1.4 Plan Reading: Electrical Drawings, Symbols & Schedules
Kentucky Journeyman Electrician Exam
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Kentucky Licensing, Electrical Theory & Plan Reading
1.1 Kentucky Electrical Licensing Framework & Regulations 1.2 Electrical Fundamentals, Ohm's Law & Power Calculations 1.3 AC Theory, Power Factor & Three-Phase Principles 1.4 Plan Reading: Electrical Drawings, Symbols & Schedules
2 Chapter 2: NEC Organization, Article 100 Definitions & Working Spaces
2.1 NEC Structure, Article 90 Scope & Code Navigation 2.2 Essential Article 100 Definitions 2.3 Article 110 Installation Requirements & Equipment Working Spaces
3 Chapter 3: Branch Circuits & Receptacle Outlets
3.1 Branch Circuit Ratings & Conductor Sizing 3.2 Multiwire Branch Circuits & Identification 3.3 GFCI and AFCI Protection Requirements 3.4 Required Dwelling Outlets & Lighting
4 Chapter 4: Feeders, Outside Branch Circuits & Calculations
4.1 Feeder Conductor Sizing & Continuous Loads 4.2 Feeder Tap Rules & Overcurrent Protection 4.3 Outside Branch Circuits & Feeders
5 Chapter 5: Services & Service Equipment
5.1 Service Conductors, Overhead & Underground 5.2 Service Disconnecting Means & Equipment Ratings 5.3 Emergency Disconnects, Surge Protection & Ground Fault Protection
6 Chapter 6: Overcurrent Protection & Tap Rules
6.1 Overcurrent Protection Principles, Fuses & Circuit Breakers 6.2 Small Conductor Protection & Next-Higher-Standard-Rating Rule 6.3 Transformer Secondary & Equipment Protection Taps
7 Chapter 7: Grounding & Bonding — Systems & Electrodes
7.1 Grounding Theory, System Grounding & Grounded Conductors 7.2 Grounding Electrode System & Electrode Types 7.3 Grounding Electrode Conductor Sizing & Installation
8 Chapter 8: Grounding & Bonding — Equipment & Enclosures
8.1 Main & System Bonding Jumpers 8.2 Equipment Grounding Conductors 8.3 Bonding of Raceways, Enclosures & Piping Systems
9 Chapter 9: Wiring Methods, Raceways & Enclosures
9.1 General Wiring Requirements & Underground Installations 9.2 Metal Raceways — EMT, RMC, IMC & FMC 9.3 Nonmetallic Raceways & Flexible Conduits 9.4 Cabinets, Panelboards, Wireways, Cable Trays & Busways
10 Chapter 10: Conductors, Cables, Box Fill & Pull Boxes
10.1 Conductor Types, Insulations & Ampacity Sizing 10.2 Ampacity Derating — Temperature Correction & Conduit Fill Adjustment 10.3 Nonmetallic-Sheathed Cable, MC Cable & Armored Cable 10.4 Box Fill Calculations & Pull Box Sizing
11 Chapter 11: Equipment for General Use
11.1 Switches, Receptacles & Flexible Cords 11.2 Luminaires, Lampholders & Clothes Closets 11.3 Appliances, Space Heating & De-icing Equipment
12 Chapter 12: Motors, Generators, HVAC & Control Circuits
12.1 Motor Full-Load Current & Branch Circuit Conductor Sizing 12.2 Motor Overload & Branch-Circuit Short-Circuit / Ground-Fault Protection 12.3 Motor Disconnecting Means & Motor Controllers 12.4 HVAC Equipment, Transformers & Generators 12.5 Class 1, Class 2 & Class 3 Remote-Control, Signaling & Power-Limited Circuits
13 Chapter 13: Special Occupancies & Conditions
13.1 Hazardous (Classified) Locations 13.2 Commercial Garages, Motor Fuel Dispensing & Spray Areas 13.3 Health Care Facilities & Places of Assembly 13.4 Agricultural Buildings & Swimming Pools 13.5 Manufactured Homes, RV Parks, Marinas & Temporary Installations
14 Chapter 14: Special Equipment, Standby & Communications Systems, Calculations & Exam Strategy
14.1 Solar Photovoltaic Systems, Energy Storage & EV Charging 14.2 Signs, Fire Pumps & Welders 14.3 Emergency Systems, Standby Systems & Fire Alarms 14.4 Communications Systems: Chapter 8 & Intersystem Bonding 14.5 Dwelling Unit & Commercial Load Calculations 14.6 Conduit Fill, Voltage Drop & Exam Day Strategy
1.4 Plan Reading: Electrical Drawings, Symbols & Schedules
Key Takeaways Explain This Topic AI
Electrical sheets usually carry the E discipline designator, and specifications for electrical, communications, and electronic safety work fall under CSI MasterFormat Divisions 26, 27, and 28.
