Study guide

8.1 Scheduling Trade Operations (CPM, RFI & Submittals)

Florida HVAC Contractor License Class A/B

Track your progress as you read

Finished sections get a check mark.

1 Introduction & Exam Overview

1.1 Current Exam Facts & License Classes 1.2 Exam Format, Open-Book Rules & Pearson VUE 1.3 Eligibility, Experience Paths & Financial Responsibility

2 Establishing the Contracting Business

2.1 Business Organizational Structure 2.2 Business Plan, Marketplace & License Scope 2.3 Professionals, Fixed Assets & Bonding

3 Insurance for Florida HVAC Contractors

3.1 Obtaining Insurance (GL, Workers' Compensation & Bonds) 3.2 Coverages, Limits & Policy Language 3.3 Maintaining Insurance & CILB Certificate-Holder Rules

4 Overhead, Staffing & Markets

4.1 Developing the Business, Staffing & Markets 4.2 Determining Business Overhead (FICA, FUTA, SUTA, Workers' Comp, Rent & Utilities) 4.3 Determining Outsourced Services

5 Bids, Proposals & Estimating

5.1 Preparing Bids and Proposals 5.2 AIA Documents, Offers & Contract Components 5.3 Labor Productivity, Overhead & Project Costing

6 Purchasing, Invoices, Draws & Safety Programs

6.1 Purchasing Materials, UCC & Inventory (FIFO) 6.2 Invoices, Draw Requests & Percentage of Completion 6.3 Developing a Safety Program (OSHA, SDS & Drug Testing)

7 Managing Contracts

7.1 Contract Law, Scope & Completion Schedules 7.2 Florida Lien Law Inside Contracting 7.3 Mediation, Arbitration, Tort Law & Risk

8 Managing Trade Operations

8.1 Scheduling Trade Operations (CPM, RFI & Submittals) 8.2 OSHA Records, Document Retainage & Penalties 8.3 Takeoffs, Equipment Lease vs Purchase & Inventory

9 Accounting I: Receivables, Payables & Cash

9.1 Managing Accounts Receivable 9.2 Managing Accounts Payable & Discounts 9.3 Cash Flow, Banking & Financial Ratios

10 Accounting II: Taxes, Job Cost & Payroll

10.1 Filing Tax Forms & Returns 10.2 Tracking Job Costs 10.3 Payroll, Employment Taxes & Garnishments

11 Managing Human Resources

11.1 Hiring, I-9, Background Checks & Discrimination 11.2 HR Policies, OSHA & Drug-Test Chain of Custody 11.3 Evaluating Employees

12 Florida Contractor Law: Chapter 489 & 61G4

12.1 Chapter 489: Certified vs Registered & Qualifying Agents 12.2 61G4 Board Rules, Advertising & Discipline 12.3 Qualifying Agent Duties, Supervision & Additional Entities

13 Florida Construction Lien Law (Chapter 713)

13.1 Construction Lien Overview & Claimants 13.2 Notices to Owner, Time Limits & Perfecting Liens 13.3 Payment Bonds, Waivers & Claims of Lien

14 Financial Responsibility, CE & Federal Rules

14.1 Financial Responsibility & the 660 FICO Rule 14.2 Continuing Education & Biennial Renewal 14.3 Federal Employment, Immigration, OSHA & Environmental Rules

15 Plans, Specs & Equipment Selection

15.1 Reading Plans, Specifications, Symbols & Scales 15.2 Recommending Plan Changes & Equipment Types 15.3 EER, SEER, ARI Listings & Cost Effectiveness

16 Energy Codes, Loads & Thermal Resistance

16.1 Florida Energy Codes, R-Values & U-Factors 16.2 Determining HVAC Heating & Cooling Loads 16.3 Applying Energy Conservation, Fan Curves & Pump Curves

17 HVAC System & Duct Design

17.1 Designing HVAC Systems (Psychrometrics, Enthalpy & Airflow) 17.2 Designing Duct Systems & Insulation 17.3 Selecting Equipment, Location & Codes

18 Piping, Pumps, Boilers, Controls & Rigging Design

18.1 Pipe Sizing, Valves, Fittings, Sealants & Layout 18.2 Control Requirements, Fan Motors, CFM & Compressor Capacity 18.3 Pumps, Boilers, Steam, Fuel & Pipe Insulation 18.4 Grease Ducts, Live Loads, Rigging & Mechanical Equipment

19 Sheet Metal Duct Fabrication

19.1 Fabricating Rectangular & Round Ducts 19.2 Seams, Locks, Taping, Mastics & Liners 19.3 Fittings, Outlets & Grilles 19.4 Kitchen Hoods, Exhausts & Drain Pans

