Study guide
4.1 Contract Pricing Models & Cost Risk
Georgia General Contractor Exam
Track your progress as you read
Finished sections get a check mark.
1 Chapter 0: Exam Orientation, Blueprint & Open-Book Method
0.1 Official Exam Facts, Content Outlines & Approved References 0.2 Open-Book Navigation, Reference Indexing & Study Plan
2 Chapter 1: Georgia Contractor Licensing & Regulatory Law
1.1 Board Authority & Commercial General Contractor Tiers 1.2 Scope, Exemptions & Unlicensed Contracting 1.3 Eligibility, Experience Requirements & Qualifying Agents 1.4 Financial Responsibility, Net Worth, Surety Bonds & Insurance 1.5 License Renewal, No-CE Rule & Disciplinary Actions
3 Chapter 2: Georgia Construction & Lien Law
2.1 Georgia Mechanics & Materialmen's Liens 2.2 Project Notices: Notice of Commencement, Notice to Contractor & Preliminary Notice 2.3 Statutory Lien Waivers & Affidavits of Nonpayment 2.4 Georgia Prompt Pay Act & Right to Repair Act
4 Chapter 3: Business Organization, Financial Management & Taxes
3.1 Business Entity Selection & Joint Ventures 3.2 Georgia Entity Registration, Foreign Qualification & Trade Names 3.3 Construction Accounting, WIP & Financial Statements 3.4 Cash Flow, Working Capital & Construction Banking 3.5 Federal, Georgia & Payroll Tax Administration 3.6 Worker Classification, Wage-and-Hour & Prevailing Wage
5 Chapter 4: Construction Contracts, Bidding & Risk Management
4.1 Contract Pricing Models & Cost Risk 4.2 Project Delivery Methods & Responsibility 4.3 Essential Contract Clauses & Risk Allocation 4.4 Standard Documents: AIA, ConsensusDocs & EJCDC 4.5 Quantity Takeoff, Direct Cost & Markup 4.6 Bid Scope Review, Submission & Withdrawal 4.7 Surety Bonds, Insurance & Risk Management
6 Chapter 5: Project Management, Scheduling & Quality Control
5.1 Project Planning, WBS, Logic & Resources 5.2 CPM, Float, Updating & Schedule Compression 5.3 Project Administration, Submittals, RFIs & Records 5.4 Changes, Delays, Claims & Dispute Resolution 5.5 QA/QC, Special Inspections & Closeout
7 Chapter 6: Georgia Building Codes, Environmental Regulations & Site Work
6.1 Current Georgia Codes, Amendments, Permits & Inspections 6.2 Occupancy, Construction Type, Egress & Accessibility 6.3 GESA, NPDES, Buffers, BMPs & Certified Personnel 6.4 Survey Control, Layout, Clearing & Site Preparation 6.5 Excavation, Earthwork Volumes, Hauling & Compaction 6.6 Shallow Foundations, Slabs, Deep Systems & Drainage
8 Chapter 7: Concrete & Masonry Construction
7.1 Concrete Materials, Mix Design & Field Testing 7.2 Concrete Placement, Hot/Cold Weather, Curing & Defects 7.3 Formwork, Shores, Reshores & Removal 7.4 Reinforcing Steel, Splices & Post-Tensioning 7.5 Masonry Units, Mortar, Grout & Testing 7.6 Masonry Walls, Reinforcement, Flashing & Movement Joints
9 Chapter 8: Structural Steel, Metals & Framing Systems
8.1 Structural Steel Shapes, Framing & Erection Stability 8.2 Bolted Connections, Welding & Nondestructive Testing 8.3 Steel Joists, Deck & Cold-Formed Framing 8.4 Heavy Timber, Fire Performance & Mass Timber 8.5 Engineered Wood, I-Joists, Trusses & Connectors 8.6 Wood Framing, Sheathing, Bracing & Fastening
10 Chapter 9: Building Envelope, Thermal & Moisture Protection, Doors & Windows
9.1 Low-Slope Roofing, Insulation & Drainage 9.2 Steep-Slope Roofing, Sheet Metal & Flashing 9.3 Insulation, Air Barriers & Vapor Control 9.4 Commercial Doors, Frames, Hardware & Fire Assemblies 9.5 Windows, Storefronts & Curtain Walls 9.6 Insulating Glass, Safety Glazing & Water Control
11 Chapter 10: Finishes, Mechanical, Electrical & Plumbing Coordination
10.1 Gypsum Assemblies, Ceilings & Finish Coordination 10.2 Concrete Moisture, Flooring & Tile Assemblies 10.3 HVAC, Ductwork, Dampers & Mechanical Coordination 10.4 Plumbing, DWV, Venting & Backflow 10.5 Fire Sprinklers, Standpipes & Fire Department Connections 10.6 Electrical Distribution, Grounding & Emergency Systems
12 Chapter 11: Construction Safety & OSHA Standards (29 CFR Part 1926)
11.1 OSHA Authority, Inspections, Reporting & Multi-Employer Sites 11.2 Fall Protection, Clearance Planning & Scaffolds 11.3 Excavation, Protective Systems & Trench Safety 11.4 Hazard Communication, Silica, Temporary Power & PPE 11.5 Cranes, Rigging, Signal Persons & Power-Line Safety
4.1 Contract Pricing Models & Cost Risk
Key Takeaways Explain This Topic AI
Pricing model allocates cost overrun, quantity, and transparency risk.
