4.3 Earthwork Quantities, Mass Haul Concepts, and Material Balance
ICC Soils Special Inspector EC
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Special Inspection Administration & Quality Control Framework
1.1 Special Inspection Roles, Duties, and Boundaries of Authority 1.2 Construction Documents, Soils Reports, and Statement of Special Inspections 1.3 Inspection Records, Discrepancy Notification, and Escalation
2 Chapter 2: Soil Classification Systems & Field Identification
2.1 Representative Soil Sampling and Field Quality Protocols 2.2 Visual-Manual Soil Classification (ASTM D2488) 2.3 Unified Soil Classification System (USCS) and Dual Symbols (ASTM D2487)
3 Chapter 3: Laboratory Soil Mechanics & Compaction Standards
3.1 Particle Size Analysis and Gradation Curves (ASTM D422 / D6913) 3.2 Atterberg Limits and Soil Plasticity (ASTM D4318) 3.3 Laboratory Compaction Standards: Standard vs. Modified Proctor (ASTM D698, D1557)
4 Chapter 4: Grading Plans, Contours, and Earthwork Quantities
4.1 Topographic Contours, Spot Elevations, and Slope Calculations 4.2 Cut and Fill Staking, Daylight Lines, and Benching Slopes 4.3 Earthwork Quantities, Mass Haul Concepts, and Material Balance
5 Chapter 5: Site Preparation, Clearing, and Subgrade Evaluation
5.1 Site Clearing, Grubbing, Stripping, and Unsuitable Soils 5.2 Subgrade Scarification, Moisture Conditioning, and Compaction 5.3 Proofrolling Procedures, Evaluation, and Subgrade Remediation
6 Chapter 6: Excavations, Foundation Bearing, and Ground Improvement
6.1 Overexcavation, Undercuts, and Differing Subsurface Conditions 6.2 Shallow Footing Excavation and Soil Bearing Verification 6.3 Deep Foundations and Ground Improvement Inspection
7 Chapter 7: Retaining Structures, Site Drainage, and Fill Material Control
7.1 Retaining Wall Backfill, Drainage Systems, and Lateral Earth Pressures 7.2 Structural Fill Selection, Gradation, and Clod Control 7.3 Fill Placement, Lift Thickness, and Compaction Equipment Operations
8 Chapter 8: Field Density & Moisture Testing Methods
8.1 Nuclear Density Gauge Testing and Radiation Safety (ASTM D6938) 8.2 Sand Cone Density Testing and Field Volumetric Verification (ASTM D1556) 8.3 Rapid Field Moisture Methods and Laboratory Verification (ASTM D2216, D4643, D4959)
9 Chapter 9: Compaction Calculations, Quality Assurance, and Special Conditions
9.1 Field Density and Compaction Calculations 9.2 Oversize Particle Corrections (ASTM D4718) 9.3 Testing Frequency, Failed Test Resolution, and Adverse Weather Earthwork
4.3 Earthwork Quantities, Mass Haul Concepts, and Material Balance
Key Takeaways Explain This Topic AI
The Average End Area method calculates earthwork volume in cubic yards as V = L × (A1 + A2) / 54; for steep or rapid cross-sectional transitions, the prismoidal formula must be applied to prevent significant volume overestimation.
Soil exists in three distinct volumetric states: in-situ bank volume (BCY), loose volume after excavation (LCY), and compacted volume in fill (CCY); granular materials swell 10% to 15% upon excavation, while cohesive soils shrink 10% to 25% from natural bank volume to compacted embankment volume.
The mass haul diagram is a continuous curve of cumulative net earthwork volume plotted against stationing; rising sections denote net cut, falling sections denote net fill, peaks and valleys identify daylight lines, and horizontal balance lines define equal cut-fill haul segments.
Freehaul is the maximum transport distance included in the contractor's base unit bid price, while overhaul represents additional yardage haul compensation beyond the freehaul limit, quantified in station-yards.
Special Inspectors track load counts, loose-to-compacted yield ratios, and material transitions in the field; unexpected excessive shrinkage or encounters with unmapped bedrock disrupt the mass balance, signaling severe project borrow deficits or waste surpluses.
