11.1 Mechanical (IMC) and Fuel Gas (IFGC) Plan Review
ICC Certified Building Official CBO
Track your progress as you read
Finished sections get a check mark.
1 Introduction
About the ICC CBO Exam How to Use This Guide
2 Chapter 1: Legislative and Alternative Methods
1.1 Code Adoption and Local Amendments 1.2 Board of Appeals and Alternative Materials/Methods
3 Chapter 2: Code Enforcement and Due Process
2.1 Permits and Construction Documents 2.2 Inspection Process and Certificate of Occupancy 2.3 Notices, Violations, and Stop Work Orders 2.4 Right of Entry and Administrative Warrants 2.5 Due Process and Equal Protection 2.6 Hazard Abatement and Emergency Measures 2.7 Tort Liability and Sovereign Immunity 2.8 Code Enforcement Prosecution and Civil Remedies
4 Chapter 3: Human Resources in Code Administration
3.1 Anti-Discrimination Laws in Public Employment (ADA, Title VII) 3.2 Wage, Hour, and Safety Laws (FLSA, OSHA) 3.3 Personnel Discipline, Performance, and Dismissal 3.4 Labor Relations, Grievances, and Due Process
5 Chapter 4: Reports and Public Records
4.1 Records Management and Document Retention 4.2 Public Records Disclosure and Freedom of Information Laws
6 Chapter 5: Customer Service and Public Relations
5.1 Customer Service Principles in Public Administration 5.2 Public Relations, Media, and Stakeholder Communication 5.3 Interagency Cooperation and Coordination 5.4 Conflict De-escalation and Dispute Resolution 5.5 Feedback Strategy and Continuous Service Improvement
7 Chapter 6: Personnel Administration
6.1 Job Descriptions and Personnel Needs Assessment 6.2 Recruitment, Selection, and Onboarding Processes 6.3 Staff Training, Professional Goals, and Certification 6.4 Performance Appraisals and Supervision Standards
8 Chapter 7: Financial Management
7.1 Operating and Capital Budget Development 7.2 Fee Structures, Valuation, and Revenue Generation 7.3 Financial Controls, Audits, and Cost Recovery
9 Chapter 8: Department Records and Information Systems
8.1 Permitting and Code Enforcement Reporting Systems 8.2 Electronic Document Review and Workflow Integration 8.3 Information Security, Data Privacy, and Disaster Recovery
10 Chapter 9: Architectural Plan Review
9.1 Use and Occupancy Classifications (IBC Chapter 3) 9.2 Construction Types and Height/Area Limitations (IBC Chapters 5 & 6) 9.3 Fire and Smoke Protection Features (IBC Chapters 7 & 8) 9.4 Fire Protection Systems (IBC Chapter 9) 9.5 Means of Egress and Occupant Load (IBC Chapter 10)
11 Chapter 10: Structural Plan Review
10.1 Design Loads and Structural Criteria (IBC Chapter 16) 10.2 Materials Standards and Foundations (IBC Chapters 18-23)
12 Chapter 11: Building Systems and Energy Code Plan Review
11.1 Mechanical (IMC) and Fuel Gas (IFGC) Plan Review 11.2 Plumbing Systems (IPC) and Backflow Protection 11.3 Electrical (NEC/NFPA 70) and Energy (IECC) Code Plan Review
13 Chapter 12: Field Inspection and Construction Compliance
12.1 Accessibility Standards and ANSI A117.1 Compliance 12.2 Soil Conditions, Excavation, and Site Inspections 12.3 Footing and Foundation Inspections 12.4 Concrete, Masonry, Steel, and Wood Structural Inspections 12.5 Rough-in MEP Inspections 12.6 Special Inspections and Quality Assurance (IBC Chapter 17) 12.7 Existing Buildings, Alterations (IEBC), and Final Inspections
11.1 Mechanical (IMC) and Fuel Gas (IFGC) Plan Review
Key Takeaways Explain This Topic AI
Table 403.3.1.1 dictates mechanical ventilation rates based on occupancy and square footage.