20 Split, Package & Heat Pump Installation

20.1 Installing Split & Package Air Conditioners 20.2 Installing Split & Package Heat Pumps 20.3 Air-Cooled vs Water-Cooled Systems

21 Large Systems, Chillers & Towers

21.1 Installing by Tonnage & Class A vs Class B Limits 21.2 Chilled Water, Water Towers & Secondary Coolant 21.3 Centrifugal, Absorption & Ammonia Systems

22 Refrigeration, Coolers, Ventilation & Controls Install

22.1 Low, Medium & Ultra-Low Temperature Systems & EPA Rules 22.2 Walk-In & Reach-In Coolers 22.3 Ventilation, Exhaust, Makeup Air, Grease Ducts & Kitchen Exhaust 22.4 Geothermal, Pneumatic & DDC Controls, TAB & Smoke Tests

23 Condensers, Compressors & Air Handlers

23.1 Installing Air-Cooled & Water-Cooled Condensers 23.2 Hermetic, Semi-Hermetic & Centrifugal Compressors 23.3 Air Handlers, Evaporators, Heat Exchangers, Receivers & Heat Strips

24 Duct, Fans, Filters & Terminals

24.1 Installing Sheet Metal, Fiberglass & Flexible Duct 24.2 Fans, Blowers, Motors, Grilles, Registers & Fire Dampers 24.3 Filters, Flues, Warm-Air, Gas & Fuel-Oil Appliances

25 Refrigerant Piping & Joining

25.1 Refrigerant Piping, Copper Tubing & Pipe Sizing 25.2 Brazing, Welding, Flaring, Swaging & Soldering 25.3 Steel Pipe, Plastic Pipe, Threading & Oxy-Acetylene 25.4 Hangers, Supports, Horizontally Supported Piping & Pressure Testing

26 Metering Devices & Line Components

26.1 TXVs, Capillary Tubes, Reversing Valves & Metering Devices 26.2 Liquid, Suction & Heat-Pump Dryers, Filters & Oil Traps 26.3 Receivers, Heat Strips, Gas/Oil Appliances & Related Accessories

27 Controls Installation

27.1 Pressure, Temperature, Humidity & Bellows Controls 27.2 Thermostats, Humidistats, Pneumatic & Solid-State Controls 27.3 Transformers, Capacitors, Contactors, Relays & Safety Disconnects 27.4 Defrost Components, Starters, Solenoids & Limit Switches

28 Motors, Wiring & Electrical Installation

28.1 Wiring Single-Phase & Three-Phase Equipment 28.2 Motor Types, Protection, Controllers, Belts & Pulleys 28.3 Geothermal Loops, Surge Protectors, Phase Monitors & Plastic Pipe

29 Diagnostic Analysis: Refrigeration

29.1 Pressure-Enthalpy Diagrams & Operating Pressures 29.2 Air Volumes, Enthalpy, Wet-Bulb & Dry-Bulb 29.3 Leak Detection & Refrigeration Test Instruments

30 Diagnostic Analysis: Electrical & Instruments

30.1 Current Draw, Voltage, Power & Motor Terminals 30.2 Testing Relays, Capacitors, Starters, Transformers & Defrost Stats 30.3 Using Amprobes, Velometers, Pitot Tubes, Manometers & Gauges

31 Recovery, Repair & Calibration

31.1 Nitrogen & Gas Regulators, Recovery & Retrofit 31.2 Repairing Hermetic, Semi-Hermetic, Centrifugal Compressors & Blowers 31.3 Calibrating Thermostats, Pressure Switches & Pneumatic Controls 31.4 Superheat, Safety Cutouts, Defrost Clocks & Freezer Controls

32 Mechanical Service & Cleaning

32.1 Belts, Pulleys, Motor Rotation & Seized Compressors 32.2 Crankcase & Evaporator Pressure Regulators & Unloaders 32.3 Cleaning Towers, Condensers, Foreign Matter & Condensate Drains

33 Jobsite Safety & Equipment

33.1 PPE: Hearing, Head, Eye, Face & Respiratory Protection 33.2 Lockout/Tagout, Warning Signs, Toxic Materials & Ventilation 33.3 Rigging, Hoists, Cranes, Forklifts, Backhoes & Excavation 33.4 Ladders, Scaffolds, Tools & Air Compressors

34 Energy Management

34.1 Envelope, Duct Pressure & Blower-Door Testing 34.2 Efficient Equipment, Zoning, ERVs, Wi-Fi Thermostats & Green Buildings 34.3 Energy Forms, R/U Factors, Window Heat Gain & Florida Load Calcs

35 Indoor Air Quality

35.1 Ventilation, Filtration, Humidity, UV & Air Cleaners 35.2 Contaminants, Source Control, TAB & Human Health Effects

8.1 Scheduling Trade Operations (CPM, RFI & Submittals)

Key Takeaways Explain This Topic AI

Business & Finance Area C (Managing Trade Operations) is 10% of the 120-question B&F exam; CPM, delivery and manufacture times, RFIs, trade sequencing, and submittal/approval/fabrication are the first cluster.

