Study guide

3.1 R401.2 Application: Prescriptive, Performance, ERI & Tropical Options

ICC Residential Energy Inspector/Plans Examiner Exam 79

Track your progress as you read

Finished sections get a check mark.

1 Exam Overview, Scope & Construction Documents

1.1 Current Exam 79 Facts, References & Open-Book Rules 1.2 Residential Scope, Mixed Occupancy & When the IECC Applies (R101, R102) 1.3 Construction Documents & Plan-Review Adequacy (R103)

2 Climate Zones, Materials Identification & Inspections

2.1 Climate Zones, Moisture Regimes & County Lookup (R301) 2.2 Design Conditions, Insulation Marks & Fenestration Labels (R302, R303) 2.3 Inspection Sequence & the Permanent Energy Certificate (R105, R401.3)

3 Compliance Paths, UA Tradeoff & Additional Efficiency

3.1 R401.2 Application: Prescriptive, Performance, ERI & Tropical Options 3.2 Additional Energy Efficiency Packages (R401.2.5, R408) 3.3 Total UA Alternative & Fenestration Tradeoff Caps (R402.1.5, R402.5)

4 Building Thermal Envelope Criteria

4.1 Building Thermal Envelope, Conditioned Space & Low-Energy Exceptions (R402.1) 4.2 Insulation Minimum R-Values — Table R402.1.3 4.3 Maximum Assembly U-Factors — Table R402.1.2 & R-Value Computation (R402.1.2, R402.1.4)

5 Specific Insulation Assemblies

5.1 Ceilings With and Without Attics, Eave Baffles & Access Hatches (R402.2.1–R402.2.4) 5.2 Wood-Frame, Mass & Steel-Frame Walls (R402.2.5–R402.2.6) 5.3 Floors, Basement Walls & Slab-on-Grade Insulation (R402.2.7–R402.2.9) 5.4 Crawl Spaces, Masonry Veneer, Sunrooms & Heated Garages (R402.2.10–R402.2.12)

6 Fenestration, Glazing & Doors

6.1 Fenestration U-Factor, SHGC & NFRC Labels (R402.3, R303.1.3) 6.2 Area-Weighted Averages, Dynamic Glazing & Exemptions (R402.3.1–R402.3.4) 6.3 Fenestration Air Leakage, Opaque Doors & Replacement Units (R402.4.3, R503.1.1.1)

7 Air Leakage Testing, Air Barrier & Moisture

7.1 Table R402.4.1.1: Ceilings, Walls, Rim Joists & Floors 7.2 Table R402.4.1.1: Openings, Penetrations, Tubs, Garages & Boxes 7.3 Blower-Door Testing, ACH50 Limits & Dwelling-Unit Alternatives (R402.4.1.2–R402.4.1.3) 7.4 Fireplaces, Recessed Luminaires, Air-Sealed Boxes, Combustion Rooms & Vapor Retarders (R402.4.2–R402.4.6, R402.1.1)

8 HVAC Controls, Sizing & Ventilation

8.1 Thermostats, Heat-Pump Supplementary Heat & Boiler Reset (R403.1, R403.2) 8.2 Equipment Sizing, Efficiency Ratings & Multi-Family Systems (R403.7, R403.8) 8.3 Mechanical Ventilation, HRV/ERV, Fan Efficacy & Airflow Testing (R403.6)

9 Duct Insulation, Sealing & Leakage Testing

9.1 Duct Insulation, Location & Buried Ducts (R403.3.1–R403.3.3) 9.2 Duct Sealing, Air Handlers & Framing-Cavity Ban (R403.3.4, R403.3.7) 9.3 Duct Testing Protocols & Leakage Limits (R403.3.5–R403.3.6)

10 Service Water Heating, Piping & Lighting

10.1 Service Water Heating Equipment, Circulation & Heat Trace (R403.5, R403.5.1) 10.2 Hot-Water Pipe Insulation, Mechanical Piping & Drain-Water Heat Recovery (R403.4, R403.5.2–R403.5.3) 10.3 High-Efficacy Lighting & Lighting Controls (R404)

