1 Exam Overview

Well Control Incidents and Their Consequences Qualification, Assessment and Study Planning

2 Hydrostatic Pressure and the Circulating System

Hydrostatic Pressure, Fluid Gradients, and Mud Weight Multiple Fluid Columns and Inverse Hydrostatic Calculations U-Tube Principle, Dynamic Pressure Losses, and Equivalent Circulating Density

3 Formation Pressure and Integrity Limits

Formation Pore Pressure, Normal vs Abnormal Pressure, and Fracture Gradient LOT/FIT Graphs and the Pressure Window MAASP, Kick Tolerance, and Formation Breakdown

4 Barriers and Risk Management

Well Barrier Concepts: Primary, Secondary, and Composite Envelopes Barrier Verification, Monitoring, and Life Cycle Management Well Control Risk Assessment, Human Factors, and Management of Change

5 Fluid Density and Circulation Data

Insufficient Mud Density & Encountering Abnormal Pressures Barite Weighting and Pump-Pressure Changes Pre-Recorded Data, Pump Output, and Slow Circulating Rates

6 Trip Preparation and Pressure Support

Swabbing and Surging During Tripping Operations Slugs, Trip Margin and Pumping Out Unfilled-Hole Limits and Tubular Displacement

7 Trip Monitoring and Connections

Hole Fill Failure and Trip Tank Monitoring Procedures Trip Tanks, PVT Systems, and Flow Return Sensors Kick Indicators During Tripping, Connections, and Out of Hole

8 Kick Warnings and Indicators

Flow Checks and Drilling Breaks Primary Kick Indicators While Drilling Lost Circulation and Loss of Hydrostatic Head

9 Influx Characteristics and Behaviour

Influx Types (Gas, Oil, Salt Water) & Influx Density Determination Gas Solubility in Oil-Based Mud vs Water-Based Mud

10 Gas Expansion and Closed-Well Migration

Gas Physics: Boyle's Law, Expansion, and Migration Velocities Gas Migration in a Shut-In Well & Pressure Buildup Effects

11 Surface Shut-In and Pressure Interpretation

Hard Shut-In vs Soft Shut-In Philosophies & Principles Surface BOP Shut-In Protocols (Drilling, Tripping, Wireline/Out of Hole) Post Shut-In Pressure Stabilization & Data Recording

12 Subsea, Wireline and Stripping Response

Subsea BOP Shut-In Protocols & Space-Out Procedures Wireline Displacement and Pressure-Control Equipment Annular and Ram-to-Ram Stripping

13 Kill-Sheet Calculations

Calculating Kill Mud Weight, ICP, and FCP Drill String/Annular Volumes, Strokes to Bit, and Circulating Times

14 Circulating Kill Methods

The Driller's Method: Detailed Two-Circulation Procedure The Wait and Weight Method & Step-Down Pressure Graphs Comparison of Constant Bottomhole Pressure Methods

15 Special Pressure-Control Methods

Volumetric Method, Lubricate and Bleed, and Bullheading Subsea CLF: Startup, Shutdown and Fluid Displacement

16 Casing and Cementing Well Control

Running Casing: Floats, Clearances and Volumes Cementing: Pressure Profile and Barrier Quality Casing Shut-In and Assembly Readiness

17 Drills and Equipment First Actions

Well Control Drills and Operational Checklists Gauge Failure and BOP Leak First Actions Bit Nozzle Plugging and Mud Pump Failure During a Kill

18 Operational Contingencies

Drill String Washout and Parted Pipe Management Severe Lost Circulation and Underground Blowout Scenarios Gas at Surface, Hydrate Formation, and Diverter Operations

19 Preventer Capabilities

Annular Preventers: Design, Operation, and Stripping Use Pipe Rams and Variable Bore Rams (VBRs) Blind Rams, Shear Rams, and Casing Shear Rams

20 Stack, Connections and Flow Routes

Surface BOP Stack Arrangements, API Specifications, and Outlets Ram Locking Mechanisms and Wellhead Connectors Choke and Kill Lines, Valves, and Pressure Ratings Choke Manifolds, Remote Chokes, and Manual Adjustable Chokes

21 Diverters and Auxiliary Equipment

Shallow Gas and Diverter Response Mud/Gas Separators (Poor Boy Degassers): Liquid Seal & Blow-Through Vacuum Degassers, Desanders, Desilters, and Rig Gas Detectors Drill String Safety Valves, Gray Valves, and Float Valves

22 Hydraulic Control Systems

Accumulator Unit Components: Reservoir, Fluid, and Pumps Accumulator Bottles, Nitrogen Precharge, and Operating Pressures Regulators, Pilot Circuits, and Manifold/Annular Pressure Control Stored Capacity, Accumulator Drawdown Tests and Remote Panels

23 Testing and Subsea Systems

Low-Pressure and High-Pressure BOP Testing Criteria Function Testing, Test Frequencies, and Test Tools Subsea BOP Architecture, LMRP, MUX Control, and Choke Line Friction Subsea Riser Margin, Gas in Riser, and Emergency Disconnect

Casing Shut-In and Assembly Readiness

Key Takeaways Explain This Topic AI

Prepare compatible internal and annular closure equipment before running casing.

