6.6 Time & Work, Speed-Time-Distance, Simple & Compound Interest

UGC NET National Eligibility Test

Track your progress as you read

Finished sections get a check mark.

1 Introduction & UGC NET Exam Structure

1.1 Exam Format, Scoring & Qualification Rules 1.2 Paper 1 Blueprint, Unit Weighting & High-Yield Strategy 1.3 CBT Interface Navigation, Pacing & Error Traps

2 Unit 1: Teaching Aptitude

2.1 Concept, Objectives & Levels of Teaching 2.2 Learner Characteristics & Factors Affecting Teaching 2.3 Teacher-Centred vs. Learner-Centred & Digital Teaching Methods 2.4 Evaluation Systems, CBCS & Computer-Based Assessment 2.5 Teaching Support Systems: Traditional, Modern & ICT-Based

3 Unit 2: Research Aptitude

3.1 Meaning, Types & Characteristics of Research 3.2 Steps of Research & Experimental Methodologies 3.3 Thesis Writing, Formatting Styles & Shodhganga 3.4 Research Ethics, UGC Plagiarism Regulations 2018 & Academic Integrity

4 Unit 3: Reading Comprehension

4.1 Academic Text Analysis & Core Question Archetypes 4.2 Logical Inferences, Authorial Stance & Contextual Vocabulary 4.3 High-Density Passage Walkthroughs & Question Deconstruction

5 Unit 4: Communication

5.1 Meaning, Types & Models of Communication 5.2 Verbal, Non-Verbal & Classroom Communication Dynamics 5.3 Psychological, Semantic, Cultural & Organizational Barriers 5.4 Mass Media, Digital Communication & Societal Impact

6 Unit 5: Mathematical Reasoning & Aptitude

6.1 Types of Reasoning: Verbal, Non-Verbal, Deductive, Inductive & Analogical 6.2 Number Series, Letter Series, Coding-Decoding & Direction Tests 6.3 Blood Relations, Order & Ranking, Family Tree Logic 6.4 Mathematical Aptitude: Fractions, Percentages, Profit & Loss 6.5 Ratios, Proportions, Mixtures & Averages 6.6 Time & Work, Speed-Time-Distance, Simple & Compound Interest

7 Unit 6: Logical Reasoning & Indian Logic

7.1 Structure of Arguments, Deductive vs. Inductive Reasoning, Syllogisms 7.2 Classical Square of Opposition, Categorical Propositions & Connotation/Denotation 7.3 Venn Diagrams, Moods & Figures, Formal and Informal Fallacies 7.4 Indian Logic: Six Pramanas 7.5 Structure of Anumana & Hetvabhasa

8 Unit 7: Data Interpretation

8.1 Sources, Acquisition & Graphical Representation 8.2 Tabular Data Analysis & Quantitative Calculation Shortcuts 8.3 Pie Charts, Bar Charts & Multi-Variable Data Sets 8.4 Data and Governance, Common NTA Traps & Error Prevention

9 Unit 8: Information & Communication Technology (ICT)

9.1 ICT Terminology, Acronyms, Hardware & Memory Hierarchy 9.2 Binary, Octal, Decimal, Hexadecimal Conversions & File Formats 9.3 Internet, Intranet, TCP/IP, Protocols, Email Mechanics & Cyber Security 9.4 Digital Initiatives in Higher Education 9.5 Audio & Video Conferencing: Protocols, Codecs & Educational Deployment 9.6 ICT and Governance: e-Governance Models, Digital India & Service Delivery

10 Unit 9: People, Development & Environment

10.1 Millennium Development Goals (MDGs) & Sustainable Development Goals (SDGs) 10.2 Air, Water, Soil & Noise Pollution and Health Impacts 10.3 Solid Waste, Hazardous Waste, Climate Change & Global Warming 10.4 Solar, Wind, Hydro, Biomass & India's Clean Energy Targets 10.5 Environmental Protection Act 1986, NAPCC & International Accords 10.6 Natural Hazards, Disasters & Mitigation Strategies

11 Unit 10: Higher Education System

11.1 Institutions of Higher Learning in Ancient India 11.2 Evolution of Higher Learning in Pre & Post-Independence India 11.3 Apex Regulatory Bodies, Accreditations & Institutional Classifications 11.4 National Education Policy (NEP 2020) & Institutional Transformation 11.5 Professional, Technical & Skill-Based Education 11.6 Value Education & Environmental Education