11 Simulated Performance, ERI & Tropical Option

11.1 Simulated Performance Alternative (R405) 11.2 Energy Rating Index Alternative (R406) 11.3 Tropical Climate Region Option (R407)

12 Additions, Alterations, Repairs & Change of Occupancy

12.1 Additions & Change in Space Conditioning (R501, R502) 12.2 Alterations, Replacement Fenestration & Repairs (R503, R504) 12.3 Change of Occupancy, Historic Buildings & Maintenance (R505, R501.3, R501.6)

3.1 R401.2 Application: Prescriptive, Performance, ERI & Tropical Options

Key Takeaways Explain This Topic AI

Residential buildings shall comply with R401.2.5 additional energy efficiency and either R401.2.1, R401.2.2, R401.2.3, or R401.2.4.

Prescriptive R401.2.1 requires Sections R401 through R404; performance R401.2.2 requires R405; ERI R401.2.3 requires R406; tropical R401.2.4 requires R407.

R401.2.5 sits on every primary path: one R408.2 package (prescriptive), an R408.2 package omitted from the R405 proposed design or proposed annual energy cost at or below 95 percent of the standard reference design (performance), or an ERI at least 5 percent less than Table R406.5 (ERI).

The compliance path and the additional-efficiency option selected shall be identified on the R401.3 certificate and should be declared on the construction documents before envelope numbers are reviewed.

The four primary options are alternatives, not a buffet; a UA worksheet, an R405 report, and an ERI score are not interchangeable evidence.

Last updated: September 2026

3.1 R401.2 Application: Prescriptive, Performance, ERI & Tropical Options

Quick Answer: Under the 2021 IECC, residential buildings shall comply with Section R401.2.5 and either Section R401.2.1 (prescriptive, R401 through R404), R401.2.2 (total building performance, R405), R401.2.3 (Energy Rating Index, R406), or R401.2.4 (tropical climate region, R407). The additional-efficiency option selected is identified on the R401.3 certificate.

Section R401.2 is the application rule that tells a plans examiner which residential energy path is on the table. Independent ExamFinch material for ICC Exam 79 treats it as a documentation decision, not a marketing slogan. Until the drawings name a path, Table R402.1.3 R-values, an R405 printout, and an ERI score are competing attachments rather than a compliance showing.

The two-part 2021 rule

The charging sentence is short and easy to misread. Residential buildings shall comply with Section R401.2.5 and either Sections R401.2.1, R401.2.2, R401.2.3, or R401.2.4.

Read the and first. Additional energy efficiency in R401.2.5 applies to every approach. A complete prescriptive envelope that never installs an R408.2 package does not comply. An R405 run that neither installs an R408.2 package without including those measures in the proposed design nor shows proposed annual energy cost less than or equal to 95 percent of the standard reference design does not comply. An ERI that merely equals Table R406.5, instead of coming in at least 5 percent less than that target, does not comply.

Read the either second. The four primary options are alternatives. The code does not invite a designer to satisfy walls from Table R402.1.3, ducts from an R405 model, and the roof from an ERI on the same house. Mandatory provisions that travel with a chosen path (testing, lighting, R405 envelope backstops, and similar) are still required by that path. They are not a license to mix primary options.

This guide teaches 2021 IECC residential provisions (first printing) as used on Exam 79. Confirm the code year on the live ICC Exam Catalog. Do not treat New Jersey energy-subcode amendments, or any other state overlay, as the national 2021 text.

Four primary options

Path (R401.2) Pointer Building must satisfy Energy packet usually contains

Prescriptive Compliance Option R401.2.1 Sections R401 through R404 R-value or U-factor tables, NFRC fenestration data, air-barrier notes, blower-door and duct-leakage tests, R404 lighting, plus one R408.2 package

Total Building Performance Option R401.2.2 Section R405 Approved performance report comparing proposed annual energy cost to the standard reference design, plus the R401.2.5 method (R408 package omitted from the proposed design, or cost ≤ 95% of reference)

Energy Rating Index Option R401.2.3 Section R406 ERI report against Table R406.5, with the index at least 5 percent less than the table target, listed with and without on-site generation on the certificate

Tropical Climate Region Option R401.2.4 Section R407 Demonstration that the tropical climate region applies, plus the R407 compactness, shading, ventilation, and equipment provisions

Prescriptive work remains the stack most Exam 79 items will assume, because Building Envelope is 46 percent of the outline and the component tables live in R402. Performance and ERI do not erase those tables from the codebook; they change how envelope compliance is demonstrated. Tropical R407 is a real fourth option, not a warm-climate nickname for R405.

