Study guide

15.1 Reading Plans, Specifications, Symbols & Scales

Florida HVAC Contractor License Class A/B

Track your progress as you read

Finished sections get a check mark.

1 Introduction & Exam Overview

1.1 Current Exam Facts & License Classes 1.2 Exam Format, Open-Book Rules & Pearson VUE 1.3 Eligibility, Experience Paths & Financial Responsibility

2 Establishing the Contracting Business

2.1 Business Organizational Structure 2.2 Business Plan, Marketplace & License Scope 2.3 Professionals, Fixed Assets & Bonding

3 Insurance for Florida HVAC Contractors

3.1 Obtaining Insurance (GL, Workers' Compensation & Bonds) 3.2 Coverages, Limits & Policy Language 3.3 Maintaining Insurance & CILB Certificate-Holder Rules

4 Overhead, Staffing & Markets

4.1 Developing the Business, Staffing & Markets 4.2 Determining Business Overhead (FICA, FUTA, SUTA, Workers' Comp, Rent & Utilities) 4.3 Determining Outsourced Services

5 Bids, Proposals & Estimating

5.1 Preparing Bids and Proposals 5.2 AIA Documents, Offers & Contract Components 5.3 Labor Productivity, Overhead & Project Costing

6 Purchasing, Invoices, Draws & Safety Programs

6.1 Purchasing Materials, UCC & Inventory (FIFO) 6.2 Invoices, Draw Requests & Percentage of Completion 6.3 Developing a Safety Program (OSHA, SDS & Drug Testing)

7 Managing Contracts

7.1 Contract Law, Scope & Completion Schedules 7.2 Florida Lien Law Inside Contracting 7.3 Mediation, Arbitration, Tort Law & Risk

8 Managing Trade Operations

8.1 Scheduling Trade Operations (CPM, RFI & Submittals) 8.2 OSHA Records, Document Retainage & Penalties 8.3 Takeoffs, Equipment Lease vs Purchase & Inventory

9 Accounting I: Receivables, Payables & Cash

9.1 Managing Accounts Receivable 9.2 Managing Accounts Payable & Discounts 9.3 Cash Flow, Banking & Financial Ratios

10 Accounting II: Taxes, Job Cost & Payroll

10.1 Filing Tax Forms & Returns 10.2 Tracking Job Costs 10.3 Payroll, Employment Taxes & Garnishments

11 Managing Human Resources

11.1 Hiring, I-9, Background Checks & Discrimination 11.2 HR Policies, OSHA & Drug-Test Chain of Custody 11.3 Evaluating Employees

12 Florida Contractor Law: Chapter 489 & 61G4

12.1 Chapter 489: Certified vs Registered & Qualifying Agents 12.2 61G4 Board Rules, Advertising & Discipline 12.3 Qualifying Agent Duties, Supervision & Additional Entities

13 Florida Construction Lien Law (Chapter 713)

13.1 Construction Lien Overview & Claimants 13.2 Notices to Owner, Time Limits & Perfecting Liens 13.3 Payment Bonds, Waivers & Claims of Lien

14 Financial Responsibility, CE & Federal Rules

14.1 Financial Responsibility & the 660 FICO Rule 14.2 Continuing Education & Biennial Renewal 14.3 Federal Employment, Immigration, OSHA & Environmental Rules

15 Plans, Specs & Equipment Selection

15.1 Reading Plans, Specifications, Symbols & Scales 15.2 Recommending Plan Changes & Equipment Types 15.3 EER, SEER, ARI Listings & Cost Effectiveness

16 Energy Codes, Loads & Thermal Resistance

16.1 Florida Energy Codes, R-Values & U-Factors 16.2 Determining HVAC Heating & Cooling Loads 16.3 Applying Energy Conservation, Fan Curves & Pump Curves

17 HVAC System & Duct Design

17.1 Designing HVAC Systems (Psychrometrics, Enthalpy & Airflow) 17.2 Designing Duct Systems & Insulation 17.3 Selecting Equipment, Location & Codes

