Study guide
1.3 Eligibility, Experience Requirements & Qualifying Agents
Georgia General Contractor Exam
Track your progress as you read
Finished sections get a check mark.
1 Chapter 0: Exam Orientation, Blueprint & Open-Book Method
0.1 Official Exam Facts, Content Outlines & Approved References 0.2 Open-Book Navigation, Reference Indexing & Study Plan
2 Chapter 1: Georgia Contractor Licensing & Regulatory Law
1.1 Board Authority & Commercial General Contractor Tiers 1.2 Scope, Exemptions & Unlicensed Contracting 1.3 Eligibility, Experience Requirements & Qualifying Agents 1.4 Financial Responsibility, Net Worth, Surety Bonds & Insurance 1.5 License Renewal, No-CE Rule & Disciplinary Actions
3 Chapter 2: Georgia Construction & Lien Law
2.1 Georgia Mechanics & Materialmen's Liens 2.2 Project Notices: Notice of Commencement, Notice to Contractor & Preliminary Notice 2.3 Statutory Lien Waivers & Affidavits of Nonpayment 2.4 Georgia Prompt Pay Act & Right to Repair Act
4 Chapter 3: Business Organization, Financial Management & Taxes
3.1 Business Entity Selection & Joint Ventures 3.2 Georgia Entity Registration, Foreign Qualification & Trade Names 3.3 Construction Accounting, WIP & Financial Statements 3.4 Cash Flow, Working Capital & Construction Banking 3.5 Federal, Georgia & Payroll Tax Administration 3.6 Worker Classification, Wage-and-Hour & Prevailing Wage
5 Chapter 4: Construction Contracts, Bidding & Risk Management
4.1 Contract Pricing Models & Cost Risk 4.2 Project Delivery Methods & Responsibility 4.3 Essential Contract Clauses & Risk Allocation 4.4 Standard Documents: AIA, ConsensusDocs & EJCDC 4.5 Quantity Takeoff, Direct Cost & Markup 4.6 Bid Scope Review, Submission & Withdrawal 4.7 Surety Bonds, Insurance & Risk Management
6 Chapter 5: Project Management, Scheduling & Quality Control
5.1 Project Planning, WBS, Logic & Resources 5.2 CPM, Float, Updating & Schedule Compression 5.3 Project Administration, Submittals, RFIs & Records 5.4 Changes, Delays, Claims & Dispute Resolution 5.5 QA/QC, Special Inspections & Closeout
7 Chapter 6: Georgia Building Codes, Environmental Regulations & Site Work
6.1 Current Georgia Codes, Amendments, Permits & Inspections 6.2 Occupancy, Construction Type, Egress & Accessibility 6.3 GESA, NPDES, Buffers, BMPs & Certified Personnel 6.4 Survey Control, Layout, Clearing & Site Preparation 6.5 Excavation, Earthwork Volumes, Hauling & Compaction 6.6 Shallow Foundations, Slabs, Deep Systems & Drainage
8 Chapter 7: Concrete & Masonry Construction
7.1 Concrete Materials, Mix Design & Field Testing 7.2 Concrete Placement, Hot/Cold Weather, Curing & Defects 7.3 Formwork, Shores, Reshores & Removal 7.4 Reinforcing Steel, Splices & Post-Tensioning 7.5 Masonry Units, Mortar, Grout & Testing 7.6 Masonry Walls, Reinforcement, Flashing & Movement Joints
9 Chapter 8: Structural Steel, Metals & Framing Systems
8.1 Structural Steel Shapes, Framing & Erection Stability 8.2 Bolted Connections, Welding & Nondestructive Testing 8.3 Steel Joists, Deck & Cold-Formed Framing 8.4 Heavy Timber, Fire Performance & Mass Timber 8.5 Engineered Wood, I-Joists, Trusses & Connectors 8.6 Wood Framing, Sheathing, Bracing & Fastening
10 Chapter 9: Building Envelope, Thermal & Moisture Protection, Doors & Windows
9.1 Low-Slope Roofing, Insulation & Drainage 9.2 Steep-Slope Roofing, Sheet Metal & Flashing 9.3 Insulation, Air Barriers & Vapor Control 9.4 Commercial Doors, Frames, Hardware & Fire Assemblies 9.5 Windows, Storefronts & Curtain Walls 9.6 Insulating Glass, Safety Glazing & Water Control
11 Chapter 10: Finishes, Mechanical, Electrical & Plumbing Coordination
10.1 Gypsum Assemblies, Ceilings & Finish Coordination 10.2 Concrete Moisture, Flooring & Tile Assemblies 10.3 HVAC, Ductwork, Dampers & Mechanical Coordination 10.4 Plumbing, DWV, Venting & Backflow 10.5 Fire Sprinklers, Standpipes & Fire Department Connections 10.6 Electrical Distribution, Grounding & Emergency Systems
12 Chapter 11: Construction Safety & OSHA Standards (29 CFR Part 1926)
11.1 OSHA Authority, Inspections, Reporting & Multi-Employer Sites 11.2 Fall Protection, Clearance Planning & Scaffolds 11.3 Excavation, Protective Systems & Trench Safety 11.4 Hazard Communication, Silica, Temporary Power & PPE 11.5 Cranes, Rigging, Signal Persons & Power-Line Safety
1.3 Eligibility, Experience Requirements & Qualifying Agents
Key Takeaways Explain This Topic AI
Commercial General Contractor applicants must be at least 21, not 18.
