Study guide
1.5 Project Scheduling, CPM & Budget Management
Landscape Architect Registration Examination L.A.R.E.
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Project Management, Legal Framework & Contracts
1.1 Professional Practice, Ethics & the HSW Mandate 1.2 Standard of Care, Responsible Charge & Sealing Documents 1.3 Professional Services Agreements & Contract Clauses 1.4 Fee Structures, Compensation Models & Billing 1.5 Project Scheduling, CPM & Budget Management 1.6 Risk Management, Professional Liability & Insurance
2 Chapter 2: Site Inventory, Surveying & Regulatory Framework
2.1 Boundary Surveys, Legal Descriptions & Survey Datums 2.2 Topographic Surveys, Easements & Encumbrances 2.3 Desktop Inventory, GIS Data & Field Reconnaissance 2.4 Policy Documents & Prior Planning Studies 2.5 Adjacent Land Use & Contextual Data Collection 2.6 Stakeholder Engagement & Public Participation 2.7 Zoning Frameworks, Dimensional Standards & FAR 2.8 Parking Standards, Buffer Yards & Zoning Relief 2.9 Clean Water Act Permitting & NEPA Review 2.10 ESA, Floodplain, Coastal & Historic Preservation Compliance
3 Chapter 3: Physical, Contextual & Environmental Site Analysis
3.1 Scoping Site Analysis & Synthesizing Opportunities and Constraints 3.2 Geotechnical Investigation & Soil Classification Systems 3.3 Problematic Soil Conditions & Agronomic Soil Quality 3.4 Topographic Interpretation & Slope Suitability 3.5 Watershed Mechanics, Stream Order & FEMA Flood Hazard Zones 3.6 Wetland Delineation, Classification & Riparian Buffers 3.7 Utility Analysis & Infrastructure Capacity 3.8 Visual Resource & Viewshed Analysis 3.9 Contextual Analysis: Appropriate Use & Future Development Impacts 3.10 Microclimates, Solar Orientation & Vegetation Analysis
4 Chapter 4: Stewardship, Climate Resiliency & Design Principles
4.1 SITES v2 & LEED Site Credit Rating Systems 4.2 Life-Cycle Assessment, Embodied Carbon & Ecosystem Services 4.3 Climate Resiliency, Adaptation & Urban Heat Island Mitigation 4.4 Environmental Justice & Social Equity in Site Design 4.5 Cultural Landscapes, Historic Preservation & Adaptive Reuse
5 Chapter 5: Master Planning, Programming & Land Use
5.1 Project Visioning, Goal Setting & Space Programming 5.2 Carrying Capacity Analysis & NRPA Park Classification Standards 5.3 Site Suitability Synthesis & Opportunities/Constraints Mapping 5.4 Land Use Allocation & Development Scenario Evaluation 5.5 Master Plan Deliverables & Design Guidelines 5.6 Capital Improvement Programming, Phasing & Implementation
6 Chapter 6: Schematic Design & Spatial Organization
6.1 Design Intent, Conceptual Diagrams & Form Generation 6.2 Basis of Design, Alternatives Evaluation & the Preferred Scheme 6.3 Spatial Hierarchy, Outdoor Rooms & Proportion 6.4 Pedestrian Circulation Networks & Environmental Wayfinding 6.5 ADA & PROWAG Accessible Route Design 6.6 Multimodal Transportation, Vehicular Circulation & Parking Layout
7 Chapter 7: Design Development, Materials & Planting Systems
7.1 Paving Systems: Rigid, Flexible & Unit Pavers 7.2 Retaining Walls, Earth Pressure & Wall Drainage 7.3 Wall System Selection, Fences, Screens & Gates 7.4 Site Furnishings: Selection, Materiality & Anchoring 7.5 Exterior Lighting, Photometrics, Dark Sky & Electrical Safety 7.6 Public Playground Safety: CPSC & ASTM Standards 7.7 Planting Design Principles & Ecological Matching 7.8 Water Conservation, Xeriscaping & Irrigation System Principles 7.9 Opinions of Probable Cost & Value Engineering
8 Chapter 8: Construction Drawings, Layout & Detailing
8.1 Drawing Set Hierarchy, Sheet Standards & Drafting Conventions 8.2 Interdisciplinary Coordination & QA/QC Review 8.3 Demolition Plans & Tree Protection Requirements 8.4 Site Preparation: Clearing, Grubbing, Topsoil & Utility Abandonment 8.5 Layout, Dimensioning & Materials Plans 8.6 Planting Plans, Plant Schedules & Installation Details 8.7 Technical Detailing: Pavements, Curbs & Joint Assemblies 8.8 Retaining Wall, Stair & Ramp Detailing Standards