18 Piping, Pumps, Boilers, Controls & Rigging Design

18.1 Pipe Sizing, Valves, Fittings, Sealants & Layout 18.2 Control Requirements, Fan Motors, CFM & Compressor Capacity 18.3 Pumps, Boilers, Steam, Fuel & Pipe Insulation 18.4 Grease Ducts, Live Loads, Rigging & Mechanical Equipment

19 Sheet Metal Duct Fabrication

19.1 Fabricating Rectangular & Round Ducts 19.2 Seams, Locks, Taping, Mastics & Liners 19.3 Fittings, Outlets & Grilles 19.4 Kitchen Hoods, Exhausts & Drain Pans

20 Split, Package & Heat Pump Installation

20.1 Installing Split & Package Air Conditioners 20.2 Installing Split & Package Heat Pumps 20.3 Air-Cooled vs Water-Cooled Systems

21 Large Systems, Chillers & Towers

21.1 Installing by Tonnage & Class A vs Class B Limits 21.2 Chilled Water, Water Towers & Secondary Coolant 21.3 Centrifugal, Absorption & Ammonia Systems

22 Refrigeration, Coolers, Ventilation & Controls Install

22.1 Low, Medium & Ultra-Low Temperature Systems & EPA Rules 22.2 Walk-In & Reach-In Coolers 22.3 Ventilation, Exhaust, Makeup Air, Grease Ducts & Kitchen Exhaust 22.4 Geothermal, Pneumatic & DDC Controls, TAB & Smoke Tests

23 Condensers, Compressors & Air Handlers

23.1 Installing Air-Cooled & Water-Cooled Condensers 23.2 Hermetic, Semi-Hermetic & Centrifugal Compressors 23.3 Air Handlers, Evaporators, Heat Exchangers, Receivers & Heat Strips

24 Duct, Fans, Filters & Terminals

24.1 Installing Sheet Metal, Fiberglass & Flexible Duct 24.2 Fans, Blowers, Motors, Grilles, Registers & Fire Dampers 24.3 Filters, Flues, Warm-Air, Gas & Fuel-Oil Appliances

25 Refrigerant Piping & Joining

25.1 Refrigerant Piping, Copper Tubing & Pipe Sizing 25.2 Brazing, Welding, Flaring, Swaging & Soldering 25.3 Steel Pipe, Plastic Pipe, Threading & Oxy-Acetylene 25.4 Hangers, Supports, Horizontally Supported Piping & Pressure Testing

26 Metering Devices & Line Components

26.1 TXVs, Capillary Tubes, Reversing Valves & Metering Devices 26.2 Liquid, Suction & Heat-Pump Dryers, Filters & Oil Traps 26.3 Receivers, Heat Strips, Gas/Oil Appliances & Related Accessories

27 Controls Installation

27.1 Pressure, Temperature, Humidity & Bellows Controls 27.2 Thermostats, Humidistats, Pneumatic & Solid-State Controls 27.3 Transformers, Capacitors, Contactors, Relays & Safety Disconnects 27.4 Defrost Components, Starters, Solenoids & Limit Switches

28 Motors, Wiring & Electrical Installation

28.1 Wiring Single-Phase & Three-Phase Equipment 28.2 Motor Types, Protection, Controllers, Belts & Pulleys 28.3 Geothermal Loops, Surge Protectors, Phase Monitors & Plastic Pipe

29 Diagnostic Analysis: Refrigeration

29.1 Pressure-Enthalpy Diagrams & Operating Pressures 29.2 Air Volumes, Enthalpy, Wet-Bulb & Dry-Bulb 29.3 Leak Detection & Refrigeration Test Instruments

30 Diagnostic Analysis: Electrical & Instruments

30.1 Current Draw, Voltage, Power & Motor Terminals 30.2 Testing Relays, Capacitors, Starters, Transformers & Defrost Stats 30.3 Using Amprobes, Velometers, Pitot Tubes, Manometers & Gauges