A GMP needs precise definitions of allowable cost, contingency, fee, and savings.
Unit-price work requires reliable measurement and payment rules.
Last updated: August 2026
4.1 Contract Pricing Models & Cost Risk
A construction contract is the foundational legal instrument that defines the rights, responsibilities, risk allocation, and compensation mechanisms between the project owner and the general contractor. In commercial construction, selecting the appropriate contract type and project delivery method establishes how design and construction proceed, who bears the financial burden of unforeseen site conditions or material cost volatility, and how project disputes are adjudicated. General contractors operating in Georgia must master both standard industry contracts and statutory contract requirements to protect their cash flow, bonding capacity, and corporate liability.
1. Construction Contract Pricing Models
The pricing structure of a construction agreement dictates how the contractor is reimbursed for labor, materials, equipment, and overhead, and establishes which party bears the risk of cost overruns. +---------------------------------------------------------------------------------------------------------+
- | CONSTRUCTION CONTRACT RISK SPECTRUM |
- | |
- | MAXIMUM CONTRACTOR RISK MAXIMUM OWNER RISK |
- | <-------------------------------------------------------------------------------------------------> |
- | [ LUMP SUM / STIPULATED SUM ] ---> [ GMP WITH SHARED SAVINGS ] ---> [ UNIT PRICE ] ---> [ COST-PLUS ] |
- | Contractor absorbs all cost Contractor absorbs overruns; Owner absorbs volume Owner |
- | overruns; retains 100% savings. owner/GC share savings below GMP. variations at fixed unit. pays. |
- +---------------------------------------------------------------------------------------------------------+
- Lump Sum / Stipulated Sum Contracts
In a Lump Sum or Stipulated Sum contract (such as AIA Document A101), the contractor agrees to complete the entire scope of work defined in the plans and specifications for a fixed, single dollar amount.
Risk Allocation: The general contractor bears nearly 100% of the cost risk. If material prices spike, labor productivity drops, or subcontractor defaults occur, the contractor's profit margin is eroded. Conversely, if the contractor achieves labor efficiencies or negotiates lower material prices, the contractor retains 100% of the cost savings.
Suitability: Optimal for projects with fully completed, detailed design documents (100% Construction Documents), well-defined site conditions, and minimal anticipated design changes.
Owner Pros & Cons: High price certainty upfront; however, changes during construction require formal Change Orders, which often carry high markups and can trigger contentious scope disputes.
Cost-Plus Contracts (Cost-Plus-Fee)
Under a Cost-Plus agreement, the owner reimburses the contractor for the actual direct "Cost of the Work" (labor, materials, equipment, subcontracts) plus an agreed-upon contractor fee for home office overhead and profit.
Fee Structures:
Cost-Plus-Percentage: The fee is calculated as a fixed percentage of total job costs (e.g., Cost + 8%). While simple, this provides a disincentive for contractor cost control because higher job costs yield a higher contractor fee.
Cost-Plus-Fixed-Fee: The fee is a predetermined, fixed dollar amount regardless of total project cost (e.g., Cost + $250,000 fee). This aligns contractor incentives with budget control, as delays and cost growth do not increase the contractor's net fee.
Risk Allocation: The project owner assumes almost all financial risk of cost overruns. The contractor is obligated only to exercise professional care and maintain transparent accounting records.
Suitability: Used when the scope cannot be accurately defined upfront, such as emergency repairs, fast-track exploratory renovations, or historic restorations.
Guaranteed Maximum Price (GMP) Contracts
A Guaranteed Maximum Price (GMP) contract (such as AIA Document A102) is a hybrid structure combining Cost-Plus accounting with a hard cost ceiling. The contractor is reimbursed for actual costs plus fee up to the agreed GMP threshold.
Cost Overruns: If total costs exceed the GMP (excluding approved owner change orders), the general contractor pays 100% of the overage out of pocket.
Cost Underruns & Shared Savings: If the project is completed beneath the GMP, the remaining balance ("savings") reverts to the owner, or is shared between owner and contractor according to a negotiated contractual split (e.g., 75% to Owner / 25% to Contractor).
Contingency Management: GMP contracts typically establish a Contractor's Contingency within the GMP to absorb internal trade buyout gaps, scope creep, or minor coordination errors without requiring owner change orders.
Unit Price Contracts
In Unit Price contracts, the total contract value is based on established fixed rates for specified units of work (e.g., $45 per cubic yard of mass excavation; $120 per linear foot of 12-inch storm sewer pipe; $85 per square yard of asphalt paving).
Measurement & Payment: The owner or civil engineer field-measures actual quantities placed in place, and progress payments are calculated by multiplying certified quantities by unit bid prices.
Risk Allocation: The contractor bears the risk of unit cost accuracy (labor and equipment productivity per unit), while the owner bears the quantity risk (total volume of work required).
Suitability: Standard for heavy civil engineering, highway infrastructure (GDOT projects), mass grading, utility pipeline installation, and foundation drilling where underground quantities cannot be verified before excavation.
Target Price / Target Value Design Contracts
Used primarily in progressive Integrated Project Delivery (IPD) models, a Target Price contract sets a collaborative target cost determined jointly by owner, designer, and trade contractors. If final costs are below the target, all participants share the financial reward; if costs exceed the target, the team shares the financial downside, creating mutual accountability.