9 Chapter 9: Construction Specifications & Bidding
9.1 CSI MasterFormat Divisions & SectionFormat Structure 9.2 Specification Writing Methods & the Drawings–Specifications Relationship 9.3 Project Manual, General Conditions & Front-End Documents 9.4 Bid Requirements, Bid Forms & Addenda Management 9.5 Pre-Bid Procedures, Bid Opening & Contractor Evaluation
10 Chapter 10: Construction Administration, Submittals & Changes
10.1 Pre-Construction Conference & Construction Administration Authority 10.2 Initial Decision Maker, Communication Protocols & Project Records 10.3 Submittals, Shop Drawings, Product Data & Samples 10.4 Requests for Information (RFIs) & Technical Clarifications 10.5 Change Orders, Construction Change Directives & Claims
11 Chapter 11: Field Observation, Quality Control & Close-Out
11.1 Field Observations, Site Reports & Non-Conforming Work 11.2 Quality Control, Material Testing & Inspections 11.3 Substantial Completion, Punch Lists & Retainage 11.4 Project Close-Out, Guarantees, Warranties & Final Acceptance
12 Chapter 12: Contour Interpretation, Grading & Earthwork Calculations
12.1 Contour Rules & Topographic Landform Interpretation 12.2 Spot Elevations & Contour Interpolation Calculations 12.3 Slope Formulas, Maximum Gradients & Cross Slopes 12.4 Earthwork Calculations: Average End Area & Grid Methods 12.5 Cut and Fill Balancing, Shrinkage, Swell & Mass Haul 12.6 Reviewing Grading Design: Error Detection & Constructability
13 Chapter 13: Stormwater Hydrology, Runoff & BMP Design
13.1 Hydrologic Cycle, Watershed Delineation & Time of Concentration 13.2 Peak Runoff Estimation: The Rational Method (Q = CiA) 13.3 NRCS Curve Number Method & Runoff Hydrographs 13.4 LID Principles, Water Quality Volume & Bioretention Design 13.5 Bioswales, Permeable Pavement, Green Roofs & Harvesting
14 Chapter 14: Site Drainage Systems, Hydraulics & Erosion Control
14.1 Open Channel Hydraulics, Manning’s Equation & Swale Design 14.2 Gutter Flow, Spread & Roadway Inlet Hydraulics 14.3 Subsurface Drainage, Catch Basins & Pipe Invert Calculations 14.4 Stormwater Storage: Detention, Retention & Water Quality Basins 14.5 Reviewing Drainage Plans & Evaluating Design Alternatives 14.6 Erosion Mechanics, RUSLE & the NPDES/SWPPP Framework 14.7 Erosion & Sediment Control BMPs, Basins & Site Stabilization
1.5 Project Scheduling, CPM & Budget Management
Key Takeaways Explain This Topic AI
The Critical Path Method (CPM) identifies the longest continuous sequence of dependent activities through a network diagram, where Total Float equals zero and any delay directly pushes project completion.
Total Float (TF = LS - ES = LF - EF) represents the maximum time an activity can slip without delaying the final project deadline, whereas Free Float (FF = ES_successor - EF) is the time an activity can slip without delaying the Early Start of any immediate successor.
Landscape architectural design phases adhere to standardized effort and fee distributions: Schematic Design (~15-20%), Design Development (~20-25%), Construction Documents (~35-40%), Bidding (~5%), and Construction Administration (~15-20%).
Earned Value Management (EVM) utilizes Schedule Performance Index (SPI = EV / PV) and Cost Performance Index (CPI = EV / AC); values below 1.0 indicate schedule slippage and budget overruns, respectively.
Estimating precision evolves across design phases, progressing from conceptual unit-area metrics ($/sq.ft. with +/- 20-30% contingency) to elemental system assemblies in Design Development and granular unit-price quantity takeoffs in Construction Documents.