31 Recovery, Repair & Calibration

31.1 Nitrogen & Gas Regulators, Recovery & Retrofit 31.2 Repairing Hermetic, Semi-Hermetic, Centrifugal Compressors & Blowers 31.3 Calibrating Thermostats, Pressure Switches & Pneumatic Controls 31.4 Superheat, Safety Cutouts, Defrost Clocks & Freezer Controls

32 Mechanical Service & Cleaning

32.1 Belts, Pulleys, Motor Rotation & Seized Compressors 32.2 Crankcase & Evaporator Pressure Regulators & Unloaders 32.3 Cleaning Towers, Condensers, Foreign Matter & Condensate Drains

33 Jobsite Safety & Equipment

33.1 PPE: Hearing, Head, Eye, Face & Respiratory Protection 33.2 Lockout/Tagout, Warning Signs, Toxic Materials & Ventilation 33.3 Rigging, Hoists, Cranes, Forklifts, Backhoes & Excavation 33.4 Ladders, Scaffolds, Tools & Air Compressors

34 Energy Management

34.1 Envelope, Duct Pressure & Blower-Door Testing 34.2 Efficient Equipment, Zoning, ERVs, Wi-Fi Thermostats & Green Buildings 34.3 Energy Forms, R/U Factors, Window Heat Gain & Florida Load Calcs

35 Indoor Air Quality

35.1 Ventilation, Filtration, Humidity, UV & Air Cleaners 35.2 Contaminants, Source Control, TAB & Human Health Effects

15.1 Reading Plans, Specifications, Symbols & Scales

Key Takeaways Explain This Topic AI

Pearson VUE requires every Air Conditioning A and B Trade Knowledge candidate to bring an architect's scale that includes 1/4 inch and 1/8 inch; those two scales are the exam's HVAC floor-plan scales.

At 1/4 inch = 1 foot-0 inches, each inch on paper is 4 feet in the field; a line that measures 4 1/2 inches on that drawing is 18 feet-0 inches long.

At 1/8 inch = 1 foot-0 inches, each inch on paper is 8 feet in the field; using the 1/8 edge on a 1/4-inch drawing doubles the takeoff and wrecks duct, pipe, and crane estimates.

Duct tags on mechanical plans are width by height (for example 16×12) plus airflow in cubic feet per minute; the title-block scale, the sheet legend, and Division 23 of the specifications all control the same installation.

Conflicts among drawings, specifications, and addenda are resolved by a written request for information, not by field guesswork; addenda issued before bid opening become part of the contract documents.

Last updated: August 2026

15.1 Reading Plans, Specifications, Symbols & Scales

Trade Area A (Pre-Installation) is 14 percent of the Class A trade exam and 12 percent of Class B . The first cluster is not a compressor question. It is whether you can read a set of mechanical drawings, convert a scaled line to a field dimension, match a symbol to a damper or diffuser, and reconcile that sheet with the written specifications. The 2026 Air Conditioning CBT reference list that supports this chapter is the Florida Building Code — Mechanical, 2023 (8th Edition), the Florida Building Code — Energy Conservation, 2023 , Energy Efficient Building Construction in Florida (2024) , and Refrigeration & Air Conditioning Technology , 9th Edition (2021). The DBPR/PTI candidate notice is blunt: all candidates bring an architect's scale including 1/4 inch and 1/8 inch for Trade Knowledge. If you leave that scale in the truck, you are sitting the plan-reading items with a ruler you are not supposed to use.

Quick Answer: HVAC floor plans on this exam are almost always architect's scale , most often 1/4 inch = 1 foot-0 inches or 1/8 inch = 1 foot-0 inches . Read the title block first, pick that edge of the triangular scale, and convert. One inch on a 1/4-inch drawing is 4 feet in the building; one inch on a 1/8-inch drawing is 8 feet .