Last updated: September 2026
4.3 Earthwork Quantities, Mass Haul Concepts, and Material Balance
Earthwork engineering requires precise volumetric analysis to balance site grading, schedule haul equipment, manage construction budgets, and ensure structural stability. When earthwork contractors excavate, haul, and compact soil, the material undergoes dramatic volumetric and density phase changes. For the ICC Soils Special Inspector, understanding earthwork volume calculation methods, soil bulk changes, and mass haul diagrams is essential for auditing daily field operations, tracking earthwork yields, and detecting unexpected subsurface conditions.
A failure to account for soil shrinkage can leave a project thousands of cubic yards short of required structural fill (forcing costly off-site borrow import), while unexpected rock bulking can generate mountains of unmarketable waste. This section details the mathematical formulas, soil volume states, and mass haul principles governing earthwork material balance.
Earthwork Volume Calculation Methods
Civil engineers and grading contractors quantify earthwork volumes using two primary geometric methods: the Average End Area Method (for linear alignments like roadways, channels, and railways) and the Grid / Borrow Pit Method (for mass site excavations, building pads, and borrow pits).
1. The Average End Area Method
The Average End Area method calculates the volume of a three-dimensional soil prismoid between two parallel cross-sectional stations by averaging their cross-sectional end areas and multiplying by the distance between them. Volume ( cu ft ) = L × ( A 1 + A 2 2 ) \text{Volume } (\text{cu ft}) = L \times \left( \frac{A_1 + A_2}{2} \right) Volume ( cu ft ) = L × ( 2 A 1 + A 2 )
To express the volume in the industry-standard unit of Cubic Yards (CY) , divide cubic feet by 27 cu ft/cu yd 27\text{ cu ft/cu yd} 27 cu ft/cu yd : V = L × ( A 1 + A 2 ) 2 × 27 = L × ( A 1 + A 2 ) 54 V = \frac{L \times (A_1 + A_2)}{2 \times 27} = \frac{L \times (A_1 + A_2)}{54} V = 2 × 27 L × ( A 1 + A 2 ) = 54 L × ( A 1 + A 2 )
Where:
V V V : Volume of cut or fill between stations in Cubic Yards (CY) .
L L L : Horizontal distance between the two cross-sectional stations along the centerline (in feet).
A 1 A_1 A 1 : Cross-sectional cut or fill area at the first station (in square feet).
A 2 A_2 A 2 : Cross-sectional cut or fill area at the second station (in square feet). STATION 10+00 STATION 11+50
- Cross-Section Area A1 Cross-Section Area A2
- +-------------------+ +-----------------------+
- | | | |
- | A1 = 400 sf |==============================| A2 = 650 sf |
- | | Distance L = 150 ft | |
- +-------------------+ +-----------------------+
- Volume = 150 * (400 + 650) / 54 = 2,916.7 CY
- Limitations and the Prismoidal Correction
The Average End Area method assumes that cross-sectional areas vary linearly between stations. In real terrain, this assumption introduces an error: Average End Area always overestimates volume whenever A 1 ≠ A 2 A_1 \ne A_2 A 1 = A 2 . The greater the difference between A 1 A_1 A 1 and A 2 A_2 A 2 , the larger the error.
When cross-sectional areas change rapidly (such as transitions from deep cuts to shallow daylight points, or where one end area approaches zero in a pyramid-like terminus), civil specifications require the Prismoidal Formula : V p = L × ( A 1 + 4 A m + A 2 ) 6 × 27 = L × ( A 1 + 4 A m + A 2 ) 162 V_p = \frac{L \times (A_1 + 4A_m + A_2)}{6 \times 27} = \frac{L \times (A_1 + 4A_m + A_2)}{162} V p = 6 × 27 L × ( A 1 + 4 A m + A 2 ) = 162 L × ( A 1 + 4 A m + A 2 )
Where:
A m A_m A m : The actual cross-sectional area at the mid-station ( L / 2 L/2 L /2 ).
