10.2 Concrete Moisture, Flooring & Tile Assemblies
Georgia General Contractor Exam
Track your progress as you read
Finished sections get a check mark.
1 Chapter 0: Exam Orientation, Blueprint & Open-Book Method
0.1 Official Exam Facts, Content Outlines & Approved References 0.2 Open-Book Navigation, Reference Indexing & Study Plan
2 Chapter 1: Georgia Contractor Licensing & Regulatory Law
1.1 Board Authority & Commercial General Contractor Tiers 1.2 Scope, Exemptions & Unlicensed Contracting 1.3 Eligibility, Experience Requirements & Qualifying Agents 1.4 Financial Responsibility, Net Worth, Surety Bonds & Insurance 1.5 License Renewal, No-CE Rule & Disciplinary Actions
3 Chapter 2: Georgia Construction & Lien Law
2.1 Georgia Mechanics & Materialmen's Liens 2.2 Project Notices: Notice of Commencement, Notice to Contractor & Preliminary Notice 2.3 Statutory Lien Waivers & Affidavits of Nonpayment 2.4 Georgia Prompt Pay Act & Right to Repair Act
4 Chapter 3: Business Organization, Financial Management & Taxes
3.1 Business Entity Selection & Joint Ventures 3.2 Georgia Entity Registration, Foreign Qualification & Trade Names 3.3 Construction Accounting, WIP & Financial Statements 3.4 Cash Flow, Working Capital & Construction Banking 3.5 Federal, Georgia & Payroll Tax Administration 3.6 Worker Classification, Wage-and-Hour & Prevailing Wage
5 Chapter 4: Construction Contracts, Bidding & Risk Management
4.1 Contract Pricing Models & Cost Risk 4.2 Project Delivery Methods & Responsibility 4.3 Essential Contract Clauses & Risk Allocation 4.4 Standard Documents: AIA, ConsensusDocs & EJCDC 4.5 Quantity Takeoff, Direct Cost & Markup 4.6 Bid Scope Review, Submission & Withdrawal 4.7 Surety Bonds, Insurance & Risk Management
6 Chapter 5: Project Management, Scheduling & Quality Control
5.1 Project Planning, WBS, Logic & Resources 5.2 CPM, Float, Updating & Schedule Compression 5.3 Project Administration, Submittals, RFIs & Records 5.4 Changes, Delays, Claims & Dispute Resolution 5.5 QA/QC, Special Inspections & Closeout
7 Chapter 6: Georgia Building Codes, Environmental Regulations & Site Work
6.1 Current Georgia Codes, Amendments, Permits & Inspections 6.2 Occupancy, Construction Type, Egress & Accessibility 6.3 GESA, NPDES, Buffers, BMPs & Certified Personnel 6.4 Survey Control, Layout, Clearing & Site Preparation 6.5 Excavation, Earthwork Volumes, Hauling & Compaction 6.6 Shallow Foundations, Slabs, Deep Systems & Drainage
8 Chapter 7: Concrete & Masonry Construction
7.1 Concrete Materials, Mix Design & Field Testing 7.2 Concrete Placement, Hot/Cold Weather, Curing & Defects 7.3 Formwork, Shores, Reshores & Removal 7.4 Reinforcing Steel, Splices & Post-Tensioning 7.5 Masonry Units, Mortar, Grout & Testing 7.6 Masonry Walls, Reinforcement, Flashing & Movement Joints
9 Chapter 8: Structural Steel, Metals & Framing Systems
8.1 Structural Steel Shapes, Framing & Erection Stability 8.2 Bolted Connections, Welding & Nondestructive Testing 8.3 Steel Joists, Deck & Cold-Formed Framing 8.4 Heavy Timber, Fire Performance & Mass Timber 8.5 Engineered Wood, I-Joists, Trusses & Connectors 8.6 Wood Framing, Sheathing, Bracing & Fastening
10 Chapter 9: Building Envelope, Thermal & Moisture Protection, Doors & Windows
9.1 Low-Slope Roofing, Insulation & Drainage 9.2 Steep-Slope Roofing, Sheet Metal & Flashing 9.3 Insulation, Air Barriers & Vapor Control 9.4 Commercial Doors, Frames, Hardware & Fire Assemblies 9.5 Windows, Storefronts & Curtain Walls 9.6 Insulating Glass, Safety Glazing & Water Control
11 Chapter 10: Finishes, Mechanical, Electrical & Plumbing Coordination
10.1 Gypsum Assemblies, Ceilings & Finish Coordination 10.2 Concrete Moisture, Flooring & Tile Assemblies 10.3 HVAC, Ductwork, Dampers & Mechanical Coordination 10.4 Plumbing, DWV, Venting & Backflow 10.5 Fire Sprinklers, Standpipes & Fire Department Connections 10.6 Electrical Distribution, Grounding & Emergency Systems
12 Chapter 11: Construction Safety & OSHA Standards (29 CFR Part 1926)
11.1 OSHA Authority, Inspections, Reporting & Multi-Employer Sites 11.2 Fall Protection, Clearance Planning & Scaffolds 11.3 Excavation, Protective Systems & Trench Safety 11.4 Hazard Communication, Silica, Temporary Power & PPE 11.5 Cranes, Rigging, Signal Persons & Power-Line Safety
10.2 Concrete Moisture, Flooring & Tile Assemblies
Key Takeaways Explain This Topic AI
Test method and acceptance limit come from the specified flooring and adhesive system.