12 Paper 2 Strategy, Mock Testing & Exam Day Execution

12.1 Paper 2 Subject Strategy & Core Discipline Methodologies 12.2 Full 150-Question Timed Simulation Strategy, Error Logging & Endurance 12.3 NTA Exam-Day Protocols, CBT Test-Taking Rules & Score Maximization

6.6 Time & Work, Speed-Time-Distance, Simple & Compound Interest

Key Takeaways Explain This Topic AI

Time and Work problems are solved using the LCM efficiency method, where Total Work equals LCM ( t 1 , t 2 , … ) \text{LCM}(t_1, t_2, \dots) LCM ( t 1 ​ , t 2 ​ , … ) and individual daily efficiencies are summed: Time Together = Total Work ∑ E i \text{Time Together} = \frac{\text{Total Work}}{\sum E_i} Time Together = ∑ E i ​ Total Work ​ .

The universal Chain Rule formula M 1 D 1 H 1 E 1 W 1 = M 2 D 2 H 2 E 2 W 2 \frac{M_1 D_1 H_1 E_1}{W_1} = \frac{M_2 D_2 H_2 E_2}{W_2} W 1 ​ M 1 ​ D 1 ​ H 1 ​ E 1 ​ ​ = W 2 ​ M 2 ​ D 2 ​ H 2 ​ E 2 ​ ​ reconciles multi-parameter variations in personnel, daily operating hours, efficiency, and project output.

Speed conversions require multiplying km/h \text{km/h} km/h by 5 18 \frac{5}{18} 18 5 ​ to obtain m/s \text{m/s} m/s (and m/s × 18 5 \text{m/s} \times \frac{18}{5} m/s × 5 18 ​ for km/h \text{km/h} km/h ); average speed over equal distances equals 2 x y x + y \frac{2xy}{x+y} x + y 2 x y ​ .

Relative speed equals s 1 + s 2 s_1 + s_2 s 1 ​ + s 2 ​ when two moving bodies travel in opposite directions and ∣ s 1 − s 2 ∣ |s_1 - s_2| ∣ s 1 ​ − s 2 ​ ∣ when traveling in the same direction; boats moving downstream have speed u + v u+v u + v , and upstream u − v u-v u − v .

Simple interest ( S I = P R T 100 SI = \frac{PRT}{100} S I = 100 PRT ​ ) accrues linearly, while compound interest ( A = P ( 1 + R 100 ) T A = P(1 + \frac{R}{100})^T A = P ( 1 + 100 R ​ ) T ) compounds exponentially; the difference between CI and SI for 2 2 2 years is P ( R 100 ) 2 P(\frac{R}{100})^2 P ( 100 R ​ ) 2 .

Last updated: August 2026

Time & Work, Speed-Time-Distance, Simple & Compound Interest

Quick Answer: Arithmetic aptitude in Paper 1 relies on structured algebraic formulas. Solve Time and Work via the LCM efficiency method (Total Work = LCM = \text{LCM} = LCM , Time = Work / ∑ Efficiencies = \text{Work}/\sum \text{Efficiencies} = Work / ∑ Efficiencies ) and the Chain Rule: M 1 D 1 H 1 W 1 = M 2 D 2 H 2 W 2 \frac{M_1 D_1 H_1}{W_1} = \frac{M_2 D_2 H_2}{W_2} W 1 ​ M 1 ​ D 1 ​ H 1 ​ ​ = W 2 ​ M 2 ​ D 2 ​ H 2 ​ ​ . For Speed-Time-Distance , convert km/h × 5 18 = m/s \text{km/h} \times \frac{5}{18} = \text{m/s} km/h × 18 5 ​ = m/s , apply average speed 2 x y x + y \frac{2xy}{x+y} x + y 2 x y ​ , and combine train/platform lengths. For Interest , S I = P R T 100 SI = \frac{PRT}{100} S I = 100 PRT ​ , C I = P ( 1 + R 100 ) T − P CI = P(1 + \frac{R}{100})^T - P C I = P ( 1 + 100 R ​ ) T − P , and the 2 2 2 -year difference between CI and SI is P ( R 100 ) 2 P(\frac{R}{100})^2 P ( 100 R ​ ) 2 .