Type I hoods are required for grease/smoke-producing commercial cooking, whereas Type II hoods handle steam/odor.
Combustion air requires 50 cubic feet per 1,000 Btu/h for fuel gas appliances, otherwise outdoor air openings must be provided.
Category I vent systems are non-condensing, negative-pressure, while Category IV are condensing, positive-pressure.
Fuel gas piping must undergo pressure testing at a minimum of 1.5 times working pressure, and not less than 3 psig.
Last updated: July 2026
11.1 Mechanical (IMC) and Fuel Gas (IFGC) Plan Review
Key Concept: Mechanical and fuel gas plan review ensures buildings maintain safe occupant environments, protect fire-resistance-rated assemblies, and provide adequate combustion air to prevent carbon monoxide poisoning and backdrafting.
The plan review process for mechanical systems relies on the International Mechanical Code (IMC) and the International Fuel Gas Code (IFGC). These codes interface with the International Building Code (IBC) to regulate mechanical ventilation, kitchen exhaust systems, duct design, smoke dampers, and fuel gas piping systems.
Mechanical Ventilation: Natural vs. Mechanical
Plan reviewers must confirm that all occupied spaces are provided with ventilation in accordance with IMC Chapter 4.
Natural Ventilation
Under IMC Section 402, natural ventilation requires that the openable area to the outdoors be at least 4 percent of the floor area being ventilated. The outdoor air must come directly from openings to the outdoors, which can include windows, doors, louvers, or skylights.
Mechanical Ventilation
For mechanical ventilation systems, the plan reviewer must audit design calculations against IMC Table 403.3.1.1. The design must account for both the occupancy-based ventilation rate (Rp in CFM per person) and the area-based ventilation rate (Ra in CFM per square foot). The total outdoor airflow rate (Vot) is calculated as: Vot = (Rp * Pz) + (Ra * Az), where Pz is the zone population and Az is the zone floor area.
Outdoor air intakes must be strategically located to prevent the recirculation of contaminants. Under IMC Section 401.4, outdoor air intakes must be positioned at least 10 feet away from hazardous or noxious sources such as plumbing vents, chimneys, mechanical exhaust outlets, streets, alleys, and loading docks. In addition, intakes must be placed at least 3 feet below or 10 feet away from any plumbing vent that terminates above the intake level.
Commercial Kitchen Exhaust Systems
Commercial kitchen hoods represent a high-risk mechanical system due to grease accumulation and fire hazards. Under IMC Chapter 5, the plan reviewer must identify the type of hood required based on the cooking appliances:
Type I Hoods : Required where cooking appliances produce grease or smoke. This includes deep fat fryers, griddles, charbroilers, and ovens cooking meats. Type I systems require commercial grease filters, liquid-tight welded duct construction (minimum 16-gauge steel or 18-gauge stainless steel), structural shafts for vertical duct enclosures, and automatic fire suppression systems complying with UL 300.
Type II Hoods : Required where cooking appliances produce steam, heat, vapor, or odors without producing grease. Examples include dishwashers, steam tables, and light-duty ovens. They do not require fire suppression or heavy-gauge welded ducts.
Makeup Air Integration
A critical plan review item is makeup air. Under IMC Section 508, makeup air systems must be interlocked with the exhaust system to run simultaneously. The makeup air flow rate must be approximately equal to the exhaust air flow rate (within 10 percent). Neglecting makeup air creates negative pressure, causing backdrafting of fuel-fired appliances and preventing egress doors from opening properly.
Duct Construction, Dampers, and Detectors
Duct systems (IMC Chapter 6) must be reviewed for materials, pressure classification, and support spacing. Duct smoke detectors are a vital life-safety integration:
Equipment Shutdown : IMC Section 606 requires duct smoke detectors in the supply air systems of mechanical units with a design capacity exceeding 2,000 CFM. If a return air system has a design capacity exceeding 15,000 CFM and serves more than one story, detectors must be installed at each story's connection to the return air riser. Upon detection of smoke, the controls must automatically shut down the associated HVAC equipment.
