7.2 Concrete Placement, Hot/Cold Weather, Curing & Defects

Georgia General Contractor Exam

Track your progress as you read

Finished sections get a check mark.

1 Chapter 0: Exam Orientation, Blueprint & Open-Book Method

0.1 Official Exam Facts, Content Outlines & Approved References 0.2 Open-Book Navigation, Reference Indexing & Study Plan

2 Chapter 1: Georgia Contractor Licensing & Regulatory Law

1.1 Board Authority & Commercial General Contractor Tiers 1.2 Scope, Exemptions & Unlicensed Contracting 1.3 Eligibility, Experience Requirements & Qualifying Agents 1.4 Financial Responsibility, Net Worth, Surety Bonds & Insurance 1.5 License Renewal, No-CE Rule & Disciplinary Actions

3 Chapter 2: Georgia Construction & Lien Law

2.1 Georgia Mechanics & Materialmen's Liens 2.2 Project Notices: Notice of Commencement, Notice to Contractor & Preliminary Notice 2.3 Statutory Lien Waivers & Affidavits of Nonpayment 2.4 Georgia Prompt Pay Act & Right to Repair Act

4 Chapter 3: Business Organization, Financial Management & Taxes

3.1 Business Entity Selection & Joint Ventures 3.2 Georgia Entity Registration, Foreign Qualification & Trade Names 3.3 Construction Accounting, WIP & Financial Statements 3.4 Cash Flow, Working Capital & Construction Banking 3.5 Federal, Georgia & Payroll Tax Administration 3.6 Worker Classification, Wage-and-Hour & Prevailing Wage

5 Chapter 4: Construction Contracts, Bidding & Risk Management

4.1 Contract Pricing Models & Cost Risk 4.2 Project Delivery Methods & Responsibility 4.3 Essential Contract Clauses & Risk Allocation 4.4 Standard Documents: AIA, ConsensusDocs & EJCDC 4.5 Quantity Takeoff, Direct Cost & Markup 4.6 Bid Scope Review, Submission & Withdrawal 4.7 Surety Bonds, Insurance & Risk Management

6 Chapter 5: Project Management, Scheduling & Quality Control

5.1 Project Planning, WBS, Logic & Resources 5.2 CPM, Float, Updating & Schedule Compression 5.3 Project Administration, Submittals, RFIs & Records 5.4 Changes, Delays, Claims & Dispute Resolution 5.5 QA/QC, Special Inspections & Closeout

7 Chapter 6: Georgia Building Codes, Environmental Regulations & Site Work

6.1 Current Georgia Codes, Amendments, Permits & Inspections 6.2 Occupancy, Construction Type, Egress & Accessibility 6.3 GESA, NPDES, Buffers, BMPs & Certified Personnel 6.4 Survey Control, Layout, Clearing & Site Preparation 6.5 Excavation, Earthwork Volumes, Hauling & Compaction 6.6 Shallow Foundations, Slabs, Deep Systems & Drainage

8 Chapter 7: Concrete & Masonry Construction

7.1 Concrete Materials, Mix Design & Field Testing 7.2 Concrete Placement, Hot/Cold Weather, Curing & Defects 7.3 Formwork, Shores, Reshores & Removal 7.4 Reinforcing Steel, Splices & Post-Tensioning 7.5 Masonry Units, Mortar, Grout & Testing 7.6 Masonry Walls, Reinforcement, Flashing & Movement Joints

9 Chapter 8: Structural Steel, Metals & Framing Systems

8.1 Structural Steel Shapes, Framing & Erection Stability 8.2 Bolted Connections, Welding & Nondestructive Testing 8.3 Steel Joists, Deck & Cold-Formed Framing 8.4 Heavy Timber, Fire Performance & Mass Timber 8.5 Engineered Wood, I-Joists, Trusses & Connectors 8.6 Wood Framing, Sheathing, Bracing & Fastening

10 Chapter 9: Building Envelope, Thermal & Moisture Protection, Doors & Windows

9.1 Low-Slope Roofing, Insulation & Drainage 9.2 Steep-Slope Roofing, Sheet Metal & Flashing 9.3 Insulation, Air Barriers & Vapor Control 9.4 Commercial Doors, Frames, Hardware & Fire Assemblies 9.5 Windows, Storefronts & Curtain Walls 9.6 Insulating Glass, Safety Glazing & Water Control

11 Chapter 10: Finishes, Mechanical, Electrical & Plumbing Coordination

10.1 Gypsum Assemblies, Ceilings & Finish Coordination 10.2 Concrete Moisture, Flooring & Tile Assemblies 10.3 HVAC, Ductwork, Dampers & Mechanical Coordination 10.4 Plumbing, DWV, Venting & Backflow 10.5 Fire Sprinklers, Standpipes & Fire Department Connections 10.6 Electrical Distribution, Grounding & Emergency Systems

12 Chapter 11: Construction Safety & OSHA Standards (29 CFR Part 1926)

11.1 OSHA Authority, Inspections, Reporting & Multi-Employer Sites 11.2 Fall Protection, Clearance Planning & Scaffolds 11.3 Excavation, Protective Systems & Trench Safety 11.4 Hazard Communication, Silica, Temporary Power & PPE 11.5 Cranes, Rigging, Signal Persons & Power-Line Safety

7.2 Concrete Placement, Hot/Cold Weather, Curing & Defects

Key Takeaways Explain This Topic AI

Placement, consolidation, finishing, and curing must be planned as one operation.

Hot weather accelerates slump loss and evaporation; cold weather delays strength and raises freezing risk.