1. Time and Work: The LCM / Efficiency Framework

While the unitary method solves work problems via fractions, the LCM (Total Work) Method avoids fractional addition, accelerating speed and accuracy.

The LCM Efficiency Method Steps

Define Total Work: Let Total Work equal the LCM \text{LCM} LCM of the individual completion times.

Compute Individual Daily Efficiencies ( E E E ): Efficiency ( E ) = Total Work Time Taken \text{Efficiency } (E) = \frac{\text{Total Work}}{\text{Time Taken}} Efficiency ( E ) = Time Taken Total Work ​

Combine Efficiencies: Add efficiencies for collaborative work; subtract efficiency for negative work (leaks/drainage).

Calculate Time Taken: Time Taken = Total Work Combined Efficiency \text{Time Taken} = \frac{\text{Total Work}}{\text{Combined Efficiency}} Time Taken = Combined Efficiency Total Work ​

Worker Time Taken ( T T T ) Total Work (LCM) Daily Efficiency ( E = W / T E = W/T E = W / T )

Worker A 12 days 12\text{ days} 12 days LCM ( 12 , 15 , 20 ) = 60 units \text{LCM}(12, 15, 20) = 60\text{ units} LCM ( 12 , 15 , 20 ) = 60 units 60 / 12 = 5 units/day 60 / 12 = 5\text{ units/day} 60/12 = 5 units/day

Worker B 15 days 15\text{ days} 15 days 60 units 60\text{ units} 60 units 60 / 15 = 4 units/day 60 / 15 = 4\text{ units/day} 60/15 = 4 units/day

Worker C 20 days 20\text{ days} 20 days 60 units 60\text{ units} 60 units 60 / 20 = 3 units/day 60 / 20 = 3\text{ units/day} 60/20 = 3 units/day

A + B + C Together — 60 units 60\text{ units} 60 units 5 + 4 + 3 = 12 units/day 5 + 4 + 3 = 12\text{ units/day} 5 + 4 + 3 = 12 units/day Time for A, B, C Together = 60 units 12 units/day = 5 days \text{Time for A, B, C Together} = \frac{60\text{ units}}{12\text{ units/day}} = 5\text{ days} Time for A, B, C Together = 12 units/day 60 units ​ = 5 days

Two-Worker Algebraic Shortcut

If A A A takes x x x days and B B B takes y y y days: Time Together = x × y x + y \text{Time Together} = \frac{x \times y}{x + y} Time Together = x + y x × y ​

The Multi-Variable Chain Rule (Man-Days-Hours Formula)

To resolve scenarios involving changing workforce sizes, daily operating hours, differing efficiencies, and varied work quotas: M 1 × D 1 × H 1 × E 1 W 1 = M 2 × D 2 × H 2 × E 2 W 2 \frac{M_1 \times D_1 \times H_1 \times E_1}{W_1} = \frac{M_2 \times D_2 \times H_2 \times E_2}{W_2} W 1 ​ M 1 ​ × D 1 ​ × H 1 ​ × E 1 ​ ​ = W 2 ​ M 2 ​ × D 2 ​ × H 2 ​ × E 2 ​ ​

  • M = Number of workers M = \text{Number of workers} M = Number of workers
  • D = Number of working days D = \text{Number of working days} D = Number of working days
  • H = Working hours per day H = \text{Working hours per day} H = Working hours per day
  • E = Efficiency factor of workers E = \text{Efficiency factor of workers} E = Efficiency factor of workers

W = Quantum of work produced (e.g., metres of wall, units manufactured, wages earned) W = \text{Quantum of work produced (e.g., metres of wall, units manufactured, wages earned)} W = Quantum of work produced (e.g., metres of wall, units manufactured, wages earned)

Pipes and Cisterns

Inlet Pipe ( A A A ): Fills tank ⟹ \implies ⟹ Positive Efficiency ( + E A +E_A + E A ​ ).

Outlet / Drainage Pipe / Leak ( B B B ): Empties tank ⟹ \implies ⟹ Negative Efficiency ( − E B -E_B − E B ​ ).

Net Filling Rate: E net = E inlet − E outlet E_{\text{net}} = E_{\text{inlet}} - E_{\text{outlet}} E net ​ = E inlet ​ − E outlet ​ .

