Study guide

11.5 Cranes, Rigging, Signal Persons & Power-Line Safety

Georgia General Contractor Exam

Track your progress as you read

Finished sections get a check mark.

1 Chapter 0: Exam Orientation, Blueprint & Open-Book Method

0.1 Official Exam Facts, Content Outlines & Approved References 0.2 Open-Book Navigation, Reference Indexing & Study Plan

2 Chapter 1: Georgia Contractor Licensing & Regulatory Law

1.1 Board Authority & Commercial General Contractor Tiers 1.2 Scope, Exemptions & Unlicensed Contracting 1.3 Eligibility, Experience Requirements & Qualifying Agents 1.4 Financial Responsibility, Net Worth, Surety Bonds & Insurance 1.5 License Renewal, No-CE Rule & Disciplinary Actions

3 Chapter 2: Georgia Construction & Lien Law

2.1 Georgia Mechanics & Materialmen's Liens 2.2 Project Notices: Notice of Commencement, Notice to Contractor & Preliminary Notice 2.3 Statutory Lien Waivers & Affidavits of Nonpayment 2.4 Georgia Prompt Pay Act & Right to Repair Act

4 Chapter 3: Business Organization, Financial Management & Taxes

3.1 Business Entity Selection & Joint Ventures 3.2 Georgia Entity Registration, Foreign Qualification & Trade Names 3.3 Construction Accounting, WIP & Financial Statements 3.4 Cash Flow, Working Capital & Construction Banking 3.5 Federal, Georgia & Payroll Tax Administration 3.6 Worker Classification, Wage-and-Hour & Prevailing Wage

5 Chapter 4: Construction Contracts, Bidding & Risk Management

4.1 Contract Pricing Models & Cost Risk 4.2 Project Delivery Methods & Responsibility 4.3 Essential Contract Clauses & Risk Allocation 4.4 Standard Documents: AIA, ConsensusDocs & EJCDC 4.5 Quantity Takeoff, Direct Cost & Markup 4.6 Bid Scope Review, Submission & Withdrawal 4.7 Surety Bonds, Insurance & Risk Management

6 Chapter 5: Project Management, Scheduling & Quality Control

5.1 Project Planning, WBS, Logic & Resources 5.2 CPM, Float, Updating & Schedule Compression 5.3 Project Administration, Submittals, RFIs & Records 5.4 Changes, Delays, Claims & Dispute Resolution 5.5 QA/QC, Special Inspections & Closeout

7 Chapter 6: Georgia Building Codes, Environmental Regulations & Site Work

6.1 Current Georgia Codes, Amendments, Permits & Inspections 6.2 Occupancy, Construction Type, Egress & Accessibility 6.3 GESA, NPDES, Buffers, BMPs & Certified Personnel 6.4 Survey Control, Layout, Clearing & Site Preparation 6.5 Excavation, Earthwork Volumes, Hauling & Compaction 6.6 Shallow Foundations, Slabs, Deep Systems & Drainage

8 Chapter 7: Concrete & Masonry Construction

7.1 Concrete Materials, Mix Design & Field Testing 7.2 Concrete Placement, Hot/Cold Weather, Curing & Defects 7.3 Formwork, Shores, Reshores & Removal 7.4 Reinforcing Steel, Splices & Post-Tensioning 7.5 Masonry Units, Mortar, Grout & Testing 7.6 Masonry Walls, Reinforcement, Flashing & Movement Joints

9 Chapter 8: Structural Steel, Metals & Framing Systems

8.1 Structural Steel Shapes, Framing & Erection Stability 8.2 Bolted Connections, Welding & Nondestructive Testing 8.3 Steel Joists, Deck & Cold-Formed Framing 8.4 Heavy Timber, Fire Performance & Mass Timber 8.5 Engineered Wood, I-Joists, Trusses & Connectors 8.6 Wood Framing, Sheathing, Bracing & Fastening

10 Chapter 9: Building Envelope, Thermal & Moisture Protection, Doors & Windows

9.1 Low-Slope Roofing, Insulation & Drainage 9.2 Steep-Slope Roofing, Sheet Metal & Flashing 9.3 Insulation, Air Barriers & Vapor Control 9.4 Commercial Doors, Frames, Hardware & Fire Assemblies 9.5 Windows, Storefronts & Curtain Walls 9.6 Insulating Glass, Safety Glazing & Water Control

11 Chapter 10: Finishes, Mechanical, Electrical & Plumbing Coordination

10.1 Gypsum Assemblies, Ceilings & Finish Coordination 10.2 Concrete Moisture, Flooring & Tile Assemblies 10.3 HVAC, Ductwork, Dampers & Mechanical Coordination 10.4 Plumbing, DWV, Venting & Backflow 10.5 Fire Sprinklers, Standpipes & Fire Department Connections 10.6 Electrical Distribution, Grounding & Emergency Systems

12 Chapter 11: Construction Safety & OSHA Standards (29 CFR Part 1926)

11.1 OSHA Authority, Inspections, Reporting & Multi-Employer Sites 11.2 Fall Protection, Clearance Planning & Scaffolds 11.3 Excavation, Protective Systems & Trench Safety 11.4 Hazard Communication, Silica, Temporary Power & PPE 11.5 Cranes, Rigging, Signal Persons & Power-Line Safety

11.5 Cranes, Rigging, Signal Persons & Power-Line Safety

Key Takeaways Explain This Topic AI

Crane capacity depends on the exact configuration, radius, boom length and angle, deductions, setup, and manufacturer load chart.

