Study guide
2.3 Bathtubs, Showers, Sinks & Food Prep Fixtures
Iowa Journeyperson Plumber Study Guide Exam
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Iowa Licensing, Exam Format, Code Adoption & UPC General Regulations
1.1 Iowa Licensing Tiers, PMSB Rules, Code Adoption, Permits & Inspections 1.2 UPC Chapter 3 General Regulations: Trenching, Protection of Piping & Iowa Burial Depths 1.3 Plumbing Mathematics, Pipe Sizing Formulas & Blueprint Reading 1.4 Hangers, Supports, Pipe Joints, and Material Compatibility 1.5 Exam Format, Approved References & Open-Book Lookup Strategy
2 Chapter 2: Plumbing Fixtures & Fixture Fittings (UPC Chapter 4)
2.1 Fixture Unit Values & Iowa Minimum Plumbing Fixture Requirements 2.2 Water Closets, Urinals, Bidets & Lavatories 2.3 Bathtubs, Showers, Sinks & Food Prep Fixtures 2.4 Plumbing Fixture Installation Standards & ADA Accessibility 2.5 Specialty Appliances, Floor Drains, Indirect Waste & Interceptors
3 Chapter 3: Sanitary Drainage & Building Sewers (UPC Chapter 7)
3.1 Sanitary Drainage System Components, Layout & Gravity Flow Principles 3.2 Drainage Fixture Unit (DFU) Values & Horizontal/Vertical Sizing 3.3 Building Sewers, Building Drains & Sewer Connection Standards 3.4 Drain Slopes, Velocities & Changes of Direction (UPC 706.0 and 708.0) 3.5 Cleanouts: Placement, Sizing, Clearances & Access Requirements 3.6 Sump Pumps, Sewage Ejectors & Backwater Valves 3.7 Drainage Materials, Joints, Prohibited Practices & DWV Testing 3.8 Sizing a Complete DWV System: Two Worked Walkthroughs
4 Chapter 4: Venting Systems (UPC Chapter 9)
4.1 Venting Fundamentals, Trap Seal Protection & the Iowa Trap Arm Table 4.2 Vent Sizing from UPC Table 703.2, Vent Stacks & Yoke Vents 4.3 Wet Venting Under UPC Section 908 and the Iowa Sizing Amendment 4.4 Venting Fixture Batteries: Common Vents, Relief Vents & Why Circuit Venting Is Not an Iowa Method 4.5 Air Admittance Valves, Combination Waste & Vent, and Island Venting 4.6 Vent Termination, Roof Penetrations & Flashings 4.7 Applying the Vent Rules: Worked Venting Walkthroughs 4.8 Diagnosing Venting Failures: Symptom-to-Cause Troubleshooting
5 Chapter 5: Traps, Interceptors & Indirect Waste (UPC Chapters 8 and 10)
5.1 Trap Design, Seals, Prohibited Traps & Trap Primers 5.2 Indirect & Special Waste Receptors and Air Gaps 5.3 Grease Interceptors & Trap Sizing (Hydromechanical & Gravity) 5.4 Oil, Sand, Flammable Liquid & Chemical Interceptors
6 Chapter 6: Water Supply & Distribution (UPC Chapter 6)
6.1 Water Service Piping, Main Sizing & Meter Installation 6.2 Water Supply Fixture Units (WSFU) & Pipe Sizing Calculations 6.3 Water Pressure Regulators, Pressure Relief & Thermal Expansion 6.4 Backflow Prevention: Cross-Connection Control & Device Selection 6.5 Potable Water Pipe Materials, Valves & Disinfection
7 Chapter 7: Water Heaters (UPC Chapter 5)
7.1 Water Heater Types, Sizing, Recovery Rate & First-Hour Rating 7.2 Water Heater Safety: T&P Relief Valves, Drain Pans, Combustion Air & Anti-Scald Controls 7.3 Water Heater Venting: Appliance Categories, Vent Connectors, Chimneys & Terminations 7.4 Water Heater Location, Clearances, Supports, Replacement & Iowa Amendments
8 Chapter 8: Storm Drainage (UPC Chapter 11)
8.1 Storm Drainage Scope, Materials, Traps & Prohibited Connections 8.2 Sizing Roof Drains, Leaders & Vertical Rainwater Piping (UPC Table 1103.1) 8.3 Sizing Horizontal Storm Drains, Storm Sewers & Gutters (UPC Tables 1103.2 and 1103.3) 8.4 Side Walls Draining Onto a Roof, Secondary Roof Drainage & Controlled-Flow Roofs 8.5 Subsoil Drains, Areaway Drains, Storm Sumps & Building Storm Sewers