Last updated: September 2026
Core Focus: Project success hinges on scheduling precision, phase-by-phase resource allocation, and rigorous cost engineering. Mastery of the Critical Path Method (CPM), float calculations, Earned Value Management (EVM), and tiered estimating methodologies is indispensable for LARE Section 1.
1. Critical Path Method (CPM) Mechanics
The Critical Path Method (CPM) is an analytical, network-based scheduling technique used to determine the minimum total project duration, identify critical bottlenecks, and quantify scheduling flexibility (float) for every project task.
In landscape architecture, CPM networks are modeled using Activity-on-Node (AON) notation, where nodes represent activities with distinct durations, and arrows represent precedence dependencies (Finish-to-Start relationships).
The Forward Pass (Calculating Early Dates)
The forward pass determines the earliest possible calendar dates that activities can begin and conclude, moving left-to-right through the network:
Initial Activity: ES = 0 \text{ES} = 0 ES = 0 (or Day 1).
Early Finish Calculation: EF = ES + Duration \text{EF} = \text{ES} + \text{Duration} EF = ES + Duration
Successor Activities: When an activity depends on multiple predecessors, its Early Start is governed by the latest completing predecessor: ES successor = max ( EF all predecessors ) \text{ES}_{\text{successor}} = \max(\text{EF}_{\text{all predecessors}}) ES successor = max ( EF all predecessors )
The Backward Pass (Calculating Late Dates)
The backward pass determines the latest possible dates that activities can commence and finish without delaying the overall project completion deadline, moving right-to-left:
Terminal Activity: LF = EF terminal \text{LF} = \text{EF}_{\text{terminal}} LF = EF terminal (the project completion duration).
Late Start Calculation: LS = LF − Duration \text{LS} = \text{LF} - \text{Duration} LS = LF − Duration
Predecessor Activities: When an activity precedes multiple successors, its Late Finish is governed by the earliest starting successor: LF predecessor = min ( LS all successors ) \text{LF}_{\text{predecessor}} = \min(\text{LS}_{\text{all successors}}) LF predecessor = min ( LS all successors )
Float (Slack) Calculations
Float represents scheduling flexibility. The LARE tests three specific forms of float:
Float Type Formula Definition & Practical Impact
Total Float (TF) TF = LS − ES = LF − EF \text{TF} = \text{LS} - \text{ES} = \text{LF} - \text{EF} TF = LS − ES = LF − EF The maximum time an activity can be delayed from its Early Start without delaying the final project completion date.
Free Float (FF) FF = min ( ES successors ) − EF activity \text{FF} = \min(\text{ES}_{\text{successors}}) - \text{EF}_{\text{activity}} FF = min ( ES successors ) − EF activity The maximum time an activity can be delayed without delaying the Early Start of any immediate successor activity.
Interfering Float Interfering Float = TF − FF \text{Interfering Float} = \text{TF} - \text{FF} Interfering Float = TF − FF The portion of Total Float that, if utilized, will delay the early start of downstream successor tasks without delaying the final project completion date.
Defining the Critical Path
The Critical Path is the continuous sequence of dependent tasks through the network that possesses zero Total Float ( TF = 0 \text{TF} = 0 TF = 0 ) .
It represents the longest duration path through the project network.
Any delay to any activity on the critical path causes an identical, day-for-day delay to the overall project completion date.
A network may possess multiple concurrent critical paths. Furthermore, if a non-critical activity with 5 days of total float is delayed by 8 days, the critical path will shift , making that activity critical!
- 2. Scheduling Frameworks & Visual Tools
- Work Breakdown Structure (WBS)
Before establishing a schedule, project managers develop a Work Breakdown Structure (WBS) —a hierarchical, deliverable-oriented decomposition of the total project scope.
Hierarchy: Project ⟶ \longrightarrow ⟶ Phase (e.g., Design Development) ⟶ \longrightarrow ⟶ Sub-Phase / Work Package (e.g., Hardscape Detailing) ⟶ \longrightarrow ⟶ Individual Task / Activity (e.g., Detail CIP Concrete Steps).
The WBS establishes a coding structure (e.g., 1.3.2) used for resource allocation, fee tracking, and project accounting. It defines what is delivered, not the chronological sequence.
Gantt Charts vs. Network Diagrams
Gantt Charts (Bar Charts): Display activities along a horizontal calendar timescale. Excellent for visual communication with clients, tracking percent completion, and viewing resource overlaps. However, standard Gantt charts do not clearly illustrate complex dependency networks or automatically highlight how a non-critical slip impacts downstream logic.