If an inlet fills a tank in x x x hours and an outlet empties it in y y y hours ( y > x y > x y > x ): Net Time to Fill = x × y y − x \text{Net Time to Fill} = \frac{x \times y}{y - x} Net Time to Fill = y − x x × y ​

2. Speed, Time, and Distance Mastery

Unit Conversions and Basic Relations Distance ( D ) = Speed ( S ) × Time ( T ) \text{Distance } (D) = \text{Speed } (S) \times \text{Time } (T) Distance ( D ) = Speed ( S ) × Time ( T ) Speed in m/s = Speed in km/h × 5 18 \text{Speed in m/s} = \text{Speed in km/h} \times \frac{5}{18} Speed in m/s = Speed in km/h × 18 5 ​ Speed in km/h = Speed in m/s × 18 5 \text{Speed in km/h} = \text{Speed in m/s} \times \frac{18}{5} Speed in km/h = Speed in m/s × 5 18 ​

Average Speed Formulations

General Definition: Average Speed = Total Distance Travelled Total Time Taken \text{Average Speed} = \frac{\text{Total Distance Travelled}}{\text{Total Time Taken}} Average Speed = Total Time Taken Total Distance Travelled ​ .

Equal Distance Traveled at Two Different Speeds ( x x x and y y y ): Average Speed = 2 x y x + y \text{Average Speed} = \frac{2xy}{x + y} Average Speed = x + y 2 x y ​

Equal Distance Traveled at Three Different Speeds ( x , y , z x, y, z x , y , z ): Average Speed = 3 x y z x y + y z + z x \text{Average Speed} = \frac{3xyz}{xy + yz + zx} Average Speed = x y + yz + z x 3 x yz ​

Relative Speed Principles

Opposite Directions (Moving toward or away from each other): Relative Speed = S 1 + S 2 \text{Relative Speed} = S_1 + S_2 Relative Speed = S 1 ​ + S 2 ​

Same Direction (One pursuing the other): Relative Speed = ∣ S 1 − S 2 ∣ \text{Relative Speed} = |S_1 - S_2| Relative Speed = ∣ S 1 ​ − S 2 ​ ∣

Loading diagram... Train Motion and Collision Distance Formulations

Train Physics and Distance Rules

Scenario Distance Traversed ( D D D ) Relative Speed ( S S S ) Time Taken ( T T T )

Train crossing stationary point (Pole/Tree/Man) L train L_{\text{train}} L train ​ S train S_{\text{train}} S train ​ T = L train S train T = \frac{L_{\text{train}}}{S_{\text{train}}} T = S train ​ L train ​ ​

Train crossing Platform / Bridge / Tunnel L train + L platform L_{\text{train}} + L_{\text{platform}} L train ​ + L platform ​ S train S_{\text{train}} S train ​ T = L train + L platform S train T = \frac{L_{\text{train}} + L_{\text{platform}}}{S_{\text{train}}} T = S train ​ L train ​ + L platform ​ ​

Two trains crossing in Opposite Directions L 1 + L 2 L_1 + L_2 L 1 ​ + L 2 ​ S 1 + S 2 S_1 + S_2 S 1 ​ + S 2 ​ T = L 1 + L 2 S 1 + S 2 T = \frac{L_1 + L_2}{S_1 + S_2} T = S 1 ​ + S 2 ​ L 1 ​ + L 2 ​ ​

Two trains crossing in Same Direction L 1 + L 2 L_1 + L_2 L 1 ​ + L 2 ​ S 1 − S 2 S_1 - S_2 S 1 ​ − S 2 ​ T = L 1 + L 2 S 1 − S 2 T = \frac{L_1 + L_2}{S_1 - S_2} T = S 1 ​ − S 2 ​ L 1 ​ + L 2 ​ ​

Boats and Streams Vector Mechanics

Let the speed of a boat in still water be u km/h u\text{ km/h} u km/h , and the speed of the water stream/current be v km/h v\text{ km/h} v km/h :

Downstream Speed ( D D D ): Moving with the current: D = u + v D = u + v D = u + v .

Upstream Speed ( U U U ): Moving against the current: U = u − v U = u - v U = u − v .