Drawing symbols vary from one engineer to the next, so confirm every symbol in the project legend; IEEE 315 and ANSI/NECA 100 are common starting points.
At an architectural scale of 1/8 inch = 1 foot, each inch on paper represents 8 feet; at 1/4 inch = 1 foot, each inch represents 4 feet.
A feeder callout such as 4#4/0, 1#4 G, 2-1/2 in. C lists the number and size of conductors, the equipment grounding conductor, and the conduit trade size.
On a three-phase panel numbered odd-left and even-right, circuit pairs 1-2, 3-4, and 5-6 sit on phases A, B, and C, and the pattern repeats down the panel.
Last updated: October 2026
1.4 Plan Reading: Electrical Drawings, Symbols & Schedules
Prov's Kentucky journeyman outline lists Plan Reading as its own content area (about 5 of the 80 questions), and every journeyman works from prints every day. Plan-reading questions check whether you can find information in a drawing set, interpret symbols and abbreviations, measure with a scale, and read schedules and one-line diagrams. No NEC article sets drawing conventions, so every answer starts with the legend and notes on the drawings in front of you. The NEC comes in only when a question asks whether what is drawn complies with the code.
1. How a Drawing Set Is Organized
Commercial drawing sets are divided by discipline. Under the U.S. National CAD Standard, each sheet number begins with a discipline designator:
- Designator Discipline What an electrician looks for
- G General Cover sheet, sheet index, code summary, abbreviations
- A Architectural Floor plans, reflected ceiling plans, wall types, room numbers, door swings
- S Structural Beams, slabs, and penetrations that affect conduit routing
- M / P Mechanical / Plumbing HVAC units, pumps, and water heaters that need power, with their nameplate data
- E Electrical Lighting, power, systems, one-line diagrams, schedules, details
- T / F Telecommunications / Fire protection Data outlets, fire alarm and sprinkler coordination
Within the electrical sheets, a typical order is: symbols legend and general notes; electrical site plan; lighting plans; power plans; systems plans (fire alarm, data, security); one-line or riser diagrams; panel schedules; and details. The written specifications follow CSI MasterFormat: Division 26 (Electrical) , Division 27 (Communications) , and Division 28 (Electronic Safety and Security) . Projects specified before 2004 put all electrical work in Division 16. When a drawing and the specification disagree, the contract documents say which one governs; on the exam, use the information the question gives you.
Drawings also change during construction. A revision is usually shown with a cloud around the changed area and a numbered triangle (delta) keyed to the revision block. Addenda change the documents before bid, change orders change the contract afterward, and record ("as-built") drawings show what was actually installed.
2. Symbols, Abbreviations, and Notes
Symbol conventions come from standards such as IEEE 315 (graphic symbols for electrical and electronics diagrams) and ANSI/NECA 100 (symbols for electrical construction drawings), but each design firm customizes them. Read the project legend first. Common conventions include:
Receptacles: A circle with two short parallel lines is a duplex receptacle. Letters next to it modify it: GFCI, WP (weatherproof), WR (weather-resistant), IG (isolated ground), or a mounting height such as +42" above finished floor.
Switches: S is a single-pole switch, S3 a three-way, S4 a four-way, and a lowercase letter (a, b, c) ties a switch to the luminaires it controls. Dimmers, occupancy sensors, and low-voltage stations have their own legend symbols.
Luminaires: A letter or tag inside or beside the luminaire symbol, such as "A1" or "F2", refers to the luminaire schedule , which lists the manufacturer, lamp, voltage, wattage, and mounting.
Home runs: An arrow at the end of a circuit line means the circuit continues to its panel. A tag such as "LP-1-3,5" names the panel (LP-1) and the circuit numbers (3 and 5).