Caution
A critical mathematical rule: A m A_m A m is NOT the arithmetic average of A 1 A_1 A 1 and A 2 A_2 A 2 (which would reduce the prismoidal formula right back to the Average End Area formula!). Rather, A m A_m A m is determined from cross-sectional dimensions linearly interpolated at the midpoint between the two stations.
2. The Grid / Borrow Pit Method (Unit Area Method)
For broad mass excavations—such as commercial building pads, multi-acre subdivisions, or borrow pits—cross-sections are impractical. The area is divided into a regular grid of square or rectangular blocks of equal horizontal area A A A (typically 50 × 50 ft = 2 , 500 sq ft 50\times50\text{ ft} = 2,500\text{ sq ft} 50 × 50 ft = 2 , 500 sq ft or 20 × 20 ft = 400 sq ft 20\times20\text{ ft} = 400\text{ sq ft} 20 × 20 ft = 400 sq ft ).
Surveyors measure existing ground elevations at every grid intersection (corner node) prior to excavation, and re-survey the same nodes after excavation. The vertical cut (or fill) depth h h h is calculated at each node. To account for the geometric fact that interior grid nodes are shared by multiple adjoining squares, corners are weighted by the number of adjacent grid squares sharing that node: V = A 4 × 27 ( ∑ h 1 + 2 ∑ h 2 + 3 ∑ h 3 + 4 ∑ h 4 ) V = \frac{A}{4 \times 27} \left( \sum h_1 + 2\sum h_2 + 3\sum h_3 + 4\sum h_4 \right) V = 4 × 27 A ( ∑ h 1 + 2 ∑ h 2 + 3 ∑ h 3 + 4 ∑ h 4 )
Where:
V V V : Total volume in cubic yards (CY).
A A A : Plan area of a single grid square (sq ft).
∑ h 1 \sum h_1 ∑ h 1 : Sum of cut/fill depths at nodes belonging to only 1 square (perimeter exterior corners).
∑ h 2 \sum h_2 ∑ h 2 : Sum of cut/fill depths at nodes shared by 2 adjacent squares (exterior perimeter edges).
∑ h 3 \sum h_3 ∑ h 3 : Sum of cut/fill depths at nodes shared by 3 adjacent squares (re-entrant corners).
∑ h 4 \sum h_4 ∑ h 4 : Sum of cut/fill depths at nodes shared by 4 interior squares (standard interior nodes).
Soil Bulk Changes and Phase Relationships
A cubic yard of soil does not occupy the same physical volume throughout the earthwork lifecycle. Soil volume depends entirely on its degree of compaction and void ratio across three distinct physical states: [ BANK STATE ] -------------> [ LOOSE STATE ] -------------> [ COMPACTED STATE ]
- In-Situ Undisturbed Excavated & Transported Mechanically Compacted
- Natural Void Ratio Large Void Ratio (Air Voids) Low Void Ratio (Dense)
- High Natural Density Low Density Maximum Dry Density
- ==================== ============================ ======================
- 1.00 Bank Cu Yd (BCY) =====> 1.25 Loose Cu Yd (LCY) =====> 0.85 Compacted Cu Yd (CCY)
- [ Density Drops ] [ Density Increases ]
- [ Swell: +25% ] [ Net Shrinkage: -15% relative to Bank ]
- The Three Soil Volumetric States
Bank Cubic Yards (BCY): The volume of soil in its natural, undisturbed in-situ geological condition prior to excavation.
Loose Cubic Yards (LCY): The volume of soil after it has been excavated, ripped, blasted, or loaded into haul trucks. The soil grains separate, air voids are introduced, the void ratio increases dramatically, and the bulk density drops.
Compacted Cubic Yards (CCY): The volume of soil after it has been placed in an engineered embankment, moisture-conditioned, and compacted by heavy rollers. Air voids are driven out, soil platelets pack tightly together, and the compacted dry unit weight typically exceeds the natural in-situ bank dry unit weight.