  • Speed of Boat in Still Water ( u u u ): u = D + U 2 u = \frac{D + U}{2} u = 2 D + U ​
  • Speed of Stream / Current ( v v v ): v = D − U 2 v = \frac{D - U}{2} v = 2 D − U ​
  • 3. Simple and Compound Interest Formulations
  • Simple Interest (SI)

Simple interest accrues linearly exclusively on the initial principal P P P : S I = P × R × T 100 SI = \frac{P \times R \times T}{100} S I = 100 P × R × T ​ Total Amount ( A ) = P + S I = P ( 1 + R × T 100 ) \text{Total Amount } (A) = P + SI = P\left(1 + \frac{R \times T}{100}\right) Total Amount ( A ) = P + S I = P ( 1 + 100 R × T ​ )

Rule of Doubling in SI: If a sum of money doubles itself in T T T years, then R = 100 T % R = \frac{100}{T}\% R = T 100 ​ % .

Rule of n n n -times in SI: If a sum becomes n n n times itself in T T T years, ( n − 1 ) = R × T 100 (n - 1) = \frac{R \times T}{100} ( n − 1 ) = 100 R × T ​ .

Compound Interest (CI)

Compound interest accrues on both the principal and previously accumulated interest: Total Amount ( A ) = P ( 1 + R 100 ) T \text{Total Amount } (A) = P\left(1 + \frac{R}{100}\right)^T Total Amount ( A ) = P ( 1 + 100 R ​ ) T C I = A − P = P [ ( 1 + R 100 ) T − 1 ] CI = A - P = P\left[\left(1 + \frac{R}{100}\right)^T - 1\right] C I = A − P = P [ ( 1 + 100 R ​ ) T − 1 ]

Compounding Frequencies Adjustment Table

  • Compounding Frequency Effective Rate ( R ′ R' R ′ ) Number of Periods ( T ′ T' T ′ ) Amount Formula ( A A A )
  • Annually R R R T T T A = P ( 1 + R 100 ) T A = P\left(1 + \frac{R}{100}\right)^T A = P ( 1 + 100 R ​ ) T

Semi-Annually (Half-Yearly) R / 2 R / 2 R /2 2 T 2T 2 T A = P ( 1 + R / 2 100 ) 2 T A = P\left(1 + \frac{R/2}{100}\right)^{2T} A = P ( 1 + 100 R /2 ​ ) 2 T

Quarterly R / 4 R / 4 R /4 4 T 4T 4 T A = P ( 1 + R / 4 100 ) 4 T A = P\left(1 + \frac{R/4}{100}\right)^{4T} A = P ( 1 + 100 R /4 ​ ) 4 T

Monthly R / 12 R / 12 R /12 12 T 12T 12 T A = P ( 1 + R / 12 100 ) 12 T A = P\left(1 + \frac{R/12}{100}\right)^{12T} A = P ( 1 + 100 R /12 ​ ) 12 T

Difference Between CI and SI Theorems

For a principal sum P P P invested at annual rate R % R\% R % :

Difference for 2 Years ( D 2 D_2 D 2 ​ ): D 2 = C I 2 − S I 2 = P ( R 100 ) 2 = P R 2 10000 D_2 = CI_2 - SI_2 = P\left(\frac{R}{100}\right)^2 = \frac{P R^2}{10000} D 2 ​ = C I 2 ​ − S I 2 ​ = P ( 100 R ​ ) 2 = 10000 P R 2 ​

Difference for 3 Years ( D 3 D_3 D 3 ​ ): D 3 = C I 3 − S I 3 = P ( R 100 ) 2 ( 3 + R 100 ) = P R 2 ( 300 + R ) 10 6 D_3 = CI_3 - SI_3 = P\left(\frac{R}{100}\right)^2 \left(3 + \frac{R}{100}\right) = \frac{P R^2 (300 + R)}{10^6} D 3 ​ = C I 3 ​ − S I 3 ​ = P ( 100 R ​ ) 2 ( 3 + 100 R ​ ) = 1 0 6 P R 2 ( 300 + R ) ​

Worked Example: Find the difference between CI and SI on ₹ 10 , 000 10,000 10 , 000 for 2 2 2 years at 8 % 8\% 8% per annum. D 2 = 10000 × ( 8 100 ) 2 = 10000 × 64 10000 = 64 D_2 = 10000 \times \left(\frac{8}{100}\right)^2 = 10000 \times \frac{64}{10000} = 64 D 2 ​ = 10000 × ( 100 8 ​ ) 2 = 10000 × 10000 64 ​ = 64 The calculated difference is ₹ 64 64 64 .