On a CPM network, activities with zero total float form the critical path; delaying a critical activity delays project completion by the same number of days.

HVAC factory lead time starts after submittal approval or approved-as-noted, not when the package is mailed; Revise and Resubmit keeps manufacture from starting.

An RFI is a written question when documents conflict or are unbuildable; a change in scope, time, or price is a change-order path, not a silent field fix.

SMACNA duct construction data (pressure class, seal class, gauge, reinforcement) and equipment performance data are typical HVAC submittals; FBC Mechanical 2023 inspections are scheduled activities with predecessors.

Last updated: August 2026

8.1 Scheduling Trade Operations (CPM, RFI & Submittals)

Business & Finance (B&F) Area C — Managing Trade Operations is 10% of the 120-question B&F exam, roughly a dozen scored items. The first cluster is not a motivational calendar. It tests whether a qualifying agent can sequence work with the critical path method (CPM) , honor delivery times and manufacture times , write and close requests for information (RFIs) , and drive submittals through approval into fabrication before a crane sits on a Florida school roof. The 2026 B&F references that carry this cluster are the Contractors Manual 2025 (used beginning February 1, 2026) and AIA A201-2017 . On the HVAC trade list, SMACNA HVAC Duct Construction Metal and Flexible, 4th Ed. 2020 is the duct-construction book the submittal will cite. Class A and Class B candidates sit the same B&F paper. A 40-ton packaged rooftop is outside Class B scope under F.S. 489.105 ( 25 tons of cooling and 500,000 Btu of heating in any one system ), but Class B still has to schedule the 20-ton jobs the license can take.

Why the schedule is a qualifying-agent problem

Under F.S. 489.1195 , the primary qualifying agent is jointly and equally responsible for supervision of all field work at all sites. A late rooftop unit (RTU) is not only a cash-flow problem. It strands roofers, electricians, and a crane subcontractor, burns liquidated damages, and leaves mechanical inspections uncalled under the Florida Building Code — Mechanical, 2023 (8th Edition — the listed exam edition). HVAC sits on someone else's critical path: the roof must be ready for curbs, the structure must take the operating and rigging load, the electrical service must be there for the dedicated disconnect, and the authority having jurisdiction (AHJ) must see the rough-in before the ceiling closes.

CPM, float, delivery, and manufacture

CPM is a network of activities with durations and predecessor logic, not a bar chart drawn after the fact. Each activity has an early start (ES) , early finish (EF) , late start (LS) , and late finish (LF) . Total float equals LS minus ES (or LF minus EF). Activities with zero float are on the critical path . Delay a critical activity one day and the project finish date moves one day. Delay a non-critical activity inside its float and the finish date does not move.

The forward pass computes the earliest each activity can finish. The backward pass works from the required finish date. The longest path through the network is the critical path. Use the duration convention the exam stem gives; many contractor-exam problems treat the next activity as starting after the predecessor's duration is consumed.

Worked HVAC CPM. Coastal Air is the mechanical sub on a school RTU replacement:

  • Activity Duration Predecessors
  • A — Shop drawings, SMACNA duct data, and equipment submittals 12 days None (start)
  • B — Architect/engineer review and any resubmittal 10 days A
  • C — Factory manufacture and freight of 20-ton RTUs 40 days B
  • D — Roof curbs and structural steel 6 days Roof released (can run parallel with A–C)
  • E — Crane, rigging, and set 1 day C and D
  • F — Refrigerant piping, condensate, and power wiring on the dedicated disconnect 8 days E
  • G — Start-up, TAB, and mechanical inspection 3 days F

If curb work (D) can start on day 1, it finishes on day 6. Submittals plus review plus factory (A+B+C) equal 62 days before the units exist to fly. The crane (E) cannot start until both C and D are done, so E waits on C, not on D. D has 56 days of float (62 − 6). The critical path is A–B–C–E–F–G = 12 + 10 + 40 + 1 + 8 + 3 = 74 working days . Ordering the crane for week 3 because the roof is ready is how you pay a show-up fee and still have no unit.

