Study guide

14.1 Onsite Sewage Treatment & Disposal: Septic Tanks & Drainfields

Florida Journeyman Plumber Exam

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: Florida Plumbing Code Administration & Licensure

1.1 DBPR Licensing, CILB Regulations & Journeyman Qualifications 1.2 Permits, Inspections & Code Enforcement 1.3 Florida Construction Lien Law & Business Operations

2 Chapter 2: Sanitary Drainage Fundamentals & DFU Sizing

2.1 Gravity Drainage Principles & Florida DWV Materials 2.2 Drainage Fixture Units (DFU) & Load Values 2.3 Horizontal Branch & Vertical Stack Sizing 2.4 Drainage Fittings, Flow Direction & Change of Direction Rules

3 Chapter 3: Building Drains, Sewers & Special Drainage Systems

3.1 Building Drain & Building Sewer Sizing 3.2 Drainage Cleanouts: Sizing, Clearances & Locations 3.3 Sewage Ejectors, Sumps & Macerating Systems 3.4 Florida High Water Table, Slab Penetrations & Termite Protection

4 Chapter 4: Indirect Waste, Special Waste & Interceptors

4.1 Indirect Waste Systems: Air Gaps vs Air Breaks 4.2 Grease Interceptors: Hydromechanical & Gravity Interceptor Sizing 4.3 Sand, Oil & Specialized Interceptors

5 Chapter 5: Water Supply Systems & WSFU Pipe Sizing

5.1 Potable Water Piping Materials & Installation 5.2 Water Supply Fixture Units (WSFU) & Demand Estimations 5.3 Water Distribution Pipe Sizing Methods 5.4 Water Pressure Control, Boosting & PRVs

6 Chapter 6: Water Heaters, Cross-Connection Control & Reclaimed Water

6.1 Water Heaters & Safety Controls 6.2 Backflow Prevention & Cross-Connection Protection 6.3 Reclaimed Water Systems & Florida Dual-Plumbing Rules 6.4 System Testing, Disinfection & Commissioning

7 Chapter 7: DWV Venting Systems & Sizing

7.1 Principles of Venting & Trap Seal Integrity 7.2 Vent Sizing & Developed Length 7.3 Wet Venting & Horizontal Wet Venting 7.4 Circuit, Loop & Common Venting

8 Chapter 8: Specialized Venting & Air Admittance Valves

8.1 Island Fixture Vents & Foot Venting 8.2 Combination Waste and Vent Systems 8.3 Air Admittance Valves (AAVs) & Engineered Systems

9 Chapter 9: Isometric Drawing Interpretation & Drafting

9.1 Isometric Drawing Fundamentals and Plan Reading 9.2 Drafting Florida DWV Isometric Schematics 9.3 Local Exam Plan-Reading Practice and Self-Audit 9.4 Reading Plumbing Plans, Specifications & Schedules

10 Chapter 10: Fuel Gas Piping & Storm Drainage Systems

10.1 Fuel Gas Fundamentals: Natural Gas vs LP Gas 10.2 Gas Pipe Sizing & Demand Calculations 10.3 Gas Pipe Materials, Installation, Testing & Appliance Connections 10.4 Storm Drainage Sizing & Florida Rainfall Rates 10.5 Appliance Venting, Chimneys & Combustion Air

11 Chapter 11: Trade Mathematics, Accessibility & Jobsite Safety

11.1 Plumbing Math: Grade, Pitch & Elevation Calculations 11.2 Plumbing Math: 45-Degree & Rolling Offsets 11.3 Florida Accessibility Standards for Plumbing Fixtures 11.4 OSHA Construction Safety Standards for Plumbers 11.5 Plumbing Tools, Equipment & System Troubleshooting

12 Chapter 12: Medical Gas & Vacuum Piping Systems (NFPA 99)

12.1 Medical Gas Systems: Categories, Gases & Source Equipment 12.2 Medical Gas Piping Materials, Brazing & Nitrogen Purging 12.3 Station Outlets, Zone Valves, Alarms & Pipe Sizing 12.4 Medical-Surgical Vacuum, WAGD & System Verification

13 Chapter 13: Industrial, Process & Special-Waste Piping

13.1 Compressed Air & Industrial Gas Piping Systems 13.2 Industrial Vacuum Piping Systems 13.3 Process Piping & Steam Distribution Systems 13.4 Oil & Gasoline Storage and Distribution Systems 13.5 Industrial Water Drainage & Waste Pretreatment

