Study guide
9.6 Insulating Glass, Safety Glazing & Water Control
Georgia General Contractor Exam
Track your progress as you read
Finished sections get a check mark.
1 Chapter 0: Exam Orientation, Blueprint & Open-Book Method
0.1 Official Exam Facts, Content Outlines & Approved References 0.2 Open-Book Navigation, Reference Indexing & Study Plan
2 Chapter 1: Georgia Contractor Licensing & Regulatory Law
1.1 Board Authority & Commercial General Contractor Tiers 1.2 Scope, Exemptions & Unlicensed Contracting 1.3 Eligibility, Experience Requirements & Qualifying Agents 1.4 Financial Responsibility, Net Worth, Surety Bonds & Insurance 1.5 License Renewal, No-CE Rule & Disciplinary Actions
3 Chapter 2: Georgia Construction & Lien Law
2.1 Georgia Mechanics & Materialmen's Liens 2.2 Project Notices: Notice of Commencement, Notice to Contractor & Preliminary Notice 2.3 Statutory Lien Waivers & Affidavits of Nonpayment 2.4 Georgia Prompt Pay Act & Right to Repair Act
4 Chapter 3: Business Organization, Financial Management & Taxes
3.1 Business Entity Selection & Joint Ventures 3.2 Georgia Entity Registration, Foreign Qualification & Trade Names 3.3 Construction Accounting, WIP & Financial Statements 3.4 Cash Flow, Working Capital & Construction Banking 3.5 Federal, Georgia & Payroll Tax Administration 3.6 Worker Classification, Wage-and-Hour & Prevailing Wage
5 Chapter 4: Construction Contracts, Bidding & Risk Management
4.1 Contract Pricing Models & Cost Risk 4.2 Project Delivery Methods & Responsibility 4.3 Essential Contract Clauses & Risk Allocation 4.4 Standard Documents: AIA, ConsensusDocs & EJCDC 4.5 Quantity Takeoff, Direct Cost & Markup 4.6 Bid Scope Review, Submission & Withdrawal 4.7 Surety Bonds, Insurance & Risk Management
6 Chapter 5: Project Management, Scheduling & Quality Control
5.1 Project Planning, WBS, Logic & Resources 5.2 CPM, Float, Updating & Schedule Compression 5.3 Project Administration, Submittals, RFIs & Records 5.4 Changes, Delays, Claims & Dispute Resolution 5.5 QA/QC, Special Inspections & Closeout
7 Chapter 6: Georgia Building Codes, Environmental Regulations & Site Work
6.1 Current Georgia Codes, Amendments, Permits & Inspections 6.2 Occupancy, Construction Type, Egress & Accessibility 6.3 GESA, NPDES, Buffers, BMPs & Certified Personnel 6.4 Survey Control, Layout, Clearing & Site Preparation 6.5 Excavation, Earthwork Volumes, Hauling & Compaction 6.6 Shallow Foundations, Slabs, Deep Systems & Drainage
8 Chapter 7: Concrete & Masonry Construction
7.1 Concrete Materials, Mix Design & Field Testing 7.2 Concrete Placement, Hot/Cold Weather, Curing & Defects 7.3 Formwork, Shores, Reshores & Removal 7.4 Reinforcing Steel, Splices & Post-Tensioning 7.5 Masonry Units, Mortar, Grout & Testing 7.6 Masonry Walls, Reinforcement, Flashing & Movement Joints
9 Chapter 8: Structural Steel, Metals & Framing Systems
8.1 Structural Steel Shapes, Framing & Erection Stability 8.2 Bolted Connections, Welding & Nondestructive Testing 8.3 Steel Joists, Deck & Cold-Formed Framing 8.4 Heavy Timber, Fire Performance & Mass Timber 8.5 Engineered Wood, I-Joists, Trusses & Connectors 8.6 Wood Framing, Sheathing, Bracing & Fastening
10 Chapter 9: Building Envelope, Thermal & Moisture Protection, Doors & Windows
9.1 Low-Slope Roofing, Insulation & Drainage 9.2 Steep-Slope Roofing, Sheet Metal & Flashing 9.3 Insulation, Air Barriers & Vapor Control 9.4 Commercial Doors, Frames, Hardware & Fire Assemblies 9.5 Windows, Storefronts & Curtain Walls 9.6 Insulating Glass, Safety Glazing & Water Control
11 Chapter 10: Finishes, Mechanical, Electrical & Plumbing Coordination
10.1 Gypsum Assemblies, Ceilings & Finish Coordination 10.2 Concrete Moisture, Flooring & Tile Assemblies 10.3 HVAC, Ductwork, Dampers & Mechanical Coordination 10.4 Plumbing, DWV, Venting & Backflow 10.5 Fire Sprinklers, Standpipes & Fire Department Connections 10.6 Electrical Distribution, Grounding & Emergency Systems
12 Chapter 11: Construction Safety & OSHA Standards (29 CFR Part 1926)
11.1 OSHA Authority, Inspections, Reporting & Multi-Employer Sites 11.2 Fall Protection, Clearance Planning & Scaffolds 11.3 Excavation, Protective Systems & Trench Safety 11.4 Hazard Communication, Silica, Temporary Power & PPE 11.5 Cranes, Rigging, Signal Persons & Power-Line Safety
9.6 Insulating Glass, Safety Glazing & Water Control
Key Takeaways Explain This Topic AI
Coating surface is selected from climate, performance target, glass makeup, and manufacturer design—not a universal Georgia rule.