Operators follow Subpart CC certification rules; signal persons must be qualified, and riggers must be qualified for the specific rigging work without a universal certification mandate.

OSHA Table A uses voltage bands above 50 kV rather than a 10-foot-plus-linear-inches formula.

Planning must include ground conditions, assembly/disassembly, swing radius, communication, lift path, weather, and power-line controls.

Last updated: August 2026

11.5 Cranes, Rigging, Signal Persons & Power-Line Safety

Cranes amplify planning errors. Before setup, identify the load, center of gravity, rigging, pick and set points, travel path, operating radius, crane configuration, ground support, underground hazards, obstructions, weather, personnel, and energized power lines. Use the manufacturer load chart for the exact machine and configuration.

Capacity and setup

Crane capacity falls as operating radius increases. The radius is measured from the axis of rotation to the load's center of gravity, not to the boom tip. Determine gross load by including the object, hook block or ball, slings, shackles, spreader beams, lifting devices, and other chart deductions. Use the chart quadrant, boom length, angle, parts of line, counterweight, outrigger position, and configuration that actually exist.

The controlling entity must provide ground conditions that are firm, drained, and graded sufficiently, with supporting materials when needed. The operator or competent setup personnel verify outriggers, cribbing, level, clearance, and manufacturer limits. Barricade the swing radius where employees could be struck or crushed by the rotating superstructure.

Assembly and disassembly follow manufacturer procedures or employer procedures developed by a qualified person. A competent and qualified assembly/disassembly director controls the operation. Do not release pins, pendants, or sections until their movement and load are understood and supported.

People and communication

Operators must satisfy OSHA Subpart CC training, certification or licensing, and evaluation requirements. Certification can be by crane type or by type and capacity under the standard; do not assume every credential must state capacity. The employer also evaluates the operator for the equipment and work assigned.

A signal person is required when the point of operation is not in full view, the operator's travel view is obstructed, site-specific safety concerns require one, or the operator or load handler requests one. The signal person must be qualified through an employer or third-party evaluator and demonstrate knowledge of signals, equipment limitations relevant to signaling, and the standard. Qualification is not synonymous with a mandatory third-party certification card.

A qualified rigger is required for specified assembly/disassembly and other covered work. OSHA defines qualification by recognized degree, certificate, professional standing, or extensive knowledge, training, and experience with demonstrated ability. There is no universal rule that every rigger hold an accredited certification. Qualification must fit the rigging and load.

Use one designated signal person at a time except that anyone may give a stop or emergency-stop signal. Agree on hand, radio, or other signals before the lift. The operator obeys a stop signal and halts when communication is lost.

Rigging and load control

Inspect slings and rigging before use as the applicable standard requires. Verify identification, rated capacity for hitch and angle, edge protection, hardware compatibility, center of gravity, and load control. Sling tension rises as the angle from horizontal becomes smaller. Never use an unverified shortcut in place of the manufacturer table or engineered calculation. Remove damaged rigging under the applicable discard criteria; criteria differ for alloy-chain, wire-rope, synthetic-web, round, and metal-mesh slings.

Keep employees out of the fall zone except as allowed for essential hooking, guiding, or receiving work. Use tag lines when needed without placing employees in a pinch point. A critical-lift plan should define the organization's chosen threshold, approvals, redundancy, communications, weather limits, and stop-work authority; OSHA does not impose one universal percentage definition for every project.

Power-line safety and Table A

First determine whether equipment, load line, or load could come within 20 feet of a power line. Deenergization and visible grounding, with utility confirmation, is preferred. If operating under the clearance option, identify voltage and use OSHA Table A:

  • Nominal voltage Minimum clearance
  • Up to 50 kV 10 feet
  • Over 50 through 200 kV 15 feet
  • Over 200 through 350 kV 20 feet
  • Over 350 through 500 kV 25 feet
  • Over 500 through 750 kV 35 feet
  • Over 750 through 1,000 kV 45 feet
  • Over 1,000 kV Utility/owner or registered professional engineer determination under the standard

Table A does not use the older 10-feet-plus-0.4-inches-per-kV formula. Implement the required planning meeting, encroachment prevention, warning line or barricade, dedicated spotter or permitted device, and operator warning. Treat lines as energized unless the utility owner confirms deenergization and grounding.

Stop-work rule

Stop when voltage is unknown, setup changes, ground settles, wind exceeds the governing limit, communication fails, the load chart does not match configuration, or load weight and center of gravity are uncertain. Resolve the condition before resuming.