owner also wants a 20-ton 460-volt three-phase RTU on the strip center (inside the 25-ton Class B cap). The HVAC shop may set the cabinet, ducts, condensate, and controls, and must know that swapping two leads reverses the supply fan — but the new three-phase feeder and disconnect belong to a licensed electrical contractor . If the helper “just lands T1-T2-T3” on a nine-lead 230/460 motor using the 230-volt diagram on a 460-volt site, the motor dies on the first call. If the same drawings showed a 30-ton RTU, Class B would stop at the bid table (F.S. 489.105(3)(g) ) even before the electrician is called.
Traps: (1) Treating RLA as FLA or as the fuse size. (2) Circuit below MCA or breaker above MOCP. (3) Using the ground as a neutral. (4) Calling LRA a short. (5) Pulling a new 460-volt feeder on an HVAC ticket. (6) Expecting L1-L2 swap to reverse a single-phase compressor. (7) Class B on a 30-ton three-phase plant because “we understand rotation.”