1. Swell Factor ( S w S_w S w ) and Swell Percentage
When in-situ soil is excavated, it expands ("bulks") in volume: % Swell = ( γ bank γ loose − 1 ) × 100 % = ( V loose V bank − 1 ) × 100 % \% \text{ Swell} = \left( \frac{\gamma_{\text{bank}}}{\gamma_{\text{loose}}} - 1 \right) \times 100\% = \left( \frac{V_{\text{loose}}}{V_{\text{bank}}} - 1 \right) \times 100\% % Swell = ( γ loose γ bank − 1 ) × 100% = ( V bank V loose − 1 ) × 100% L C Y = B C Y × ( 1 + S w ) LCY = BCY \times (1 + S_w) L C Y = BC Y × ( 1 + S w )
Where γ bank \gamma_{\text{bank}} γ bank and γ loose \gamma_{\text{loose}} γ loose are the dry densities in the bank and loose states, and S w S_w S w is the decimal swell factor (e.g., 25 % swell ⟹ S w = 0.25 25\% \text{ swell} \implies S_w = 0.25 25% swell ⟹ S w = 0.25 ).
2. Load Factor ( L F LF L F )
The Load Factor is the mathematical inverse of the swell expansion, converting loose haul volumes back into bank excavation volumes: L F = γ loose γ bank = 1 1 + S w LF = \frac{\gamma_{\text{loose}}}{\gamma_{\text{bank}}} = \frac{1}{1 + S_w} L F = γ bank γ loose = 1 + S w 1 B C Y = L C Y × L F BCY = LCY \times LF BC Y = L C Y × L F
3. Shrinkage Factor ( S h Sh S h ) and Shrinkage Percentage
When soil is excavated from the natural bank state and compacted into an engineered embankment, the final compacted volume is almost always smaller than the original bank volume (except in blasted rock, which bulks permanently). This volumetric reduction is termed shrinkage : % Shrinkage = ( 1 − γ bank γ compacted ) × 100 % = ( 1 − V compacted V bank ) × 100 % \% \text{ Shrinkage} = \left( 1 - \frac{\gamma_{\text{bank}}}{\gamma_{\text{compacted}}} \right) \times 100\% = \left( 1 - \frac{V_{\text{compacted}}}{V_{\text{bank}}} \right) \times 100\% % Shrinkage = ( 1 − γ compacted γ bank ) × 100% = ( 1 − V bank V compacted ) × 100% C C Y = B C Y × ( 1 − S h ) CCY = BCY \times (1 - Sh) CC Y = BC Y × ( 1 − S h )
To determine how many Bank Cubic Yards (BCY) of excavation are required to produce a specified Compacted Cubic Yard (CCY) fill volume: B C Y required = C C Y 1 − S h BCY_{\text{required}} = \frac{CCY}{1 - Sh} BC Y required = 1 − S h CC Y
Where S h Sh S h is the decimal shrinkage factor (e.g., 15 % shrinkage ⟹ S h = 0.15 15\% \text{ shrinkage} \implies Sh = 0.15 15% shrinkage ⟹ S h = 0.15 ).
