6.5 Excavation, Earthwork Volumes, Hauling & Compaction

Georgia General Contractor Exam

Track your progress as you read

Finished sections get a check mark.

1 Chapter 0: Exam Orientation, Blueprint & Open-Book Method

0.1 Official Exam Facts, Content Outlines & Approved References 0.2 Open-Book Navigation, Reference Indexing & Study Plan

2 Chapter 1: Georgia Contractor Licensing & Regulatory Law

1.1 Board Authority & Commercial General Contractor Tiers 1.2 Scope, Exemptions & Unlicensed Contracting 1.3 Eligibility, Experience Requirements & Qualifying Agents 1.4 Financial Responsibility, Net Worth, Surety Bonds & Insurance 1.5 License Renewal, No-CE Rule & Disciplinary Actions

3 Chapter 2: Georgia Construction & Lien Law

2.1 Georgia Mechanics & Materialmen's Liens 2.2 Project Notices: Notice of Commencement, Notice to Contractor & Preliminary Notice 2.3 Statutory Lien Waivers & Affidavits of Nonpayment 2.4 Georgia Prompt Pay Act & Right to Repair Act

4 Chapter 3: Business Organization, Financial Management & Taxes

3.1 Business Entity Selection & Joint Ventures 3.2 Georgia Entity Registration, Foreign Qualification & Trade Names 3.3 Construction Accounting, WIP & Financial Statements 3.4 Cash Flow, Working Capital & Construction Banking 3.5 Federal, Georgia & Payroll Tax Administration 3.6 Worker Classification, Wage-and-Hour & Prevailing Wage

5 Chapter 4: Construction Contracts, Bidding & Risk Management

4.1 Contract Pricing Models & Cost Risk 4.2 Project Delivery Methods & Responsibility 4.3 Essential Contract Clauses & Risk Allocation 4.4 Standard Documents: AIA, ConsensusDocs & EJCDC 4.5 Quantity Takeoff, Direct Cost & Markup 4.6 Bid Scope Review, Submission & Withdrawal 4.7 Surety Bonds, Insurance & Risk Management

6 Chapter 5: Project Management, Scheduling & Quality Control

5.1 Project Planning, WBS, Logic & Resources 5.2 CPM, Float, Updating & Schedule Compression 5.3 Project Administration, Submittals, RFIs & Records 5.4 Changes, Delays, Claims & Dispute Resolution 5.5 QA/QC, Special Inspections & Closeout

7 Chapter 6: Georgia Building Codes, Environmental Regulations & Site Work

6.1 Current Georgia Codes, Amendments, Permits & Inspections 6.2 Occupancy, Construction Type, Egress & Accessibility 6.3 GESA, NPDES, Buffers, BMPs & Certified Personnel 6.4 Survey Control, Layout, Clearing & Site Preparation 6.5 Excavation, Earthwork Volumes, Hauling & Compaction 6.6 Shallow Foundations, Slabs, Deep Systems & Drainage

8 Chapter 7: Concrete & Masonry Construction

7.1 Concrete Materials, Mix Design & Field Testing 7.2 Concrete Placement, Hot/Cold Weather, Curing & Defects 7.3 Formwork, Shores, Reshores & Removal 7.4 Reinforcing Steel, Splices & Post-Tensioning 7.5 Masonry Units, Mortar, Grout & Testing 7.6 Masonry Walls, Reinforcement, Flashing & Movement Joints

9 Chapter 8: Structural Steel, Metals & Framing Systems

8.1 Structural Steel Shapes, Framing & Erection Stability 8.2 Bolted Connections, Welding & Nondestructive Testing 8.3 Steel Joists, Deck & Cold-Formed Framing 8.4 Heavy Timber, Fire Performance & Mass Timber 8.5 Engineered Wood, I-Joists, Trusses & Connectors 8.6 Wood Framing, Sheathing, Bracing & Fastening

10 Chapter 9: Building Envelope, Thermal & Moisture Protection, Doors & Windows

9.1 Low-Slope Roofing, Insulation & Drainage 9.2 Steep-Slope Roofing, Sheet Metal & Flashing 9.3 Insulation, Air Barriers & Vapor Control 9.4 Commercial Doors, Frames, Hardware & Fire Assemblies 9.5 Windows, Storefronts & Curtain Walls 9.6 Insulating Glass, Safety Glazing & Water Control

11 Chapter 10: Finishes, Mechanical, Electrical & Plumbing Coordination

10.1 Gypsum Assemblies, Ceilings & Finish Coordination 10.2 Concrete Moisture, Flooring & Tile Assemblies 10.3 HVAC, Ductwork, Dampers & Mechanical Coordination 10.4 Plumbing, DWV, Venting & Backflow 10.5 Fire Sprinklers, Standpipes & Fire Department Connections 10.6 Electrical Distribution, Grounding & Emergency Systems

12 Chapter 11: Construction Safety & OSHA Standards (29 CFR Part 1926)

11.1 OSHA Authority, Inspections, Reporting & Multi-Employer Sites 11.2 Fall Protection, Clearance Planning & Scaffolds 11.3 Excavation, Protective Systems & Trench Safety 11.4 Hazard Communication, Silica, Temporary Power & PPE 11.5 Cranes, Rigging, Signal Persons & Power-Line Safety

6.5 Excavation, Earthwork Volumes, Hauling & Compaction

Key Takeaways Explain This Topic AI

Never compare BCY, LCY, and CCY without a stated conversion basis.