Rule 553-4 recognizes three experience routes: relevant bachelor plus one year; approved education and experience totaling four years; or four years of active related experience meeting the two-year and one-year subrequirements.
Georgia commercial rules do not create primary and secondary qualifying-agent classes; all qualifying agents for an entity are jointly and equally responsible.
The current rule requires notice within 45 days when the only qualifying agent leaves and gives the entity 120 days to employ a replacement and submit the application.
Last updated: August 2026
1.3 Eligibility, Experience Requirements & Qualifying Agents
Board Rule 553-4—not the residential Chapter 553-3—sets the commercial eligibility rules. An applicant must be at least 21 years old , possess good character, competency, ability, integrity, and financial responsibility, and establish one of three education-and-experience paths.
Three eligibility paths
Path Required showing
Relevant bachelor's degree Degree from an accredited four-year institution in engineering, architecture, construction management, building construction, or another field accepted by the Division, plus at least one year of proven general-contractor or substantially similar experience
Mixed education and experience An acceptable combination of accredited college-level academic credit and proven practical general-contractor or similar experience totaling at least four years
Experience route At least four years of active construction-related experience, including at least two years as or in the employment of a general contractor or accepted equivalent and at least one year in administration, marketing, accounting, estimating, drafting, engineering, supervision, project management, or a substantially similar function
Do not turn the third route into a rule requiring four years as a superintendent. The rule uses a four-year total plus nested two-year and one-year conditions. Likewise, the bachelor's path requires one year of proven experience; the degree does not eliminate experience entirely.
The applicant swears to the qualifications and supplies the proof directed by the application. The Division may conduct a background check. The application also identifies affiliated people and entities and includes insurance, tax, and identifying information required for the chosen application type.
Approval and examination attempts
The Division evaluates the application before the candidate tests. The PSI approval letter is valid for one year, during which both required examinations must be passed. Under Rule 553-4, an otherwise qualified applicant may be reexamined during that period after paying the reexamination fee. A person requesting a third or subsequent examination must wait at least one calendar year after the last examination and submit an application with the appropriate fees. Always follow the current approval letter for the candidate's authorized attempts.
What a qualifying agent is
A business organization applies through an individual qualifying agent affiliated by ownership or employment. The license is issued to the person and the named business organization. The qualifying agent's affidavit confirms final approval authority over construction work and business matters, including contracts, performance, and financial affairs. The entity must employ at least one currently licensed general contractor full-time who provides adequate supervision and is responsible for projects.
Georgia's current commercial rules do not establish a primary-versus-secondary qualifier hierarchy. An entity may have multiple qualifying agents, and Rule 553-4-.03 makes them jointly and equally responsible for supervision of all operations, field work at all sites, and financial matters. A qualifier cannot merely lend a license number while lacking authority or oversight.
Disassociation timeline
If a qualifying agent ceases affiliation, the agent must notify the Division within 45 days . If that person was the only qualifying agent, the business also must give written notice within 45 days and has 120 days from termination to employ another qualifying agent and submit the new application. Submitting the application preserves licensed status while the Division considers it, subject to the rule's denial consequence.
In limited circumstances the Division may grant a temporary nonrenewable license to a financially responsible officer or specified executive. That temporary authority only permits completion of contracts already in progress as defined by the rule; it is not a general extension to bid new work. Changes of qualifier operate prospectively, but a former qualifier remains responsible under the licensing chapter for conduct during that person's service.
To qualify another entity, the agent and new entity provide the application information, financial responsibility, and insurance for that organization. Each additional entity is separately evaluated; common ownership does not automatically transfer a license.
Evidence quality
Experience evidence should connect dates, employer, project type, role, duties, and the portion that satisfies each nested requirement. Overlapping projects do not automatically create extra calendar years. A title such as project manager is not conclusive without described functions. Keep affidavits, employer verification, project lists, education records, and explanations consistent across the application. Material misrepresentation can create a discipline problem even if the candidate later passes both tests.
Responsibility does not end at delegation
Superintendents, estimators, accountants, and subcontractors can perform daily tasks, but delegation does not erase the qualifying agent's final authority and licensing responsibility. The agent should receive reliable reports, visit and supervise as operations require, correct unsafe or noncompliant work, and control contracts and finances rather than appearing only on an application.