14 Chapter 14: Site Utilities, Sewage Disposal & Water Mains

14.1 Onsite Sewage Treatment & Disposal: Septic Tanks & Drainfields 14.2 Sewage Lift Stations & Force Mains 14.3 Water Transmission Mains, Excavation & Heavy Equipment

15 Chapter 15: Pools, Wells, Irrigation, Solar & Fire Protection

15.1 Swimming Pool & Spa Piping Systems 15.2 Water Wells, Pumps & Irrigation Systems 15.3 Solar Water Heating Systems 15.4 Fire Protection Systems & Standpipes (NFPA 14)

14.1 Onsite Sewage Treatment & Disposal: Septic Tanks & Drainfields

Key Takeaways Explain This Topic AI

Current Rule 62-6.005 siting provisions must be distinguished from historical rules, local exam references and supplied training tables.

Exhibits A–C explicitly supply hypothetical flow, tank and loading criteria; select the controlling row and preserve inclusive boundaries.

Absorption area equals sizing flow divided by the supplied loading rate; round required whole-square-foot areas upward.

The current unobstructed-area provision includes the drainfield: 1.5 × 500 = 750 ft² total, outside setbacks.

Apply the actual well/surface-water provisions and exceptions; storm-sewer separation is 10 feet to the maximum extent possible, never less than 5 feet.

Last updated: October 2026

Onsite Sewage Treatment & Disposal: Septic Tanks & Drainfields

Onsite sewage systems require a separate flow, tank, soil and siting analysis. This section retains worked table exercises for learning; the current permit rules and any approved local-exam reference edition must be checked separately. A state contractor reference list does not authorize a local journeyman candidate to bring a bound rule PDF.

Note

Florida transferred the Onsite Sewage Program from DOH to DEP effective July 1, 2021 . DEP’s current forms-and-publications page links Chapter 62-6, F.A.C. Older 64E-6 publications are historical sources, not proof that their edition is the current permit rule or an authorized local-exam book. These table exercises do not replace current site-specific permitting requirements.

1. Supplied Design Exhibit A: Flow Selection

The numerical tables in Exhibits A–C are provided training-design criteria . They are not represented as the current adopted Tables I–III of Rules 62-6.008 and 62-6.013. Actual design needs the current permit-specific flow, tank, treatment and soil requirements. Here the learning task is to choose the controlling row, preserve units and apply the given conditions consistently.

For this exercise, choose the greater residential flow produced by the bedroom count and building-area band. Do not average conflicting rows.

  • Dwelling Unit Estimated Flow
  • 1 bedroom with 750 sq ft or less of building area 100 gpd
  • 2 bedrooms with 751 to 1,200 sq ft 200 gpd
  • 3 bedrooms with 1,201 to 2,250 sq ft 300 gpd
  • 4 bedrooms with 2,251 to 3,300 sq ft 400 gpd
  • Each additional bedroom, or each additional 750 sq ft or fraction thereof add 60 gpd
  • Other, per occupant 50 gpd

Additional exercise assumptions are: residential flow is split 50% blackwater/50% graywater; the base residence allowance assumes up to two occupants per bedroom and the provided care-facility case adds 50 gpd per additional occupant; a food-operation calculation assigns 66% of the total to kitchen flow. These values are supplied only when that case asks for the corresponding split; they are not current-law assertions.

The following commercial schedule is also a provided exercise schedule , not a permit table. Use the listed units and conditions before multiplying.

  • Establishment Estimated Flow
  • Restaurant operating 16 hours or less per day 40 gpd per seat
  • Restaurant operating more than 16 hours per day 60 gpd per seat
  • Restaurant using single-service articles only, 16 hours or less 20 gpd per seat
  • Bar and cocktail lounge 20 gpd per seat, add 15 gpd per pool table or video game
  • Office building 15 gpd per employee per 8-hour shift or 15 gpd per 100 sq ft, whichever is greater
  • Hotel or motel, regular 100 gpd per room
  • Resort hotel, camp, cottage 200 gpd per room
  • Self-service laundry facilities add 750 gpd per machine
  • Barber and beauty shops 75 gpd per service chair
  • Doctor and dentist offices 250 gpd per practitioner, plus 15 gpd per employee per 8-hour shift
  • Schools, day type 10 gpd per student, plus 4 for showers, 4 for cafeteria, 15 per day school worker

For a designated high-volume interstate exercise only, apply the provided 3.0 multiplier after selecting the base establishment rate. For example, a 20-seat restaurant operating 12 hours uses 20 × 40 = 800 gpd before that multiplier and 2,400 gpd with it. Do not apply this exercise modifier to an actual establishment without its governing approved criteria.