Proctor results establish laboratory moisture-density relationships for field comparison.

Compaction equipment should match cohesive or cohesionless soil behavior.

Last updated: August 2026

  • 6.5 Excavation, Earthwork Volumes, Hauling & Compaction
  • Earthwork Volumetric Calculations & Cut/Fill Balancing

Earthwork engineering focuses on cut and fill balancing —calculating earth volumes to ensure that soil excavated from high elevations (cuts) matches the soil volume needed for low elevations (fills), minimizing expensive off-site borrow import or waste export hauling.

1. Average End-Area Method

The Average End-Area method is the standard engineering formula used for calculating earthwork volumes for linear excavations —including utility trenches, roadways, pipeline ditches, and drainage swales:

V = ((A_1 + A_2) / 2) * (L / 27)

Where:

V = Volume of earth in Cubic Yards (cu yd) .

A_1 = Cross-sectional area of cut or fill at the first station (in square feet, sq ft).

A_2 = Cross-sectional area of cut or fill at the second station (in square feet, sq ft).

L = Horizontal distance between station 1 and station 2 (in feet).

27 = Conversion factor (27 cubic feet = 1 cubic yard).

2. Grid Method (Borrow Pit Method)

The Grid Method is used to calculate cut and fill volumes for broad, non-linear areas such as commercial building pads, parking lots, and site mass grading. The site plan is divided into uniform square grids (e.g., 50 ft x 50 ft, where Grid Area A = 2,500 sq ft):

V = A * ((sum h_1 + 2 sum h_2 + 3 sum h_3 + 4*sum h_4) / (4 * 27))

Where:

A = Area of a single grid square (in square feet).

h_1 = Cut or fill depths at corner stakes shared by only 1 grid square.

h_2 = Cut or fill depths at corner stakes shared by 2 adjoining grid squares.

h_3 = Cut or fill depths at corner stakes shared by 3 adjoining grid squares.

h_4 = Cut or fill depths at corner stakes shared by 4 adjoining grid squares.

Soil Volume Phase Transitions: BCY, LCY, CCY

Soil volume changes substantially during earthmoving operations due to variations in air void ratios. Contractors must account for three distinct volumetric states: ┌───────────────────────┐ Excavation (Swell) ┌───────────────────────┐

  • │ BANK CUBIC YARD │ ─────────────────────────────► │ LOOSE CUBIC YARD │
  • │ (BCY) │ │ (LCY) │
  • │ Natural In-Situ Soil │ ◄───────────────────────────── │ Excavated / Hauled │
  • └───────────┬───────────┘ Load Factor └───────────────────────┘
  • │
  • │ Compaction (Shrinkage)
  • ▼
  • ┌───────────────────────┐
  • │ COMPACTED CUBIC YARD │
  • │ (CCY) │
  • │ Engineered Fill Pad │
  • └───────────────────────┘
  • 1. Bank Cubic Yards (BCY)

Soil in its natural, undisturbed in-situ state prior to excavation. All engineering plans, cut depths, and baseline surveys are measured in BCY.

2. Loose Cubic Yards (LCY)

Soil after excavation and loading. When soil is disturbed, particle bonds break and air voids enter, causing the soil to expand or "swell":

LCY = BCY * (1 + S_w) Swell Factor (S_w) = (LCY - BCY) / BCY = (Density_bank / Density_loose) - 1 Load Factor = BCY / LCY = 1 / (1 + S_w)

3. Compacted Cubic Yards (CCY)

Soil after mechanical compaction in fill lifts. Compaction expels air voids and forces particles into dense packing, resulting in a volume smaller than the original bank volume:

  • CCY = BCY * (1 - S_h) Shrinkage Factor (S_h) = 1 - (CCY / BCY) = 1 - (Density_bank / Density_compacted)
  • Soil Volume Properties Table
  • Soil Description Typical Swell Factor ( S w S_w S w ​ ) Load Factor Typical Shrinkage Factor ( S h S_h S h ​ )
  • Clean Sand & Gravel 10% to 15% (0.10–0.15) 0.87–0.91 5% to 10% (0.05–0.10)
  • Common Earth / Loam 20% to 25% (0.20–0.25) 0.80–0.83 15% to 20% (0.15–0.20)
  • Dense Clay (Georgia Red Clay) 25% to 35% (0.25–0.35) 0.74–0.80 20% to 25% (0.20–0.25)
  • Blasted Solid Rock 50% to 70% (0.50–0.70) 0.59–0.67 -15% to -30% (Expands net)
  • Hauling & Fill Calculation Example

Problem: A commercial site requires placing and compacting 10,000 CCY of dense clay fill. The clay has a bank-to-compacted shrinkage factor of 20% ( S h = 0.20 S_h = 0.20 S h ​ = 0.20 ) and an excavation swell factor of 30% ( S w = 0.30 S_w = 0.30 S w ​ = 0.30 ) . How many Bank Cubic Yards must be excavated, and how many Loose Cubic Yards must be hauled by 18-LCY dump trucks?