Safety glazing is required in defined hazardous locations.
IGU seals manage gas and moisture but are not the primary structural glazing attachment.
Last updated: September 2026
- 9.6 Insulating Glass, Safety Glazing & Water Control
- Insulated Glazing Units (IGUs) & Optical Energy Properties
Modern commercial windows utilize Insulated Glazing Units (IGUs) consisting of two (dual-pane) or three (triple-pane) lites of glass hermetically sealed around a gas-filled airspace. INSULATED GLAZING UNIT (IGU) ANATOMY
- OUTDOOR (EXTERIOR) INDOOR (INTERIOR)
- │ │
- ▼ ▼
- ┌──────────────┐ ┌──────────────┐
- │ OUTER LITE │ SEALED AIR │ INNER LITE │
- │ (4mm / 6mm) │ OR ARGON │ (4mm / 6mm) │
- │ │ AIRSPACE │ │
- │ SURFACE #1 │ (1/2" GAP) │ SURFACE #3 │
- │ (EXTERIOR) │ │ (CAVITY) │
- │ │ ◄── WARM-EDGE ─────► │ │
- │ SURFACE #2 │ SPACER WITH │ SURFACE #4 │
- │ (CAVITY) │ DESICCANT │ (INTERIOR) │
- │ │ │ │
- │ LOW-E ON │ PRIMARY PIB SEAL │ │
- │ SURFACE #2 │ + STRUCTURAL SIL │ │
- └──────────────┘ └──────────────┘
- ▲ ▲
- │ │
- [IN GEORGIA CLIMATE: LOW-E ON SURFACE #2 REFLECTS SOLAR HEAT OUTWARD]
- IGU Construction & Sealing
Spacers & Desiccants: Glass lites are separated by stainless steel or composite warm-edge spacers filled with molecular sieve desiccant beads that adsorb residual moisture within the airspace to prevent internal fogging.
Dual-Seal System: The primary seal is polyisobutylene (PIB) (applied under heat to prevent moisture vapor infiltration and gas loss). The secondary structural seal is silicone or polysulfide (providing structural elastomeric bonding holding the glass panes together).
Gas Filling: Air in the cavity is replaced with Argon gas (90% argon fill), reducing conductive and convective heat transfer due to argon's higher density and lower thermal conductivity ( k a r g o n ≈ 0.016 W / m ∗ K k_{argon} \approx 0.016 W/m * K k a r g o n ≈ 0.016 W / m ∗ K vs k a i r ≈ 0.024 W / m ∗ K k_{air} \approx 0.024 W/m * K k ai r ≈ 0.024 W / m ∗ K ).
Glazing Performance Metrics (NFRC Ratings)
Under the IECC and ASHRAE 90.1, fenestration products are rated by the National Fenestration Rating Council (NFRC) across three critical performance metrics:
U-Factor: Measures the overall rate of non-solar heat flow through the fenestration assembly ( Btu / ( h ⋅ ft 2 ⋅ ∘ F ) \text{Btu}/(\text{h} \cdot \text{ft}^2 \cdot {}^\circ\text{F}) Btu / ( h ⋅ ft 2 ⋅ ∘ F ) ). Lower U-factors represent superior insulating performance.
Solar Heat Gain Coefficient (SHGC): The fraction of incident solar radiation admitted through the glass (expressed from 0.0 to 1.0). In Georgia's cooling-dominated climate (Zones 2A and 3A), code mandates a low SHGC (typically ≤ 0.25) to minimize air conditioning peak electrical loads.
Visible Transmittance (VT): The percentage of the visible light spectrum (380-740 nm) transmitted through the glass (0.0 to 1.0). Designers optimize the Light-to-Solar Gain (LSG) ratio ( L S G = V T / S H G C LSG = VT / SHGC L SG = V T / S H GC ); high LSG ratios (> 1.5) maximize natural daylight while rejecting solar heat.
Low-Emissivity (Low-E) Coatings & Surface Numbering
Low-E coatings consist of microscopically thin, transparent metallic layers (silver or metal oxide) that reflect long-wave infrared thermal radiation while transmitting visible light:
Surface Numbering Standard: Glass surfaces in an IGU are numbered sequentially starting from the exterior:
Surface #1: Exterior face of the outer lite.