Curing maintains moisture and temperature so hydration can develop required properties.

Last updated: August 2026

  • 7.2 Concrete Placement, Hot/Cold Weather, Curing & Defects
  • Environmental Concreting: Hot vs. Cold Weather Protocols

Ambient climate significantly affects hydration kinetics, setting times, plastic shrinkage, and ultimate load-bearing capacity.

Hot Weather Concreting (ACI 305R)

Hot weather conditions exist when high ambient temperature, low relative humidity, solar radiation, and wind velocity accelerate water evaporation from the fresh surface. High temperatures increase water demand, cause rapid slump loss, accelerate setting, and increase the risk of plastic shrinkage cracking . Use the current ACI evaporation guidance and project specification; an old memorized threshold does not replace evaluation of temperature, humidity, wind, and concrete temperature.

Maximum Fresh Concrete Temperature: ACI hot-weather guidance does not make one temperature limit universal to every mixture and specification. Confirm the project limit and use an approved hot-weather plan when conditions threaten placement, finishing, curing, or required properties.

Field Mitigation Techniques:

Replace a portion of the batch mixing water with shaved ice or inject liquid nitrogen ( L N 2 LN_2 L N 2 ​ ) directly into ready-mix truck drums;

Cool aggregate or batch water by an approved method while measuring aggregate moisture and adjusting batch water;

  • Use ASTM C494 Type D or Type G retarding admixtures;
  • Erect temporary windbreaks and sunshades over slab placements;
  • Schedule concrete pours during nighttime or early morning hours;

Apply spray-on evaporation retarders (monomolecular films) immediately after screeding to prevent surface drying.

Cold Weather Concreting (ACI 306R)

Current ACI cold-weather guidance applies when air temperature has fallen to, or is expected to fall below, 40°F (4°C) during the protection period. The older multi-day definition is a common distractor; use the edition and specification governing the work.

Critical Freezing Rule: Fresh concrete must never be allowed to freeze before reaching a minimum compressive strength of 500 psi (3.5 MPa) . If concrete freezes while saturated before reaching 500 psi, ice crystal expansion causes irreversible internal micro-fracturing, reducing ultimate compressive strength by up to 50% .

Placement & Curing Requirements:

Never place concrete on frozen ground, ice, or snow-covered formwork (thaw subgrade completely);

Heat materials only within the producer-approved mixture and ACI limits, preventing cement contact with excessively hot water;

Maintain and monitor the concrete temperature for the member size, mixture, required strength, exposure, and protection period stated by the approved plan;

Use safely vented heating and protect surfaces from drying and combustion products. Unvented heaters can add carbon dioxide, moisture, and safety hazards; the plan must address ventilation, fire, carbon monoxide, and surface carbonation rather than relying on an unsupported universal equipment slogan.

Curing Methods & Duration Standards

Curing is the deliberate maintenance of satisfactory moisture content and temperature in concrete during its early hydration stages. Without adequate curing, surface paste dries prematurely, leading to crazing, dusting, high permeability, and severe strength loss. ┌─────────────────────────────────────────┐

  • │ CONCRETE CURING METHODOLOGIES │
  • └────────────────────┬────────────────────┘
  • │
  • ┌───────────────────────────────┼───────────────────────────────┐
  • ▼ ▼ ▼
  • ┌─────────────────┐ ┌─────────────────┐ ┌─────────────────┐
  • │ WATER PONDING / │ │IMPERVIOUS SHEET │ │ MEMBRANE LIQUID │
  • │ WET BURLAP │ │ MEMBRANES │ │ COMPOUNDS │
  • │ Continuous wet │ │Polyethylene film│ │ASTM C309 Type 1 │
  • │ saturation for │ │or waterproof │ │clear or Type 2 │
  • │ maximum quality │ │curing blankets │ │white-pigmented │
  • └─────────────────┘ └─────────────────┘ └─────────────────┘
  • Primary Curing Methods

Continuous Water Curing (Flooding / Ponding / Wet Burlap): The most effective curing method. Involves continuous water ponding on flat slabs or covering exposed surfaces with cotton mats / burlap kept continuously saturated with clean water. Prevents moisture loss and cools the hydration reaction.

Impervious Sheet Curing (ASTM C171): Covering wet concrete with white polyethylene sheeting or waterproof kraft paper, overlapping sheets 6 inches and taping all seams to trap mixing water.

Liquid Membrane-Forming Curing Compounds (ASTM C309): Spray-applied chemical resins, waxes, or polymers that form a water-retaining barrier over fresh concrete. Must be applied immediately after final finishing and just as the surface bleed-water sheen disappears:

Type 1: Clear or translucent (for architectural surfaces);

Type 2: White-pigmented (mandatory for outdoor highway paving and slabs to reflect solar heat and visually verify uniform coverage).

Curing duration and acceptance

Curing duration comes from the governing ACI specification, mixture, exposure, member, temperature, and strength-development option. Traditional rules of thumb such as 7 days for ordinary cement, 3 days for high-early-strength cement, or longer periods for mixtures with supplementary cementitious materials can be study aids, but they are not automatic substitutions for the contract. Continue curing until the selected specification criterion is satisfied and protect the concrete from harmful thermal shock after heated protection ends.

The placement record should capture batch tickets, water added, arrival and discharge times, slump or slump flow, air, concrete temperature, cylinders, weather, evaporation controls, curing start, and protection temperatures. Reject the exam shortcut that adds water to restore slump without authorization: it can change the water-cementitious ratio, strength, durability, and air system. A pre-pour conference assigns who may adjust the mix, who samples, and who decides when placement stops.