Comprehensive Soil Volume State Transition Table
Soil Classification & Material Type Bank Density (pcf) Loose Density (pcf) Compacted Density (pcf) Swell (%) Shrinkage (%) Conversion: 1 BCY to LCY Conversion: 1 BCY to CCY Conversion: 1 CCY to BCY
Clean Sand & Gravel (GW / SW) 115 − 125 115 - 125 115 − 125 100 − 110 100 - 110 100 − 110 125 − 135 125 - 135 125 − 135 12 % 12\% 12% 8 % 8\% 8% 1.12 LCY 1.12\text{ LCY} 1.12 LCY 0.92 CCY 0.92\text{ CCY} 0.92 CCY 1.09 BCY 1.09\text{ BCY} 1.09 BCY
Silty Sand / Sandy Loam (SM) 105 − 115 105 - 115 105 − 115 85 − 95 85 - 95 85 − 95 120 − 130 120 - 130 120 − 130 18 % 18\% 18% 12 % 12\% 12% 1.18 LCY 1.18\text{ LCY} 1.18 LCY 0.88 CCY 0.88\text{ CCY} 0.88 CCY 1.14 BCY 1.14\text{ BCY} 1.14 BCY
Lean Clay / Silt (CL / ML) 100 − 110 100 - 110 100 − 110 75 − 85 75 - 85 75 − 85 115 − 125 115 - 125 115 − 125 25 % 25\% 25% 16 % 16\% 16% 1.25 LCY 1.25\text{ LCY} 1.25 LCY 0.84 CCY 0.84\text{ CCY} 0.84 CCY 1.19 BCY 1.19\text{ BCY} 1.19 BCY
Fat Clay (CH) 90 − 105 90 - 105 90 − 105 65 − 75 65 - 75 65 − 75 110 − 120 110 - 120 110 − 120 35 % 35\% 35% 20 % 20\% 20% 1.35 LCY 1.35\text{ LCY} 1.35 LCY 0.80 CCY 0.80\text{ CCY} 0.80 CCY 1.25 BCY 1.25\text{ BCY} 1.25 BCY
Blasted Solid Rock / Granite 160 − 170 160 - 170 160 − 170 95 − 105 95 - 105 95 − 105 130 − 145 130 - 145 130 − 145 65 % 65\% 65% − 20 % -20\% − 20% (Bulks!) 1.65 LCY 1.65\text{ LCY} 1.65 LCY 1.20 CCY 1.20\text{ CCY} 1.20 CCY 0.83 BCY 0.83\text{ BCY} 0.83 BCY
Warning
Notice the critical anomaly for Blasted Rock : Rock does not shrink when placed in fill! Blasting breaks solid bedrock into jagged, interlocking boulders with large interstitial air voids. Even after heavy compaction with rock rollers, blasted rock exhibits permanent bulking ( 1.0 BCY 1.0\text{ BCY} 1.0 BCY yields approximately 1.20 CCY 1.20\text{ CCY} 1.20 CCY of fill). Treating rock as having soil-like shrinkage will produce severe material balance errors.
Mass Haul Diagrams and Material Balancing
A Mass Haul Diagram is a continuous two-dimensional graphical plot used by civil engineers to plan, manage, and economically optimize earthwork distribution along a linear project (roadway, railway, levee, or pipeline).
Horizontal (X) Axis: Linear stationing along the centerline alignment (in hundreds of feet).
Vertical (Y) Axis: The cumulative algebraic sum of net earthwork volume (in cubic yards), with excavation (cut) plotted as positive (increasing) and embankment (fill) plotted as negative (decreasing). Cumulative Earthwork
- Volume (CY)
- +
- ^ DAYLIGHT POINT (Peak)
- +8,000| /\ (Transition Cut to Fill)
- +6,000| / \
- +4,000| BALANCE LINE / \------------------------- (Haul Loop)
- +2,000| ------------------------------/ \ /
- 0|===============================+========\=====================+=====> Stationing
- 2,000| Sta 10+00 \ Sta 22+00
- 4,000| \ /
- 6,000| \ /
- 8,000| \ /
- | \___________/ (Transition Fill to Cut)
- DAYLIGHT POINT (Valley)
- Fundamental Properties of the Mass Haul Curve
Rising Sections (Positive Slope): Indicate sections of the project where cut exceeds fill (net excavation).
Falling Sections (Negative Slope): Indicate sections where fill exceeds cut (net embankment).
Peaks (Local Maxima): Represent the exact point where a cut section ends and a fill section begins—the daylight line .
Valleys (Local Minima): Represent the point where a fill section ends and a cut section begins—another daylight line.
Balance Line: Any horizontal line drawn across the mass haul diagram. Where the mass curve intersects the balance line, the net volume of cut exactly equals the net volume of fill between those two stations. Earthwork is completely balanced between those intersection points.
Direction of Haul:
A loop above the balance line represents material that must be hauled forward (in the direction of increasing stationing, left to right).
A loop below the balance line represents material that must be hauled backward (in the direction of decreasing stationing, right to left).
Economic Haul Concepts: Freehaul vs. Overhaul
Haul Distance: The actual distance excavated material is transported from the cut excavation to the fill embankment.