What each path does not authorize

Prescriptive (R401.2.1) covers R401 through R404. That includes the certificate, envelope, mechanical systems, service water heating, and lighting. Hitting the wall R-value does not excuse R404 high-efficacy lamps or duct testing. Inside R402, the applicant may use the R-value alternative, the U-factor table, or the Total UA alternative, but those are envelope methods within the prescriptive option, not a switch to R405 or R406.

Performance (R401.2.2) requires R405, not a homemade spreadsheet. The standard reference design is defined by the code. R401.2.5 then adds either an R408.2 package kept out of the proposed design, or a 95 percent annual-energy-cost cap. Modeling the efficient furnace inside R405 and counting that same furnace as the R408 HVAC package is the performance-path trap: if the R408 package is the R401.2.5 method, those measures are not included in the proposed design under R405.

ERI (R401.2.3) requires R406. Table R406.5 is the 2021 target (Climate Zone 5 is 55 ). R401.2.5 then requires the rated index to be at least 5 percent less than that target (55 × 0.95 = 52.25). Meeting 55 on the nose is not enough on the 2021 ERI path. Chapter 11 works the rating mechanics; this section only plants the application overlay.

Tropical (R401.2.4) requires R407 and only where the tropical climate region applies. It is not available to a Climate Zone 2 inland subdivision because a brochure says island living.

Plans-examiner documentation

Exam 79 scores envelope compliance documentation and path identification. On review, require all four of the following:

A declared path on the construction documents. Section R103 energy data should state prescriptive, total building performance, ERI, or tropical. Mixed attachments without a declared path are not a path.

An R401.2.5 statement. Prescriptive: which one R408.2 package. Performance: package installed and excluded from the proposed design, or the 95 percent cost demonstration. ERI: Table R406.5 target and the 5 percent reduction.

Certificate language that will actually be posted. R401.3 requires a permanent certificate in the furnace space, a utility room, or another approved interior location. It lists predominant insulation R-values, fenestration U-factor and SHGC (largest-area value and area-weighted average when more than one value exists), duct and envelope leakage test results, heating, cooling, and water-heating types, sizes, and efficiencies, photovoltaic array data if present, ERI scores with and without on-site generation when R406 is used, the code edition, and the compliance path used. R401.2.5 independently requires the additional-efficiency option selected to be identified on that same certificate. A furnace-closet card that lists R-values but not the path is incomplete.

Reports that match the path. A Total UA worksheet supports R402.1.5 inside the prescriptive envelope. It is not an R405 compliance report. An ERI certificate is not a substitute for R405. Reject the wrong report stapled to the right form.

Field inspection

The inspector does not re-run the rating software. The inspector confirms that installed assemblies, labels, equipment nameplates, duct locations, and test reports match the approved path. If the permit says prescriptive plus R408.2.4 ducts and air handlers entirely within the building thermal envelope, and the air handler is in an unconditioned attic, the package fails even if the cavity R-values look generous.

Scenario. A Climate Zone 5 two-story permit lists Table R402.1.3 values, a blower-door target, and LED lighting, but never names R408. Under R401.2 the file is incomplete: R401.2.5 is missing. Do not invent a package in the field. Require a revision that names one R408.2 option, or that switches the project to performance or ERI with the matching R401.2.5 method.

Scenario. Drawings stamp ERI, but the only energy sheet is a UA worksheet. UA is the R402.1.5 alternative to Table R402.1.2, not R406. Ask for the ERI report and the 5 percent reduction against Table R406.5, or have the applicant redeclare the prescriptive path.

Keep path talk independent: this is ExamFinch teaching of 2021 IECC residential provisions for Exam 79 study, not a claim of ICC endorsement.