Contract documents are a set, not a picture

A permit set is not one sheet. For an HVAC job the contract documents typically include architectural floor plans and reflected ceiling plans, structural framing (for roof curbs, pads, and hanger loads), mechanical plans, equipment schedules, details, control diagrams, the project manual ( specifications ), and any addenda issued before bids. Under the usual AIA structure, those pieces are complementary. Quantity and location generally live on the drawings; quality, product requirements, and execution live in the specs. When they disagree, you do not pick the cheaper reading. You issue a written request for information (RFI) and, if you are still in bidding, you acknowledge the addendum that answers it.

CSI MasterFormat Division 23 is the HVAC specification division. Inside it you will see common-work results, insulation, controls, refrigerant piping, hydronic piping, metal and flexible duct, fans, terminals, and packaged equipment. A performance specification states capacity, efficiency, sound, and listing (for example “AHRI-certified split system, minimum 14.3 SEER2, capacity per the schedule”). A prescriptive specification names acceptable manufacturers and model families. Substituting a cheaper condenser after award, without a specified “or equal” process, is a specification breach, not value engineering.

Read every sheet in this order on the exam and on a real bid:

Title block. Project name, sheet number (M-1, M-2), drawn scale, revision date, and the design professional's seal.

General notes and legend. That sheet's symbols override “what our shop usually draws.”

Plan. Equipment tags, duct mains, piping, outdoor units, thermostats.

Schedule. Manufacturer, model, MBH, CFM, static, voltage, SEER2/EER2, MCA/MOCP, weight.

Details and sections. Curb, condensate, hanging, fire-damper sleeve — often at a larger scale such as 1/2 inch or 1 1/2 inches = 1 foot-0 inches.

Specifications and addenda. Efficiency, listed products, submittals, testing and balancing.

Architect's scale versus engineer's scale

An architect's scale is a triangular ruler whose faces are marked in fractions of an inch that represent one foot . The faces you must own for this exam are 1/4 inch = 1 foot-0 inches and 1/8 inch = 1 foot-0 inches . Other architect faces (1/2 inch, 3/8 inch, 3/16 inch, 3/32 inch, 3/4 inch, 1 inch, 1 1/2 inches, 3 inches) show up on details, not on whole-building HVAC floor plans. An engineer's scale is decimal: 1 inch = 10, 20, 30, 40, 50, or 60 feet. Site plans, underground chilled-water mains, and civil sheets use the engineer's scale. Putting an engineer's 20-scale on an architect's 1/4-inch mechanical plan is a guaranteed wrong takeoff.

On a triangular architect's scale, 1/4 inch and 1/8 inch share one edge, running in opposite directions . The zero is inset from the end. To the left (or right) of zero is a fully divided foot, marked in inches. To use it: identify the title-block scale, turn the scale so that edge faces you, set the 0 on one end of the line, read whole feet on the open scale, then read leftover inches on the subdivided foot. If you accidentally use the 1/8 numbers on a 1/4-inch drawing, every length doubles.

Worked scale example — 1/4 inch = 1 foot-0 inches

A mechanical plan is labeled SCALE: 1/4" = 1'-0" . You are taking off a supply main from the air-handler discharge to a fire damper. The paper distance, measured with the 1/4-inch edge, is 4 1/2 inches .

Conversion rule: 1/4 inch on paper = 1 foot in the field, so 1 inch on paper = 4 feet .

4.5 in × 4 ft/in = 18 ft 4.5 \text{ in} \times 4 \text{ ft/in} = 18 \text{ ft} 4.5 in × 4 ft/in = 18 ft

The run is 18 feet-0 inches . If you need inches leftover, convert the fractional paper inch the same way: 1/8 inch on this drawing is 6 inches in the field (because 1/8 ÷ 1/4 = 1/2 foot). A paper measurement of 5 3/8 inches is 5.375 × 4 = 21.5 5.375 \times 4 = 21.5 5.375 × 4 = 21.5 feet, which you report as 21 feet-6 inches of duct — plus fittings, which you do not get by scaling the centerline through an elbow as if it were a straight stick.