Milestone Schedules: High-level executive summaries displaying major zero-duration achievement checkpoints (e.g., "50% DD Submittal," "Wetland Permit Approved," "Notice to Proceed," "Substantial Completion").
3. Project Phases & Design Fee Allocations
Landscape architectural design fees are distributed across standardized phases developed to align with traditional Design-Bid-Build project delivery (e.g., AIA B101):
Phase Standard Fee % Core Deliverables & Milestones Primary Coordination Focus
Pre-Design / Programming 5% - 10% (Often separate contract) Program requirements, spatial relationship diagrams, site analysis synthesis, regulatory zoning baseline. Client vision, user stakeholders, municipal planning staff.
Schematic Design (SD) 15% - 20% Alternative conceptual site layouts, circulation diagrams, character sketches, preliminary cost model ($/sq.ft.). Client review, overall spatial organization, massing.
Design Development (DD) 20% - 25% Scaled hardscape layout, precise grading profiles, typical construction details, material selections, plant palette, system assembly cost estimates. Civil engineer (stormwater tie-ins), structural engineer (retaining walls), architect (finish floor elevations).
Construction Documents (CD) 35% - 40% Full technical working drawings (demolition, layout, grading, utilities, planting, details) and project manual specifications. Permitting agencies, comprehensive interdisciplinary cross-checking, QA/QC review.
Bidding / Negotiation ~5% Pre-bid conference, issuing addenda, responding to bidder RFIs, bid opening, contractor qualification review. Prospective general contractors, sub-bidders, material suppliers.
Construction Administration (CA) 15% - 20% Submittal and shop drawing review, contractor RFIs, periodic site observations, change order review, punch lists, substantial completion. General contractor, owner's representative, testing agencies, building inspector.
4. Earned Value Management (EVM)
Earned Value Management (EVM) is an objective project performance measurement system that integrates scope, schedule, and cost metrics into a unified mathematical model. EVM answers three critical questions: Are we on schedule? Are we on budget? What is our true productivity?
The Core Triad
Planned Value (PV): The budgeted cost of work scheduled to be completed by a specific date: PV = Planned % Complete × BAC \text{PV} = \text{Planned } \% \text{ Complete} \times \text{BAC} PV = Planned % Complete × BAC (BAC = Budget at Completion)
Earned Value (EV): The budgeted value of work actually completed: EV = Actual % Complete × BAC \text{EV} = \text{Actual } \% \text{ Complete} \times \text{BAC} EV = Actual % Complete × BAC
Actual Cost (AC): The total expenditures, internal direct labor, and costs incurred in completing the work to date.
- Variance Formulas
- Schedule Variance (SV): SV = EV − PV \text{SV} = \text{EV} - \text{PV} SV = EV − PV
SV > 0 \text{SV} > 0 SV > 0 : Ahead of schedule.
SV < 0 \text{SV} < 0 SV < 0 : Behind schedule (work completed is less than planned).
SV = 0 \text{SV} = 0 SV = 0 : Exactly on schedule.
Cost Variance (CV): CV = EV − AC \text{CV} = \text{EV} - \text{AC} CV = EV − AC
CV > 0 \text{CV} > 0 CV > 0 : Under budget (work accomplished cost less than budgeted).
CV < 0 \text{CV} < 0 CV < 0 : Over budget (work accomplished cost more than budgeted).
CV = 0 \text{CV} = 0 CV = 0 : Exactly on budget.
Performance Indices
Schedule Performance Index (SPI): Measures schedule efficiency: SPI = EV PV \text{SPI} = \frac{\text{EV}}{\text{PV}} SPI = PV EV
SPI > 1.0 \text{SPI} > 1.0 SPI > 1.0 : Work is progressing faster than scheduled.
SPI < 1.0 \text{SPI} < 1.0 SPI < 1.0 : Work is progressing slower than scheduled.
Cost Performance Index (CPI): Measures financial and labor efficiency: CPI = EV AC \text{CPI} = \frac{\text{EV}}{\text{AC}} CPI = AC EV
CPI > 1.0 \text{CPI} > 1.0 CPI > 1.0 : Cost efficient; earning more value per dollar spent.