9 Chapter 9: Fuel Gas Piping & Appliance Venting (UPC Chapter 12)
7.1 Iowa Fuel Gas Authority (UPC Chapter 12), Gas Properties, System Types & Regulators 7.2 Gas Pipe Sizing Calculations, Longest Length & Branch Method 7.3 Gas Pipe Materials, Joining, CSST Rules Under the Iowa Amendments, Outlets & Valves 7.4 Fuel Gas Appliance Installation, Clearances & Combustion Air 7.5 Fuel Gas Venting Systems, Chimneys & Safety Testing
2.3 Bathtubs, Showers, Sinks & Food Prep Fixtures
Key Takeaways Explain This Topic AI
Bathtub and shower valves must feature ASSE 1016 pressure-balancing, thermostatic, or combination mixing controls limiting maximum water output to 120°F (49°C).
Shower receptors require a minimum finished floor area of 1,024 square inches, encompassing a 30-inch diameter circle, with curbs standing 2 to 9 inches high.
Field-fabricated shower pans must undergo a hydrostatic water test filled to the top of the threshold (minimum 2 inches) for at least 15 minutes without leakage.
Commercial food preparation sinks must discharge indirectly into an approved receptor via a physical air gap to prevent sanitary sewage backflow into food prep areas.
Last updated: August 2026
2.3 Bathtubs, Showers, Sinks & Food Prep Fixtures
Bathing, showering, and culinary fixtures represent major water discharge points in both residential and commercial buildings. Because these fixtures directly involve human bodily immersion or food handling, code requirements strictly address anti-scald temperature control, watertight shower pan liners, structural access, and cross-connection prevention via indirect waste systems.
- Bathtubs & Combination Tub/Showers
- Anti-Scald Protection (ASSE 1016 Compliance)
Water temperature control in bathtubs and combination tub/showers is governed by UPC Section 408.3 . All tub/shower valves must be equipped with an anti-scald control valve conforming to ASSE 1016 / ASME A112.18.1 / CSA B125.1 .
Approved valve types include:
Pressure-Balancing Valves: Senses changes in incoming hot and cold water supply pressures. If cold water pressure drops suddenly (e.g., someone flushes a nearby toilet), a sliding internal spool shifts immediately to reduce hot water flow, preventing thermal shock or scalding.
Thermostatic Mixing Valves: Senses water output temperature using an expanding wax element or bimetallic strip, modulating hot and cold water volume to maintain the set temperature regardless of supply line fluctuations.
Combination Pressure-Balance / Thermostatic Valves: Combines both pressure-sensing spools and temperature-sensing elements.
Maximum Temperature Setting: Anti-scald mixing valves must be equipped with a high-limit rotational stop, field-adjusted at the time of installation to cap maximum output temperature at 120°F (49°C) .
Waste Outlets & Whirlpool Bathtubs
Waste Sizing: Bathtubs must have a waste outlet and P-trap with a minimum diameter of 1-1/2 inches (40 mm) .
Whirlpool / Jetted Tubs (UPC 409.0): Circulation pumps on whirlpool bathtubs must be self-draining to prevent stagnant water retention in internal piping. An access panel measuring at least 12 x 12 inches (305 x 305 mm) must be provided to service the pump and motor. If the pump is located more than 2 feet from the access opening, the opening size must be increased to at least 18 x 18 inches (457 x 457 mm) .
- Showers & Shower Pan Construction
- Compartment & Curb Dimensions
Minimum Interior Area: Finished shower compartments must have a minimum interior area of 1,024 square inches (0.66 m²) .
