Study guide
3.4 Continuous Loads, Demand, and 125 Percent Rules
Journeyman Electrician Study Guide Exam
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Exam Orientation and Source Control
1.1 ICC R17, T17, G17, and Jurisdiction Variance 1.2 Current Format, Cost, Time, and Passing Score 1.3 Licensing Board vs. Exam Provider 1.4 Official References, Open-Book Rules, and Calculators 1.5 Domain Weights and Study Map 1.6 Using the Practice Bank, Error Log, and NEC Index
2 Chapter 2: NEC Navigation, Definitions, and Code Strategy
2.1 NEC Book Structure and Article Map 2.2 Article 100 Definitions and Exam Language 2.3 Index, Table, and Annex Navigation 2.4 Shall, Shall Not, Permitted, and Informational Notes 2.5 Using Code References Without Overlooking Context 2.6 State Amendments and Code Edition Control 2.7 NEC Navigation Case Lab
3 Chapter 3: Electrical Theory and Calculation Foundations
3.1 Ohm's Law, Power, and Basic Units 3.2 Series, Parallel, and Circuit Behavior 3.3 Single-Phase, Three-Phase, and Voltage Systems 3.4 Continuous Loads, Demand, and 125 Percent Rules 3.5 Voltage Drop and Practical Calculation Setup 3.6 Load Calculation Workflow 3.7 Calculation Foundation Case Lab
4 Chapter 4: Services, Service Equipment, and Grounding/Bonding
4.1 Service Point, Service Conductors, and Disconnects 4.2 Service Load Calculation and Sizing 4.3 Service Equipment, Panelboards, and Switchboards 4.4 Grounding Electrode System and GEC 4.5 Bonding, Main Bonding Jumpers, and Effective Fault Path 4.6 Transformers and Separately Derived Systems 4.7 Services and Grounding Case Lab
5 Chapter 5: Feeders, Branch Circuits, and Conductor Sizing
5.1 Feeder vs. Branch Circuit Boundaries 5.2 Branch Circuit Ratings and Required Outlets 5.3 Conductor Ampacity, Temperature, and Terminal Ratings 5.4 Adjustment, Correction, and More Than Three Conductors 5.5 Overcurrent Protection and Small-Conductor Rules 5.6 GFCI, AFCI, Equipment Grounding, and Dwelling Circuits 5.7 Feeders and Branch Circuits Case Lab
6 Chapter 6: Wiring Methods, Raceways, Boxes, and Cables
6.1 Raceway Selection and Installation Logic 6.2 Underground Wiring, Wet Locations, and Protection 6.3 Boxes, Enclosures, and Conduit Bodies 6.4 Box Fill, Conductor Counting, and Device Yokes 6.5 Cabinets, Panelboards, and Switchboards 6.6 Flexible Cords, Cables, and Temporary Wiring 6.7 Wiring Methods Case Lab
7 Chapter 7: Equipment, Devices, Luminaires, and Controls
7.1 Receptacles, Switches, and Device Selection 7.2 Luminaires, Lampholders, and Lighting Outlets 7.3 Appliances and Utilization Equipment 7.4 Heating, Cooling, and HVAC Electrical Connections 7.5 Disconnects, Controllers, and Switching Devices 7.6 Equipment Grounding, Bonding, and Listing Markings 7.7 Equipment and Devices Case Lab
8 Chapter 8: Motors, Generators, Transformers, and Special Equipment
8.1 Motor Circuit Anatomy and Article 430 Navigation 8.2 Motor Conductors, Overload, and Short-Circuit Protection 8.3 Motor Controllers, Disconnects, and Nameplates 8.4 Generators, Transfer Equipment, and Optional Standby 8.5 Transformer Sizing, Protection, and Grounding 8.6 Emergency Systems, Fire Alarms, and Signaling Overview 8.7 Motors and Generators Case Lab
9 Chapter 9: Special Occupancies, Renewables, and Safety
9.1 Hazardous Classified Locations 9.2 Healthcare, Marinas, RV Parks, and Mobile Home Parks 9.3 Pools, Spas, and Similar Installations 9.4 Solar PV, Energy Storage, and Renewable Systems 9.5 Temporary Power, Emergency Systems, and Special Conditions 9.6 OSHA Subpart K and Safe Work Practice Context 9.7 Special Occupancies Case Lab
10 Chapter 10: Open-Book Exam Workflow and Mixed Code Labs
10.1 Four-Hour Pacing and Question Triage 10.2 Look-Up vs. Know-From-Memory Decisions 10.3 Mixed Calculation Lab 10.4 Mixed Code Navigation Lab 10.5 Diagnostic Report and Error Log Remediation 10.6 High-Weight Domain Remediation Plan 10.7 Full Exam Simulation Playbook
11 Chapter 11: Final Review, Test Day, and License Planning
11.1 Final Two-Week Study Plan 11.2 Reference Book, Tabs, and Allowed Materials Checklist 11.3 Pearson VUE, PRONTO, and Test-Day Rules 11.4 After the Exam: Results, Retakes, and Challenges 11.5 License Application, Work Hours, and Jurisdiction Next Steps 11.6 After Journeyman: Master, Contractor, and Continuing Education
3.4 Continuous Loads, Demand, and 125 Percent Rules
Key Takeaways Explain This Topic AI
A continuous load is a load expected to run for 3 hours or more, and many NEC rules require sizing at 125 percent of that load.