CPI < 1.0 \text{CPI} < 1.0 CPI < 1.0 : Cost inefficient; spending more money than budgeted value created.
5. Cost Estimating Across Project Phases
Cost estimating is not a single event; it is an iterative discipline whose level of detail and accuracy increases as design information matures.
Design Phase Estimating Methodology Typical Accuracy Range Basis of Calculation
Schematic Design (SD) Order of Magnitude / Parametric (Unit Area) ± 20 % to 30 % \pm 20\% \text{ to } 30\% ± 20% to 30% Historical square-foot costs ($/sq.ft. of permeable plaza), per-acre site development metrics, or per-stall parking costs.
Design Development (DD) System Assemblies / Elemental Costing ± 10 % to 15 % \pm 10\% \text{ to } 15\% ± 10% to 15% Major sub-system assemblies: linear feet of 6-ft CIP concrete retaining wall, square yards of unit pavers on aggregate base, total caliper-inches of canopy trees.
Construction Documents (CD) Detailed Unit Price / Quantity Takeoff ± 5 % to 10 % \pm 5\% \text{ to } 10\% ± 5% to 10% Granular, contractor-style itemized bills of quantities: cubic yards of unclassified excavation, tons of crushed aggregate, linear feet of conduit, square feet of turf sod, specific nursery stock counts.
Design Contingency vs. Construction Contingency
Candidates must strictly differentiate between these two budget reserves:
Design Contingency: An allowance established and controlled by the design team during the design phases (typically 15% to 20% in SD, reducing to 10% to 15% in DD, 5% in CD, and 0% at bid award). It accounts for evolving design details, unknown structural attachments, and unresolved code interpretations. As design details become finalized, the design contingency is steadily absorbed and eliminated.
Construction Contingency: A dedicated contingency fund (typically 5% to 10% of the bid amount) owned and controlled solely by the Owner during construction. It is reserved to cover unforeseen physical site conditions, concealed underground obstacles, contractor claims, and owner-requested scope modifications. The landscape architect cannot commit these funds without the owner's formal written Change Order.
6. Real-World Case Scenario: The Collapsing Float
Scenario: During the construction of a 15-acre regional park, the installation of the main stormwater bioretention cell is scheduled as a non-critical activity with an Early Start on Day 40, Early Finish on Day 55, and Late Finish on Day 75 (Total Float = 20 days). The planting of the emergent wetland vegetation within the basin has an Early Start of Day 56. On Day 42, the earthwork contractor strikes an unmapped buried utility line, shutting down basin excavation for 18 calendar days while the utility company relocates the line. The contractor claims this delay entitles them to an immediate 18-day extension of the overall project completion date.
Analysis & Resolution: The landscape architect reviews the CPM baseline network. The bioretention cell possessed 20 days of Total Float. An 18-day delay consumes 18 days of float, leaving 2 days of remaining Total Float ( 20 − 18 = 2 20 - 18 = 2 20 − 18 = 2 days). Because the activity still possesses 2 days of float, the overall project completion date is not delayed. Therefore, the contractor's claim for a time extension to the project completion date is invalid. However, the 18-day delay consumed all Free Float ( F F = 56 − 55 = 1 FF = 56 - 55 = 1 FF = 56 − 55 = 1 day), delaying the early start of the downstream planting subcontractor. The landscape architect must coordinate the successor tasks to ensure the new critical path does not slip past the remaining 2 days of float.
7. Exam Traps & Pitfalls
Total Float vs. Free Float Confusion: Total Float delay affects the project completion date; Free Float delay affects only the immediate successor task. An activity can have zero Free Float while still having significant Total Float!
Design vs. Construction Contingency Misapplication: If an owner demands that an unexpected rock excavation claim during construction be paid from the "design contingency," the candidate must identify that the design contingency was already closed out at bidding, and the cost must be paid from the owner's construction contingency.
SPI / CPI Interpretation Errors: An SPI of 0.85 does not mean the project is 85% complete; it means the project is progressing at only 85% of its planned velocity (behind schedule). A CPI of 1.15 means the project is earning $1.15 of value for every $1.00 spent (under budget).
CD Phase Fee Proportion: Candidates frequently underestimate the Construction Documents phase fee allocation. CD is the largest phase (35-40%), far surpassing Schematic Design (15-20%) or Design Development (20-25%).