Minimum Clearance: The compartment must be capable of encompassing a 30-inch (762 mm) diameter circle measured from floor level up to a height of 70 inches above the drain.
Curb / Threshold Height: The finished curb or threshold height must be a minimum of 2 inches (51 mm) and a maximum of 9 inches (229 mm) measured from the top of the drain outlet. +---------------------------------------------------+
- | SHOWER ENCLOSURE |
- | |
- | /-------------\ |
- | / \ |
- | | 30-Inch (D) | |
- | | Circle | |
- | \ / |
- | \-------------/ |
- | |
- +-----------------------+---------------------------+
- | <-- Threshold / Curb
- v (Min. 2" to Max. 9" High)
- Field-Fabricated Shower Pan Materials & Slope
Where custom tiled shower pans are constructed, subfloor waterproofing is critical. The subfloor below the pan liner must slope toward the weep holes of the subdrain at a pitch of 1/4 inch per foot (20.8 mm/m) .
Approved Pan Lining Materials (UPC 408.7):
Sheet Lead: Minimum weight of 4 lbs per sq ft (1/16" thick), coated with asphalt paint.
Sheet Copper: Minimum weight of 12 oz per sq ft .
PVC Flexible Sheet Liner: Minimum thickness of 40 mil (0.040 inch / 1.02 mm) conforming to ASTM D4551.
CPE Flexible Sheet Liner: Minimum thickness of 40 mil conforming to ASTM D4068.
Hot-Mop Asphalt: Minimum 3 plies of 15-lb felt saturated with 4 continuous coats of hot asphalt.
Subdrain & Hydrostatic Testing
Shower pans feature a two-piece subdrain equipped with clamping rings and weep holes . Weep holes permit moisture migrating through the tile mortar bed to enter the drain pipe. Weep holes must be protected with gravel or plastic weep-hole guards to prevent mortar blockage.
Hydrostatic Water Test: Before tile or mortar setting bed installation, the shower liner MUST be tested (UPC 408.7.5):
Insert an expandable test plug into the subdrain below the weep holes.
Fill the shower receptor with water to the top of the threshold or curb (minimum 2 inches deep ).
Maintain water level for at least 15 minutes with zero measurable leakage or drop in water level .
- Sinks & Food Preparation Fixtures
- Domestic Sinks
Waste Sizing: Domestic kitchen sinks carry a 2 DFU rating, requiring a minimum 1-1/2 inch tailpiece and P-trap.
Dishwasher Connection — read the Iowa amendment: Rule 481—425.4(6)"a" rewrites UPC Section 807.3 to read that no domestic dishwashing machine may be directly connected to a drainage system or food waste disposer "without the use of an approved dishwasher air gap fitting on the discharge side of the dishwashing machine, or by looping the discharge line of the dishwasher as high as possible near the flood level of the kitchen sink where the waste disposer is connected." In other words, Iowa accepts the high loop as an alternative to a countertop air gap fitting. Where an air gap fitting is used, it must be installed with its flood level (FL) marking at or above the flood level of the sink or drainboard, whichever is higher.
Commercial Food Preparation Sinks (Strict Indirect Waste Rule)
Commercial sinks used for washing, soaking, preparing, or processing food, vegetables, pots, or culinary ice CANNOT be directly connected to the sanitary drainage system (UPC Section 801.1).
Hazard: Direct connection creates a severe health risk—if the sewer line backs up, raw sewage could flood directly into sinks containing food products.
Mandatory Air Gap: Food preparation sinks must discharge indirectly into an approved indirect waste receptor (such as a floor sink or mop basin) through a physical Air Gap .
Air Gap Dimension: The vertical distance through open air between the waste pipe outlet and the receptor flood level rim must be at least 2 times the diameter of the drain pipe, and never less than 1 inch (25 mm) . Food Prep Sink Drain Pipe (1-1/2" Dia)
- |
- | <-- Physical Air Gap
- v (Min. 2x Pipe Dia = 3 Inches)
- ============================= <-- Receptor Flood Rim
- | Floor Sink Receptor |
- +---------------------------+
- |
- v
- To Sanitary Drain System