Hash marks: Tick marks across a raceway line show how many conductors it contains. One common convention uses short ticks for ungrounded conductors, a long tick for the neutral, and a tick with a dot for the equipment grounding conductor. Many legends say that a run with no ticks contains two 12 AWG conductors plus an equipment grounding conductor.
Keynotes and general notes: A number in a hexagon or circle points to a keynote on the same sheet. General notes often impose requirements that are not drawn, such as "provide a dedicated neutral for each circuit" or "all branch-circuit conductors shall be copper."
3. Using Scales
Floor plans are drawn to scale. On an architectural scale , a stated fraction of an inch equals one foot: at 1/8" = 1'-0" , one inch on paper equals 8 feet; at 1/4" = 1'-0" , one inch equals 4 feet; at 1/2" = 1'-0" (common for enlarged plans and electrical rooms), one inch equals 2 feet. Site plans often use engineering scales such as 1" = 20'. To convert, multiply the measured inches by the number of feet each inch represents:
A conduit run measures 6-3/4 inches on a 1/8" = 1'-0" plan: 6.75 × 8 = 54 6.75 \times 8 = 54 6.75 × 8 = 54 feet.
The same measurement on a 1/4" = 1'-0" plan is 6.75 × 4 = 27 6.75 \times 4 = 27 6.75 × 4 = 27 feet.
On a 1" = 20' site plan, a 4.5-inch trench is 4.5 × 20 = 90 4.5 \times 20 = 90 4.5 × 20 = 90 feet long.
Prints are often reduced to half size, which makes the stated scale wrong. Use the graphic (bar) scale printed on the sheet when a print may have been resized. When you estimate wire, add the vertical drops, the rise to the panel, and slack at each end to the horizontal distance you measured.
4. One-Line and Riser Diagrams
A one-line diagram shows the power system with a single line for each circuit, no matter how many conductors it has. It traces the utility source, service, transformers, switchboards, panelboards, and major loads, and shows overcurrent device ratings, transformer kVA and voltages, and often the available fault current at each bus. A riser diagram shows the same equipment arranged by floor, in a vertical view of the building.
Feeder callouts follow a pattern you must decode quickly. For example, "4#4/0, 1#4 G, 2-1/2" C" means four 4/0 AWG conductors (three phases and a neutral), one 4 AWG equipment grounding conductor, in 2-1/2-inch conduit. A callout such as "2 sets of 4#500 kcmil" means two parallel sets, which brings in NEC 310.10(G) for parallel conductors and 250.122(F) for the equipment grounding conductor in each raceway. Once you have decoded a callout, you can check it against the NEC: conduit fill in Chapter 9, ampacity in Table 310.16, and the equipment grounding conductor size in Table 250.122.
5. Panel Schedules
A panel schedule lists each circuit along with the panel's ratings. Read the header first:
- Header item What it tells you
- Voltage, phase, wires For example, 208Y/120 V, 3-phase, 4-wire
- Bus rating Continuous rating of the bus, such as 225 A
- Main Main breaker size, or MLO (main lugs only) when the panel is protected by an upstream device
- AIC or SCCR Interrupting or short-circuit current rating, such as 22,000 A
- Mounting Surface or flush
Fed from The upstream panel or switchboard; NEC 408.4(B) requires this source marking on panelboards in other than one- and two-family dwellings
Circuits are normally numbered odd on the left and even on the right. On a three-phase panel, circuits 1 and 2 are on phase A, 3 and 4 on phase B, and 5 and 6 on phase C, and the pattern repeats down the panel. A two-pole load on circuits 7 and 9 is therefore connected to phases A and B, and a three-pole load on circuits 2, 4, and 6 uses all three phases. The schedule totals each phase's connected load so the designer can balance the phases. The NEC also requires every circuit to be legibly identified on the directory as to its clear, evident, and specific purpose (408.4(A)).
6. Exam Approach for Plan-Reading Questions
Find the scale, legend entry, or schedule line the question refers to before doing any math.
Convert measurements with the stated scale unless the question says the print was reduced; then use the graphic scale.
For phase questions, write out the A-B-C sequence from circuit 1 down to the circuit in question.
Decide whether the question asks about a drawing convention (answer from the legend and notes) or a code rule (answer from the NEC).
When a question gives a feeder callout, decode every part (conductor count, size, grounding conductor, conduit) before checking it against a code table.