A rooftop unit service platform on the same sheet measures 3 1/2 inches by 2 1/4 inches :

  • Paper dimension × 4 ft per inch Field dimension
  • 3 1/2 in 14 14 ft-0 in
  • 2 1/4 in 9 9 ft-0 in
  • Area 14 × 9 126 sq ft

On a school first-floor plan drawn at 1/8 inch = 1 foot-0 inches , 1 inch on paper = 8 feet. A corridor supply trunk that measures 6 inches on paper is 48 feet in the field. A classroom that measures 2 inches by 2 1/2 inches is 16 feet by 20 feet, or 320 square feet — useful when you are checking whether the scheduled 2-ton unit is even in the right neighborhood before you trust the load printout.

Symbols, tags, and schedules

The legend on sheet M-0 (or the first mechanical sheet) is the dictionary for that job. Refrigeration & Air Conditioning Technology and SMACNA drawing practice use a stable core set. Learn the core; then still read the legend, because architects invent variants.

Symbol / tag Typical meaning on Florida HVAC plans Exam trap

Square with an X, or a square with four arrows Ceiling supply diffuser; CFM and neck size noted beside it Counting the architectural lighting symbol as a diffuser

Rectangle with diagonal hatch Return or transfer grille Assuming every hatch is return; exhaust is often a different hatch or an “E” tag

  • T in a circle or hexagon Thermostat Missing the zone it actually controls; the home-run may serve two rooms
  • Opposite triangles on a duct, tagged VD Volume (balancing) damper Confusing with a fire damper

FD or a damper in a rated wall with a sleeve note Fire damper (NFPA 90A/90B; FBC Mechanical Chapter 6) Scaling a fire damper as a volume damper and omitting the rated sleeve

Dashed or zigzag duct Flexible duct; length limited by spec and energy code practice Scaling 40 feet of flex because the line wiggles across the attic

16×12, 800 CFM Rectangular duct width × height in inches, airflow in cfm Reading 16×12 as 16 feet of 12-inch pipe

Solid vs dashed equipment box, tag AHU-1 / CU-1 / RTU-1 Air handler, condensing unit, packaged rooftop Installing the scheduled 208-volt unit on a 480-volt roof because the plan view “looked like last job”

Duct is drawn as a double line or a single line with a size tick. A plus or minus at a fitting, or a note “UP” / “DN,” tells you the offset. Pipe is a single line with a size and a service abbreviation: CLG, HWS/HWR, CHR/CHS, LP/HP steam, RL/SL for refrigerant liquid and suction. Do not scale refrigerant line length off a schematic that is not drawn to scale — many riser diagrams are NTS (not to scale) .

The equipment schedule is as much a drawing as the floor plan. It lists nominal tons, total and sensible MBH at a stated outdoor dry-bulb, evaporator CFM, external static, SEER2 or EER/IEER, electrical MCA and MOCP, and operating weight. FBC Mechanical requires equipment to be listed and labeled and installed per the listing. If the schedule says 4 tons at 14.3 SEER2 and the plan view shows a 3-ton pad, that is an RFI, not a 3-ton changeout.

Florida HVAC scenario

Gulf Breeze Mechanical, a certified Class B firm, bids a two-story medical office drawn at 1/8 inch = 1 foot-0 inches . The estimator's triangular scale is sitting on the 1/4-inch edge. A 3-inch paper run of 18×10 supply main is taken off as 12 feet instead of 24 feet . The shop fabricates 12-foot joints, the hangers land in the wrong bays, and the fire damper tagged at a rated corridor wall is 12 feet short of the wall. The specifications (Division 23) required SMACNA pressure class and a fire damper at every rated penetration. The title block said 1/8 inch. Nothing in FBC Mechanical 2023 lets you “average” two scales. The correct takeoff uses the 1/8-inch edge, converts 1 inch = 8 feet, and then reads the legend for the FD symbol before the duct is cut. The same set's schedule showed a 20-ton rooftop; Class B's 25-ton / 500,000 Btu cap still allowed that unit, but only if the estimator actually measured the roof well and the curb — both of which were on a 1/4-inch detail, not on the 1/8-inch floor plan.