Concrete moisture results are location- and time-specific.
Tile movement joints continue through the finish and are not filled with rigid grout.
Last updated: August 2026
- 10.2 Concrete Moisture, Flooring & Tile Assemblies
- Flooring Installations & Concrete Moisture Vapor Testing
Flooring failures (adhesive debonding, vinyl blistering, microbial growth, wood buckling) represent a leading source of commercial construction claims. General contractors are responsible for testing and preparing concrete substrates before flooring installation.
- | Test | What it measures | Acceptance source | Key control |
- +|---|---|---|---|
+| ASTM F1869 calcium chloride | Surface moisture-vapor emission rate | Flooring, adhesive, or mitigation manufacturer and specification | Prepare the test area and follow exposure, mass, area, and time procedures |
+| ASTM F2170 in-situ RH | Internal slab relative humidity | Flooring, adhesive, or mitigation manufacturer and specification | Probe at the prescribed depth and equilibrium conditions |
+| ASTM F710 surface checks | Substrate condition, including pH and preparation | Product instructions and project specification | Evaluate cleanliness, soundness, flatness, porosity, and chemistry |
+| ASTM D4263 plastic sheet | Qualitative indication of moisture | Diagnostic only; not a numeric flooring acceptance substitute | Interpret with the project team rather than using it to replace specified testing |
Decision path: identify the flooring and adhesive → obtain their written moisture and pH limits → select the specified ASTM test → verify slab conditions and calibrated equipment → map test locations → compare results with those written limits → obtain an approved mitigation or installation decision.
1. Concrete Slab Moisture Mitigation
When results exceed the written limits for the selected system, stop installation and obtain the specified response. Options can include additional drying, a compatible ASTM F3010 resin-based mitigation system, a different approved adhesive or flooring system, or redesign. Verify substrate preparation, warranty, testing after mitigation when required, and compatibility among every layer; epoxy is not an automatic universal remedy.
2. Ceramic & Porcelain Tile Assemblies (TCNA / ANSI A108)
Thin-Set Mortar Standards: Modified dry-set cement mortar ( ANSI A118.4 or improved ANSI A118.15 ) containing polymer additives to improve shear bond strength over concrete and cementitious backer boards.
Movement Accommodation Joints (TCNA EJ171): Expansion joints must be detailed throughout the tile field. Interior tile fields require movement joints spaced every 20 to 25 feet in each direction. In interior areas exposed to direct sunlight or moisture, spacing drops to 8 to 12 feet . Movement joints must be filled with elastomeric sealants (silicone or polyurethane) over closed-cell backer rods—never hard cementitious grout.
Perimeter Soft Joints: A continuous 1/4" flexible perimeter movement joint must be maintained at all wall-to-floor junctures, columns, and restraining vertical surfaces.
Flooring preinstallation conference
Record the slab placement date, curing and curing-compound history, environmental conditions, HVAC operation, floor flatness, cracks and joints, contaminants, test map, product lots, acclimation, and manufacturer limits. Assign responsibility for testing and approval. Never average a failing high reading into passing results; each location can reveal a distinct moisture path. Preserve control-joint and expansion-joint movement through the finish as the approved tile or flooring detail requires.
Substrate preparation and flatness
Flooring performance begins with a sound, clean, properly profiled substrate. Survey elevation and flatness before finish mobilization. Remove laitance, weak material, curing compounds, adhesive residue, oil, paint, and contaminants by the method approved for the slab and flooring system. Do not use acid etching or a solvent merely because it is fast; it may leave residues, alter the surface, or violate product instructions. Repair cracks only after the design team classifies their movement. Honor structural and movement joints through the finish system.
Check patching and self-leveling products for thickness, primer, moisture tolerance, cure, and compatibility. A leveler can correct local geometry but cannot stop a moving crack or an uncontrolled vapor source. Protect prepared surfaces from other trades and repeat cleanliness and moisture checks if conditions change.
Installation controls
Condition the building to the flooring manufacturer's temperature and humidity range before testing and installation, and maintain those conditions afterward. Verify material acclimation, batch and dye lots, layout, seam location, trowel notch, adhesive open time, rolling, protection, and traffic release. For resilient material, substrate telegraphing and adhesive displacement can be permanent defects. For tile, verify mortar coverage, back-buttering where required, lippage control, substrate movement accommodation, perimeter joints, and sealant compatibility.
Mockups establish appearance and workmanship but do not waive written performance requirements. Record the selected product system, approved test results, substrate release, installer qualifications, daily environmental readings, and protection. If the manufacturer representative authorizes installation outside a published limit, obtain that project-specific direction in writing and coordinate warranty responsibility before proceeding.