2. Supplied Design Exhibit B: Effective Tank Capacity

For this training design, use the following effective-capacity and pump-tank schedule. A boundary value belongs to its inclusive row: 500 gpd is in 401–500, not 501–600.

Average Sewage Flow (gpd) Minimum Effective Septic Tank Capacity Minimum Total Pump Tank Capacity (Residential / Commercial)

  • 0 - 200 900 gal 150 / 225
  • 201 - 300 900 gal 225 / 375
  • 301 - 400 1,050 gal 300 / 450
  • 401 - 500 1,200 gal 375 / 600
  • 501 - 600 1,350 gal 450 / 600
  • 601 - 700 1,500 gal 525 / 750
  • 701 - 800 1,650 gal 600 / 900
  • 801 - 1,000 1,900 gal 750 / 1,050
  • 1,001 - 1,250 2,200 gal 900 / 1,200
  • 1,251 - 1,750 2,700 gal 1,350 / 1,900
  • 1,751 - 2,500 3,200 gal 1,650 / 2,700

Effective capacity is the specified operating liquid volume, not the tank's gross exterior volume. The provided construction specification uses multiple chambers or tanks in series and an accessible approved outlet filter before the drainfield. Product approval, structural loads, access and actual permit provisions remain separate checks.

Optional exercise conditions , when stated: jointly connected dwelling units add 75 gallons per unit to the scheduled capacity; a separate graywater case uses 250 gallons through 75 gpd and daily flow + 200 gallons above that; a blackwater reduction is capped at 25% and cannot reduce the exercise's 900-gallon minimum. These are supplied problem rules, not claims about the currently adopted tank rule. Do not apply one optional condition to a case that has not specified it.

Traffic support is a separate issue. Current Rule 62-6.005 addresses traffic lids and preventing bonding where concrete structures are placed over tanks. A traffic-rated lid does not automatically authorize an otherwise unsuitable tank, drainfield or access arrangement.

3. Supplied Design Exhibit C: Absorption-Area Analysis

The training site's approved soil report supplies the following illustrative loading schedules . They do not establish a statewide soil classification from appearance or a single percolation observation.

  • Supplied site schedule Trench loading (gal/ft²/day) Bed loading (gal/ft²/day)
  • A: approved sandy-site example 0.80 0.60
  • B: approved lower-loading example 0.65 0.35
  • C: approved still-lower-loading example 0.35 0.20
  • Site report rejects the proposed conventional system No permitted rate supplied No permitted rate supplied

For these exercises, use a provided minimum sizing flow of 200 gpd where estimated flow is lower. Required area equals sizing flow divided by the applicable loading rate. Round upward where the design selects whole square feet. A lower loading rate increases required area; using a bed rate for a trench or multiplying flow by rate gives the wrong result.

Soil evaluation also considers the seasonal water table, limiting layers, groundwater movement and treatment opportunity. Very rapid infiltration is not automatic approval: insufficient separation or treatment can make a site unsuitable. A rejected site has no valid conventional-system area merely by choosing the smallest number in the table. Obtain an approved alternative design; a mound or fill is not automatically a cure for every limitation.

4. Current Siting Provisions and Their Conditions

The following summarizes the ordinary siting provisions in Rule 62-6.005, effective June 8, 2026 . It is not an exhaustive exception analysis. Existing-lot, statutory surface-water and other expressly authorized provisions require their own eligibility review; the worked new-lot example below assumes none of those exceptions.

  • Feature Minimum Distance
  • Private potable well or multi-family water well 75 feet
  • Public drinking water well serving a facility with estimated sewage flow of 2,000 gpd or less 100 feet
  • Public drinking water well serving a facility with estimated flow more than 2,000 gpd 200 feet
  • Non-potable water well 50 feet
  • Storm sewer pipe 10 feet to the maximum extent possible, never less than 5 feet

Design high-water line of a retention or detention area or swale holding water less than 72 hours, or a normally dry ditch 15 feet

Surface water bodies (laterally) 75 feet , subject to the statutory exceptions expressly referenced by the rule

Building foundations (including pilings), mobile home walls, swimming pool walls, property lines 5 feet under the ordinary provision; specified utility/recorded-easement exceptions require separate review; not under buildings

Water storage tanks in contact with the ground, or potable water lines 10 feet . The exception applies only to water lines : either seal them with waterproof sealant inside a sleeve of similar-material pipe extending to at least 10 feet from the nearest portion of the onsite system , or use Schedule 40 PVC or stronger water lines. Even qualifying water lines must remain at least 24 inches from the system. This exception does not reduce the separation for water storage tanks.