Delivery times and manufacture times are activities, not margin notes. A 20-ton packaged RTU is not a warehouse commodity in peak Florida cooling season. Custom curbs, coated coils, special voltage, and energy-code ratings add factory days. Refrigerant allocation under the federal HFC phasedown (AIM Act) affects cylinder supply and pre-charged equipment availability. Do not invent a GWP number the stem did not give; do put the vendor's written ship date on the network. If the factory quotes 40 days after approved submittals, the clock does not start the day you mailed the package. It starts when the architect's stamp is Approved or Approved as Noted and you have released the order.

RFIs: when the drawings cannot be built as drawn

A request for information (RFI) is a written question to the design team when the contract documents are silent, conflicting, or unbuildable. It is not a change order, not a submittal, and not a complaint. HVAC RFIs fire when the structural drawing's RTU opening does not match the mechanical schedule's curb; when the electrical one-line shows a 208-volt three-phase disconnect and the specified unit is 460-volt; when duct mains collide with a fire-rated shaft, a grease duct under NFPA 96 (2021) , or a beam that was never on the mechanical sheet; or when the specified refrigerant is no longer the factory's production refrigerant.

AIA A201-2017 (on the 2026 B&F list) puts the contractor on the documents: review them, report errors promptly, and do not proceed with work you know is at variance. An unanswered RFI is a schedule risk — log the date sent, the date due, and the activity it gates. If the answer changes scope, price, or time, that is a change order path, not a silent field fix. A Class A shop setting a 40-ton unit on a custom steel frame is more likely to find a structural conflict than a Class B 5-ton changeout; Class B still needs the RFI procedure because B&F questions are not split by tonnage.

Submittals, approval, fabrication, and trade sequence

Submittals are the contractor's proof that the product and the shop method match the specifications. Typical HVAC packages:

Equipment — performance data, AHRI listings, efficiency as specified, curb drawings, weights for structural and crane planning, electrical characteristics, and refrigerant type.

SMACNA duct — pressure class, seal class, material, gauge, reinforcement spacing, and flexible-duct limitations from SMACNA HVAC Duct Construction Metal and Flexible, 4th Ed. 2020 (fibrous glass from the 8th Ed. 2021 when that is the spec).

Controls, TAB, and close-out — sequences, reports, O&M manuals, as-builts, and owner training.

The sequence the exam cares about is submit → review/approval → fabricate or release → deliver → install . Fabricating duct or releasing an RTU from the factory before approval is how you own a pile of wrong-gauge duct and a 20-ton unit that will not sit on the specified curb. Approved as Noted usually lets fabrication proceed if the notes are incorporated. Revise and Resubmit does not. Put resubmittal time back on the CPM.

Sequencing trades is physics and OSHA, not courtesy. Roofing and curb flashing before the crane day. Structural steel and housekeeping pads before a chiller lands (Class A work when the system exceeds 25 tons or includes boilers or unfired pressure vessels). Electrical lockout of the dedicated HVAC circuit before changeout. Crane and rigging ( OSHA 1926 Subpart CC ) need a pick plan, a competent person, a weather window, and street or right-of-way permits if the boom occupies a Florida DOT or municipal lane. You cannot TAB a system the AHJ has not seen after the ceiling has already closed.

Permit inspections as scheduled activities

Florida mechanical work is inspected under FBC Mechanical 2023 and FBC Energy Conservation 2023 . Treat inspections as activities with predecessor logic: rough duct and refrigerant piping before concealment, above-ceiling before close-in, final after start-up. A two-day wait for an inspector is float only if you put it in the network. Energy forms and AHRI data that were in the submittal are what the inspector will look for; they are not a close-out surprise.

Florida HVAC scenario

Orlando Comfort, a Class A certified contractor, is the mechanical sub on a 12-unit school RTU replacement. Each unit is 15 tons — inside Class B if they are truly separate systems; this shop is Class A. The general contractor's CPM shows mechanical complete in 60 calendar days. The factory's written lead time is 45 days after approved submittals. Architect review is 10 days in the spec. Submittal preparation is 8 days. Eight plus 10 plus 45 equals 63 days before the units ship , plus freight, plus a Saturday crane. The HVAC qualifier who knows we can make 60 days without crashing review or paying a premium factory slot is not managing trade operations — they are bidding a schedule the network already proves is impossible. The correct move is an RFI or schedule notice to the general contractor before the steel hits the ground, not a hope that the crane will wait.

Loading diagram... HVAC submittal, factory lead time, and crane-day logic