Match the actual casing body, coupling and running tools to sealing and shear capabilities.

Use the operation-specific posted sequence and verify both flow paths.

If containment fails, activate the approved alternative barrier and report the limitation.

Last updated: October 2026

Prepare the closure before the assembly enters

Running casing, a liner or completion equipment can put diameters and accessories across the BOP that differ from the drillpipe used during drilling. The crew must identify a sealable position and the method for closing the internal bore before starting. A large coupling, centraliser, running tool or hanger may be non-sealable or non-shearable with the installed elements. Closure capability is part of the running plan, not a question deferred until flow appears.

Read the stack drawing and the casing assembly tally together. Record which ram or annular is qualified for the current OD, the joint clearance needed and the applicable closing pressure. Confirm the internal shut-in valve, crossover or casing safety-valve arrangement is ready, compatible and pressure-rated. The valve's handling equipment must be suitable for the weight and connection. A drillpipe valve sitting nearby is not a ready casing barrier if it cannot connect to the assembly.

Detect an event using the correct baseline

Casing displacement can produce large planned returns. More returns than expected may indicate influx; fewer may indicate losses. Internal filling and self-fill behaviour also change the prediction. Track the actual mode and document transfers. Increased flow after movement stops, continued unexplained gain or a pressure trend inconsistent with the operation requires the approved first response. Stop the running operation and communicate promptly.

The crew must avoid confusing a warning with an already evident influx. A flow check evaluates uncertain conditions under the procedure; it must not become an extended delay when positive influx indications already require containment. The supervisor needs casing depth, float status, internal fill, the assembly at the BOP and the observed volumes. These details determine which closure path is available.

The containment sequence

Use the posted procedure for the installed casing arrangement. Its essential duties are to stop the operation, position a qualified sealable section without unnecessary delay, secure the casing interior, close the appropriate annular or ram path and ensure the choke/kill route has the intended status. The precise order and handling steps depend on equipment, flow conditions and the approved hard shut-in procedure. A manual valve installation must not expose personnel to uncontrolled high-energy flow.

If the arrangement uses a stab-in full-opening safety valve, it is normally prepared open so fluid can pass during installation, then made up and closed as instructed. Confirm connection compatibility and sealing after closure. If the flow or pressure prevents safe manual installation, use the preplanned alternative; do not improvise forceful stabbing against an uncontrolled jet. Top-drive or cementing-head valves may provide another qualified route depending on the installation.

Verify the well, not just the command

After operating the designated elements, check panel feedback, hydraulic response and observed well flow. Monitor the trip tank and appropriate gauges. Check for external leakage and pressure where there should be none. Confirm that the correct function was selected and that the sealing element is on the intended tubular body rather than a coupling. If the well is not contained, operate the planned second barrier and escalate the emergency response.

A closed annular can leave the casing interior flowing. A closed internal safety valve can leave the annulus flowing. A float may limit backflow from inside the casing but cannot be credited with sealing an annular influx. Barrier verification therefore follows every possible path. Do not open the BOP simply because one gauge reads zero when another route still shows unexplained flow.

Example of assembly selection

Suppose a training stack has fixed 5 inch pipe rams, variable-bore rams qualified only from 3.5 to 5.5 inches, and an annular qualified for the 9.625 inch casing body. The fixed and variable rams cannot be credited with sealing that casing. The annular may provide the intended annular closure at a verified body position, subject to its pressure and element limits. If a non-sealable coupling is across it, the documented space-out action is needed.

Now suppose the only available internal valve has a drillpipe connection without a suitable crossover. The annular closure remains useful, but the total envelope is incomplete. The plan must provide the compatible internal barrier before proceeding. This example illustrates why readiness requires a matching set of equipment and procedures rather than merely counting preventers.

Handover and next steps

Record stabilised pressures when available, fluid density, casing position, influx estimate, losses, closed elements, internal valve status and any equipment limitation. Preserve the timeline of movement and observed deviations. While awaiting instructions, continue monitoring for flow, pressure changes, gas and leaks. A changing pressure can indicate migration, an incomplete barrier or other effects; report the trend instead of bleeding pressure without an authorised pressure-maintenance plan.

The supervisor directs the subsequent circulation or other control method, taking account of floats, casing geometry, fluid profiles and the weak-point limit. Changing a valve line-up or moving casing through a closed element requires a defined plan and suitable equipment. The initial goal is timely verified containment; returning to the planned running depth is secondary to preserving that containment.

Casing closure paths

  • Item Interpretation
  • Casing interior Compatible pressure-rated internal closure
  • Annulus Qualified element at a sealable position
  • Verification No unplanned flow or pressure and correct function
  • Failure Designated alternative barrier and escalation