Freehaul Distance (FHD): The maximum distance specified in the contract over which the contractor must transport excavated material at the base unit bid price per cubic yard, without additional payment. Standard freehaul distances are typically 500 feet or 1,000 feet .
Overhaul: The transportation of material beyond the freehaul distance limit. Overhaul is billed as a separate bid item measured in Station-Yards ( 1 sta-yd = 1 cubic yard of soil transported one station [100 feet] beyond the freehaul limit 1\text{ sta-yd} = 1\text{ cubic yard of soil transported one station [100 feet] beyond the freehaul limit} 1 sta-yd = 1 cubic yard of soil transported one station [100 feet] beyond the freehaul limit ) : Overhaul (sta-yd) = Overhaul Volume (CY) × ( Haul Distance − Freehaul Distance 100 ft ) \text{Overhaul (sta-yd)} = \text{Overhaul Volume (CY)} \times \left( \frac{\text{Haul Distance} - \text{Freehaul Distance}}{100\text{ ft}} \right) Overhaul (sta-yd) = Overhaul Volume (CY) × ( 100 ft Haul Distance − Freehaul Distance )
Borrow vs. Waste:
Borrow: When the mass haul curve terminates below the zero datum line at the end of the project, a net deficit of material exists. The contractor must import structural fill from an off-site borrow pit.
Waste (Spoil): When the mass curve terminates above the zero datum line, a net surplus of material exists. Surplus cut must be disposed of in designated spoil berms or exported off-site.
- Worked Engineering Example: End Area Volume, Haul Loads, and Embankment Yield
- Problem Statement
A highway grading project requires mass excavation between Station 14+00 and Station 16+50 .
Cross-sectional surveys produce the following cut end areas:
- At Station 14+00: A 1 = 450.0 sq ft A_1 = 450.0\text{ sq ft} A 1 = 450.0 sq ft
- At Station 16+50: A 2 = 750.0 sq ft A_2 = 750.0\text{ sq ft} A 2 = 750.0 sq ft
Geotechnical laboratory tests classify the cut material as a lean clay with:
Natural bank in-situ dry density: γ bank = 108.0 pcf \gamma_{\text{bank}} = 108.0\text{ pcf} γ bank = 108.0 pcf
Swell factor: S w = 0.20 S_w = 0.20 S w = 0.20 ( 20 % swell 20\% \text{ swell} 20% swell )
Embankment shrinkage factor: S h = 0.15 Sh = 0.15 S h = 0.15 ( 15 % shrinkage 15\% \text{ shrinkage} 15% shrinkage from bank to compacted fill)
The contractor will haul the material using off-road articulating dump trucks with an effective rated capacity of 18.0 LCY 18.0\text{ LCY} 18.0 LCY per truck.
Calculate:
The in-situ volume of cut in Bank Cubic Yards (BCY) using the Average End Area method.
The total loose volume in Loose Cubic Yards (LCY) and the total number of truck loads required to haul the excavation.
The net yield of structural fill in Compacted Cubic Yards (CCY) that this excavation will produce in the fill embankment.
Step 1: Calculate Bank Volume (BCY)
Distance between stations: L = ( 16 + 50 ) − ( 14 + 00 ) = 1 , 650 ft − 1 , 400 ft = 250.0 ft L = (16+50) - (14+00) = 1,650\text{ ft} - 1,400\text{ ft} = 250.0\text{ ft} L = ( 16 + 50 ) − ( 14 + 00 ) = 1 , 650 ft − 1 , 400 ft = 250.0 ft .