  • Step 1: Calculate Bank Volume (BCY): BCY = CCY / (1 - S_h) = 10,000 / (1 - 0.20) = 10,000 / 0.80 = 12,500 BCY
  • Step 2: Calculate Loose Volume (LCY): LCY = BCY * (1 + S_w) = 12,500 * (1 + 0.30) = 16,250 LCY
  • Step 3: Calculate Truckloads: Truckloads = 16,250 LCY / (18 LCY/truck) = 902.78 -> 903 Truckloads
  • Geotechnical Soil Mechanics, Proctor Tests & Compaction Equipment
  • Cohesive vs. Cohesionless Soils

Cohesive Soils (Clays & Silts): Characterized by fine microscopic platelets bound by electrochemical forces. Possess high plasticity, slow drainage, and cohesive shear strength. Susceptible to volumetric shrinking when dried and swelling when saturated. (Prevalent across the Georgia Piedmont region as weathered crystalline "Georgia red clay").

Cohesionless Soils (Sands & Gravels): Composed of granular particles with no internal chemical cohesion. Shear strength derives entirely from internal friction between interlocking particles. Highly permeable with rapid drainage.

Proctor Moisture-Density Testing

To achieve structural stability, soil fill must be compacted to a specified percentage of its Maximum Dry Density (MDD) at its Optimum Moisture Content (OMC) , determined in geotechnical laboratories via Proctor tests:

  • Parameter Standard Proctor (ASTM D698 / AASHTO T99) Modified Proctor (ASTM D1557 / AASHTO T180)
  • Hammer Weight 5.5 lbs (2.5 kg) 10.0 lbs (4.54 kg)
  • Drop Height 12 inches (305 mm) 18 inches (457 mm)
  • Compacted Layers 3 layers in standard 4" or 6" mold 5 layers in standard mold
  • Blows per Layer 25 blows per layer 25 blows per layer
  • Compactive Energy 12,375 ft-lbf/cu ft 56,000 ft-lbf/cu ft (4.5x higher)

Primary Application Light residential grading, landscaping fills Heavy commercial building pads, foundations, highways, airfields PROCTOR MOISTURE-DENSITY CURVE

  • Dry Density (pcf)
  • ▲
  • │ Peak = Maximum Dry Density (MDD)
  • │ ┌─────┐
  • │ ┌─┘ └─┐
  • │ ┌─┘ └─┐
  • │ ┌─┘ └─┐
  • │ ┌─┘ └─┐
  • │ ┌─┘ └─┐
  • │ ┌─┘ └─┐
  • │ ┌─┘ └─┐
  • └────────┴─────────────┬───────────────────┴──► Moisture Content (%)
  • │
  • Optimum Moisture Content (OMC)

Optimum Moisture Content (OMC): The specific water content percentage at which soil particles are sufficiently lubricated to slip into their densest possible packing configuration under compaction. Placing soil significantly dry of OMC prevents full compaction due to friction; placing soil wet of OMC causes water to fill pore spaces, resulting in soil "pumping" and shearing failure.

Compaction Specification: Commercial building pads typically mandate compaction to 95% to 98% of Maximum Dry Density per ASTM D1557, placed in loose lifts of 6 to 8 inches within +/- 2% to +/- 3% of OMC.

Compaction Equipment Matrix

Compactor Type Primary Compactive Mechanism Recommended Soil Types & Applications

Sheepsfoot / Padfoot Roller Kneading action and high point pressure Cohesive soils (clays, silty clays). Tamping feet penetrate and compact from the bottom of the lift upward.

Smooth-Drum Vibratory Roller Dynamic vibration and static weight Cohesionless granular soils (sands, gravels, crushed stone base). Vibrations rearrange granular particles into dense interlocking.

Pneumatic-Tired (Rubber) Roller Static weight and uniform tire kneading Base courses, asphalt paving, and proof-rolling subgrades to detect soft spots.

Vibratory Plate Compactor High-frequency surface vibration Cohesionless sand and gravel in confined utility trenches and footing pads.

Rammer ("Jumping Jack") High-impact jumping blows Cohesive clay backfill in narrow foundation trenches, pipe backfill, and around manholes.

Dewatering Methods

Open Sump Pumping: Direct pumping from sumps excavated in low points; suitable for coarse gravels and low water inflows.

Wellpoint Systems: Series of small-diameter (1.5" to 2") slotted pipe points driven at 3- to 6-foot intervals around the excavation perimeter, connected to a common header pipe and vacuum pump; effective for lowering water tables up to 15 to 20 feet in sandy soils.

Deep Wells: Drilled holes containing submersible turbine pumps; used for deep excavations in permeable strata.

Loading diagram... Site Layout, Earthwork Volume Tracking & Geotechnical Compaction Process