Surface #2: Interior (cavity) face of the outer lite.
Surface #3: Exterior (cavity) face of the inner lite.
Surface #4: Interior face of the inner lite (facing building interior).
Coating placement: Select surface, coating chemistry, tint, heat treatment, edge deletion, and sealant compatibility from the specified U-factor, solar heat-gain coefficient, visible transmittance, climate, glass makeup, manufacturer design, and thermal-stress analysis. Surface #2 is common for solar-control coatings, but it is not a universal Georgia code mandate.
Safety Glazing Mandates (IBC Chapter 24 / CPSC 16 CFR 1201)
Glass installed in locations subject to human impact must comply with federal safety standards ( CPSC 16 CFR Part 1201 and ANSI Z97.1 ) to prevent catastrophic laceration injuries.
Types of Safety Glazing
Fully Tempered Glass: Heat-treated in a furnace at 1,150°F and rapidly air-quenched, creating permanent surface compression ( ≥ 10 , 000 p s i \ge 10,000 psi ≥ 10 , 000 p s i ). Tempered glass is four to five times stronger than standard annealed glass. When broken, it fractures instantly into thousands of small, relatively harmless, blunt granules ("dicing"). Tempered glass cannot be cut, drilled, or edge-worked after fabrication .
Laminated Glass: Formed by sandwiching a tough, flexible interlayer of Polyvinyl Butyral (PVB) or ionoplast resin (SentryGlas) between two lites of glass under heat and pressure (autoclave). When impacted, the glass fractures but fragments remain bonded to the interlayer. Mandatory for overhead sloped glazing/skylights, hurricane impact zones (coastal Georgia), bullet-resistant glass, and acoustic barriers. ┌─────────────────────────────────────────┐
- │ IBC 2406.4 HAZARDOUS SAFETY GLAZING │
- └────────────────────┬────────────────────┘
- │
- ┌─────────────────────────────────┼─────────────────────────────────┐
- ▼ ▼ ▼
- ┌──────────────┐ ┌──────────────┐ ┌──────────────┐
- │ DOORS & SIDEL│ │ WET / POOLS │ │ LARGE PANES │
- └──────┬───────┘ └──────┬───────┘ └──────┬───────┘
- │ │ │
- All swinging/sliding doors • Showers, saunas, hot tubs • Pane > 9 sq ft (0.84 m²)
- Glazing within 24" of door • Walls enclosing pools • Bottom edge < 18" AFF
- Bottom edge < 60" AFF • Bottom edge < 60" above floor • Top edge > 36" AFF
- Railings & glass guards • Walking surface within 60" • Walking path within 36"
- Mandatory Hazardous Locations Requiring Safety Glazing (IBC Section 2406.4)
Doors: Glazing in all swinging, sliding, folding, and revolving doors (regardless of size).
Sidelites Adjacent to Doors: Glazing in an individual pane located within 24 inches (610 mm) horizontally of either vertical door jamb, where the bottom exposed edge is less than 60 inches (1524 mm) above the floor walking surface.
Wet Locations: Glazing in walls, enclosures, or partitions enclosing showers, bathtubs, hot tubs, saunas, and swimming pools where the bottom edge of the glazing is less than 60 inches above the standing surface.
Large Windows / Fixed Panes: Glazing in an individual pane that satisfies ALL FOUR of the following conditions:
- Exposed glass surface area greater than 9 square feet (0.84 sq m) ;
- Bottom exposed edge less than 18 inches (457 mm) above the finished floor;
- Top exposed edge greater than 36 inches (914 mm) above the finished floor; AND
One or more walking surfaces located within 36 inches (914 mm) horizontally of the plane of the glass.
Guards & Handrails: All glazed panels in guardrails, balustrades, stair rails, and glass handrail systems (must be fully tempered or laminated glass).
Structural Silicone Glazing (SSG)
In modern high-performance architectural facades, Structural Silicone Glazing (SSG) utilizes high-modulus, structural-grade elastomeric silicone sealants to bond glass lites directly to the supporting aluminum framing:
Mechanical Elimination: Replaces traditional exterior aluminum pressure plates and snap-on beauty caps with a continuous structural sealant bead, creating a flush, seamless all-glass facade.
2-Sided vs. 4-Sided SSG:
2-Sided SSG: Structural silicone is applied along two opposite sides (typically vertical mullions), while the horizontal joints are retained mechanically with aluminum pressure plates.
4-Sided SSG: All four edges of the glass lite are bonded exclusively with structural silicone. Wind loads and dead loads are transferred entirely through silicone adhesion into the framing.
Quality Control & Testing: SSG requires rigorous factory cleanroom conditions, solvent degreasing, silicone adhesion peel testing (ASTM C1135), and strict chemical compatibility verification of all EPDM setting blocks, gaskets, and spacer tapes.