Average End Area: A avg = A 1 + A 2 2 = 450.0 + 750.0 2 = 1 , 200.0 2 = 600.0 sq ft A_{\text{avg}} = \frac{A_1 + A_2}{2} = \frac{450.0 + 750.0}{2} = \frac{1,200.0}{2} = 600.0\text{ sq ft} A avg = 2 A 1 + A 2 = 2 450.0 + 750.0 = 2 1 , 200.0 = 600.0 sq ft
Volume in Bank Cubic Yards: V bank = L × ( A 1 + A 2 ) 54 = 250.0 × 1 , 200.0 54 = 300 , 000.0 54 = 5 , 555.56 BCY V_{\text{bank}} = \frac{L \times (A_1 + A_2)}{54} = \frac{250.0 \times 1,200.0}{54} = \frac{300,000.0}{54} = 5,555.56\text{ BCY} V bank = 54 L × ( A 1 + A 2 ) = 54 250.0 × 1 , 200.0 = 54 300 , 000.0 = 5 , 555.56 BCY
Step 2: Calculate Loose Volume (LCY) and Truck Loads
Loose volume after excavation swell ( S w = 0.20 S_w = 0.20 S w = 0.20 ): V loose = B C Y × ( 1 + S w ) = 5 , 555.56 × ( 1 + 0.20 ) = 5 , 555.56 × 1.20 = 6 , 666.67 LCY V_{\text{loose}} = BCY \times (1 + S_w) = 5,555.56 \times (1 + 0.20) = 5,555.56 \times 1.20 = 6,666.67\text{ LCY} V loose = BC Y × ( 1 + S w ) = 5 , 555.56 × ( 1 + 0.20 ) = 5 , 555.56 × 1.20 = 6 , 666.67 LCY
Truck haul count ( 18.0 LCY 18.0\text{ LCY} 18.0 LCY capacity per truck): Truck Loads = 6 , 666.67 LCY 18.0 LCY/truck = 370.37 → 371 Truck Loads \text{Truck Loads} = \frac{6,666.67\text{ LCY}}{18.0\text{ LCY/truck}} = 370.37 \rightarrow 371\text{ Truck Loads} Truck Loads = 18.0 LCY/truck 6 , 666.67 LCY = 370.37 → 371 Truck Loads
Step 3: Calculate Compacted Fill Embankment Yield (CCY)
Compacted volume after embankment shrinkage ( S h = 0.15 Sh = 0.15 S h = 0.15 ): V compacted = B C Y × ( 1 − S h ) = 5 , 555.56 × ( 1 − 0.15 ) = 5 , 555.56 × 0.85 = 4 , 722.23 CCY V_{\text{compacted}} = BCY \times (1 - Sh) = 5,555.56 \times (1 - 0.15) = 5,555.56 \times 0.85 = 4,722.23\text{ CCY} V compacted = BC Y × ( 1 − S h ) = 5 , 555.56 × ( 1 − 0.15 ) = 5 , 555.56 × 0.85 = 4 , 722.23 CCY
This cut section will yield 4 , 722.23 CCY 4,722.23\text{ CCY} 4 , 722.23 CCY of finished structural fill.
Special Inspector Field Verification Checklist: Material Balance and Yield Tracking
In the field, the Soils Special Inspector serves as the quality control watchdog monitoring earthwork yields to detect unforeseen subsurface conditions:
Haul Count vs. Bank Excavation Tracking: Maintain daily records of scraper and dump truck tallies from each cut sector. If truck haul counts significantly exceed expected loose volumes ( B C Y × [ 1 + S w ] BCY \times [1+S_w] BC Y × [ 1 + S w ] ), investigate whether unmapped boulders or differing soil strata are expanding more than predicted.
Loose Lift Thickness Control: Verify that loose soil lift thickness prior to compaction matches project specifications (typically 8 to 12 inches loose). Measure the compacted thickness after roller passes: if an 8-inch loose lift compacts to only 5 inches (37% loose compaction loss), the material may have excessive moisture or high plasticity fines.
Early Identification of Differing Subsurface Conditions:
Excessive Shrinkage Deficit: If laboratory tests indicate 12 % 12\% 12% shrinkage but field surveys demonstrate 22 % 22\% 22% shrinkage, the site will face a critical structural fill deficit, requiring early notification to the geotechnical engineer and owner.
Unexpected Bedrock / Rock Bulking: If cut excavations hit shallow, unmapped bedrock, blasting will produce large rock fragments that bulk by 50 % 50\% 50% to 70 % 70\% 70% . Because rock fragments larger than 3 inches cannot be incorporated into standard structural fill lifts under IBC J107.4, this material must be processed, crushed, or wasted, completely upending the mass haul balance.