Fire and Smoke Dampers : Required where ducts penetrate fire-resistance-rated assemblies (such as fire walls, fire barriers, and shaft enclosures). The plan reviewer must verify that dampers are rated in accordance with UL 555 (fire dampers) and UL 555S (smoke dampers), and that access panels are provided for inspection and testing.
Fuel Gas Piping and Pressure Testing
The International Fuel Gas Code (IFGC) governs the design and installation of fuel gas piping systems. Plan reviewers must verify piping materials, sizing calculations, and pressure-testing protocols:
Materials : Acceptable piping includes schedule 40 black steel, copper tubing (if the gas is non-corrosive), and Corrugated Stainless Steel Tubing (CSST). CSST systems require electrical bonding to the electrical service grounding electrode system to prevent damage from lightning strikes. Plastic piping is permitted only for underground installations outdoors.
Sizing : Piping sizing must be verified using the longest length method or branch length method, ensuring that pressure drop is kept within allowable limits (typically 0.5 inches water column for low-pressure systems) to deliver adequate fuel to appliances.
Pressure Testing : Under IFGC Section 406, fuel gas piping must be pressure-tested before being placed into service. The minimum test pressure must be not less than 1.5 times the maximum working pressure, but under no circumstances less than 3 psig. The test duration must be at least 10 minutes for residential systems and longer for commercial installations.
Combustion Air Requirements
Fuel gas appliances require oxygen to support complete combustion. IFGC Chapter 3 establishes rules to prevent hazardous incomplete combustion and carbon monoxide production:
Confined vs. Unconfined Space : A space is considered unconfined (roomy enough to provide combustion air from normal infiltration) if its volume is at least 50 cubic feet per 1,000 Btu/h of the aggregate input rating of all appliances. If the volume is less than this threshold, it is confined, and additional combustion air must be brought into the space.
Indoor Combustion Air : If drawing from adjacent indoor spaces, two permanent openings are required, each having a free area of not less than 1 square inch per 1,000 Btu/h.
Outdoor Combustion Air : If drawing from outdoors, the plan reviewer must verify the sizing of openings. The two-permanent-openings method requires one high opening and one low opening. If venting directly to the outdoors, each opening must have a free area of 1 square inch per 4,000 Btu/h. The one-permanent-opening method requires a single opening with a free area of 1 square inch per 3,000 Btu/h, located within the upper 12 inches of the enclosure.
Venting Systems and Appliance Categories
Venting systems must safely exhaust combustion products to the outdoors. Under IFGC Chapter 5, gas appliances are classified into four categories based on vent operating temperature and pressure:
Category I : Operates with a non-positive vent static pressure and a vent gas temperature high enough to avoid condensation in the vent. These appliances rely on natural draft and use Type B or Type L double-wall vents.
Category II : Operates with a non-positive vent static pressure and a vent gas temperature low enough to cause condensation.
Category III : Operates with a positive vent static pressure and a vent gas temperature high enough to avoid condensation. These require airtight metallic vents.
Category IV : Operates with a positive vent static pressure and a vent gas temperature low enough to cause condensation. These are high-efficiency condensing appliances and typically vent through PVC or CPVC piping.
Mechanical Equipment Access and Clearances
Plan reviewers must ensure that all mechanical equipment is designed with safe and code-compliant access for maintenance and repair. Under IMC Section 306, appliances must be accessible without requiring the removal of permanent construction. Equipment installed in attics must have an access opening of not less than 22 inches by 30 inches, and a continuous passageway at least 22 inches wide and 30 inches high. Appliances installed on roofs must have a level working platform (not less than 30 inches by 30 inches) and must be located no closer than 15 feet from the edge of the roof, unless a standard 42-inch guardrail is installed to prevent falls.