Do not apply a 125 percent factor to every load automatically; identify the code rule, load type, and whether noncontinuous loads are included.
Demand factors reduce calculated load only where the NEC permits them, and they must be applied in the correct order.
Exam questions often test the difference between connected load, calculated load, minimum ampacity, and overcurrent device size.
Last updated: May 2026
The 125 percent rule is common, not universal
A major journeyman exam trap is treating 125 percent as a magic number that applies everywhere. It appears often because continuous loads stress equipment for a long duration, but the NEC applies it through specific rules. Your job on the exam is to identify the load, identify the rule, and then apply the factor only where required.
A continuous load is generally one where the maximum current is expected to continue for 3 hours or more. Commercial lighting, show-window lighting, some fixed space-heating loads, signs, and certain process loads may be continuous depending on the facts and applicable NEC rule. A garbage disposer or hand dryer is not continuous merely because it is hardwired. Read the question facts.
Basic sizing pattern
A common branch-circuit or feeder pattern is:
Minimum ampacity = noncontinuous load + 125 percent of continuous load
If the continuous load is 16 A and the noncontinuous load is 10 A, the minimum ampacity is:
10 A + (16 A x 1.25) = 10 A + 20 A = 30 A.
Do not multiply the total 26 A by 125 percent unless the rule says all of it is continuous. If you do, you get 32.5 A and may select a larger answer than required. The distinction matters in multiple-choice questions where both answers appear.
Worked example: mixed branch load
A branch circuit supplies a 12 A continuous display lighting load and an 8 A noncontinuous receptacle load. What minimum branch-circuit ampacity is required before choosing conductor size from a table?
Known values: continuous = 12 A, noncontinuous = 8 A.
Required ampacity = 8 + (12 x 1.25) = 8 + 15 = 23 A.
The calculated minimum is 23 A. The next step may involve standard overcurrent device ratings, conductor ampacity, terminal temperature limitations, and small conductor rules. The answer to the arithmetic step is not automatically a 25 A breaker unless the question asks for the next standard rating and the applicable rule allows it.
Demand factor logic
Connected load is the total rating of equipment connected. Calculated load is the load after applying NEC rules such as demand factors, load factors, or specific allowances. Demand factors recognize that not all connected loads operate at full rating at the same time. They are permitted only by specific NEC provisions.
A demand factor is not a field guess. You do not reduce a load because it seems unlikely to run. You reduce it when the NEC table or rule allows reduction for that type of occupancy, equipment, or load group. For dwellings, ranges, dryers, general lighting, multifamily calculations, and other categories may have specific methods. For non-dwelling occupancies, other rules may apply. The correct method depends on the exact article and table in the NEC edition used by your exam.
Order of operations
The exam often tests order. Suppose a problem gives several loads and asks for a feeder. You may need to calculate individual loads, apply demand factors to certain categories, then add continuous-load factors where required, then size conductors and overcurrent protection. Reversing demand and 125 percent can change the answer.
A practical workflow is:
List each load and its unit: A, W, VA, kVA, hp, or nameplate.
Convert to VA or amperes as required by the rule.
Group loads by NEC category: lighting, receptacles, appliances, motors, heating, cooking, dryers, signs, or special equipment.
Apply the demand factor only to the load group for which it is allowed.
Apply continuous-load sizing where the rule requires it.
Convert final VA to amperes if conductor or equipment ampacity is requested.
Move to tables or standard-size rules only after the calculated load is established.
Worked example: demand and continuous load
A feeder supplies 18,000 VA of noncontinuous load and 12,000 VA of continuous lighting load on a 240-volt single-phase system. No demand factor is stated or permitted in the question. What minimum feeder ampacity is required?
Continuous adjusted load = 12,000 x 1.25 = 15,000 VA. Add noncontinuous load: 15,000 + 18,000 = 33,000 VA. Convert to amperes: 33,000 / 240 = 137.5 A.
If you first added the loads and divided by voltage, you would get 30,000 / 240 = 125 A, then perhaps multiply all current by 125 percent and get 156.25 A. Both are wrong for this fact pattern. The correct method adjusts only the continuous portion.
Continuous load and equipment ratings
Some listed equipment may be rated for continuous operation at 100 percent under specific conditions. The NEC has provisions that distinguish ordinary equipment from assemblies listed for operation at 100 percent of rating. Do not assume 100 percent operation is allowed unless the problem gives that condition or the code rule supports it. On a contractor/trades exam, the safer method is to follow the stated NEC rule exactly.
Calculator discipline
Keep the continuous and noncontinuous columns separate on scratch work. On PRONTO or computer-based testing, loose paper rules and calculator permissions can vary by delivery method, so practice a compact mental layout you can reproduce with the permitted tools. If a basic four-function calculator is used, avoid long chained entries. Compute the adjusted continuous portion, write or hold it, then add the noncontinuous portion.
Exam traps
Do not apply 125 percent twice. If a load has already been adjusted by a rule or nameplate instruction, read whether the next rule asks for additional sizing. Do not apply demand factors to the 125 percent multiplier itself; demand applies to a load category, while continuous sizing applies to duration and equipment loading. Do not treat demand factor and diversity as the same thing. The NEC provides demand factors; field intuition does not.
Also watch answer wording. Minimum conductor ampacity, minimum branch-circuit rating, calculated load, and overcurrent protective device rating are related but not identical. The question stem tells you which stage of the calculation chain it wants.