Additional siting rules:

Sidewalks, decks and patios are not subject to the 5-foot setback , but drainfields shall not be installed beneath them .

Potable water lines within 5 feet of the drainfield shall not be at an elevation lower than the drainfield absorption surface.

Unobstructed area : suitable, unobstructed land shall be available at not less than 1.5 times the required drainfield absorption area , inclusive of the drainfield itself , contiguous and outside the setback areas. The rule's own example: a 200-square-foot drainfield requires a 300-square-foot total unobstructed area.

Fill material must be allowed to settle at least 6 months or be compacted to a density comparable to surrounding natural soil, and must be suitable slightly limited soil.

Keep three area concepts distinct. Rule 62-6.005(7)(a)'s specified lot route starts at one-half acre (21,780 ft²) , with dated-lot alternatives and conditions. Subdivision net density and authorized flow based on net usable lot area have their own exclusions; do not subtract every paved surface from the lot-size test by assumption.

Under the applicable net-usable-area flow provision, the allowance is 2,500 gallons/acre/day for the specified public-water category and 1,500 gallons/acre/day for private-well, limited-public, cistern and other stated categories. The rule excludes paved/prepared roadbeds within public rights-of-way or easements and surface-water bodies from that flow area, with its specified optional treatment of qualifying contiguous unpaved/uncompacted rights-of-way. Calculate the correct area and water-supply category before comparing design flow.

Existing lots and alternative treatment routes have additional conditions. Do not transfer a historical-lot well-distance exception to an ordinary new-lot case, or treat a flow-area allowance as a substitute for drainfield sizing and setbacks.

5. Worked Sizing Example

Training project : a new single-family home on private well water, with the supplied Exhibits A–C approved for this hypothetical design and no siting exception invoked. Four bedrooms, 2,400 square feet of building area. The supplied site report approves Schedule A and independently confirms the required seasonal-water-table and limiting-layer conditions. The drainfield will be a trench system.

Step 1 — Estimated sewage flow (supplied Exhibit A). Four bedrooms at 2,251 to 3,300 square feet: Q = 400 gallons per day Q = \mathbf{400\text{ gallons per day}} Q = 400 gallons per day

Apply the supplied greater-flow condition: the bedroom row and the area row agree, so no upward adjustment.

Step 2 — Effective septic tank capacity (supplied Exhibit B). 400 gpd falls in the 301-400 gpd row: V t a n k = 1 , 050 gallons minimum effective capacity V_{tank} = \mathbf{1,050\text{ gallons minimum effective capacity}} V t ank ​ = 1 , 050 gallons minimum effective capacity

The supplied construction specification requires the stated chamber/series arrangement and outlet filter; actual permits require current rule and product review.

Step 3 — Drainfield absorption area (supplied Exhibit C). Schedule A supplies a trench loading rate of 0.80 gal/sq ft/day: A = 400 gpd 0.80 gal/sq ft/day = 500 square feet of trench absorption area A = \frac{400\text{ gpd}}{0.80\text{ gal/sq ft/day}} = \mathbf{500\text{ square feet of trench absorption area}} A = 0.80 gal/sq ft/day 400 gpd ​ = 500 square feet of trench absorption area

Had the designer chosen an absorption bed instead of trenches, the rate drops to 0.60 and the area rises: A b e d = 400 0.60 = 667 square feet A_{bed} = \frac{400}{0.60} = \mathbf{667\text{ square feet}} A b e d ​ = 0.60 400 ​ = 667 square feet

The difference here comes from the two supplied design loading rates. Do not independently credit extra sidewall area or assume a trench is always the appropriate site design.

Step 4 — Unobstructed area. A u n o b s t r u c t e d = 1.5 × 500 = 750 square feet A_{unobstructed} = 1.5 \times 500 = \mathbf{750\text{ square feet}} A u n o b s t r u c t e d ​ = 1.5 × 500 = 750 square feet

inclusive of the 500-ft² drainfield, contiguous and outside all setbacks; this is 750 ft² total , not 500 + 750.

Step 5 — Check the setbacks. The system must sit at least 75 feet from the private potable well, 5 feet from the house foundation and property lines, 10 feet from storm sewer piping to the maximum extent possible and never less than 5 feet , and the ordinary 75-foot surface-water setback where no stated exception applies. A storm sewer distance of 8 feet does not by itself prove a mandatory relocation: document whether the maximum feasible separation and the absolute minimum are satisfied. Resolve every applicable siting condition before ordering the system.

Loading diagram... Supplied sizing exhibits plus current siting review