2.10 ESA, Floodplain, Coastal & Historic Preservation Compliance

Landscape Architect Registration Examination L.A.R.E.

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: Project Management, Legal Framework & Contracts

1.1 Professional Practice, Ethics & the HSW Mandate 1.2 Standard of Care, Responsible Charge & Sealing Documents 1.3 Professional Services Agreements & Contract Clauses 1.4 Fee Structures, Compensation Models & Billing 1.5 Project Scheduling, CPM & Budget Management 1.6 Risk Management, Professional Liability & Insurance

2 Chapter 2: Site Inventory, Surveying & Regulatory Framework

2.1 Boundary Surveys, Legal Descriptions & Survey Datums 2.2 Topographic Surveys, Easements & Encumbrances 2.3 Desktop Inventory, GIS Data & Field Reconnaissance 2.4 Policy Documents & Prior Planning Studies 2.5 Adjacent Land Use & Contextual Data Collection 2.6 Stakeholder Engagement & Public Participation 2.7 Zoning Frameworks, Dimensional Standards & FAR 2.8 Parking Standards, Buffer Yards & Zoning Relief 2.9 Clean Water Act Permitting & NEPA Review 2.10 ESA, Floodplain, Coastal & Historic Preservation Compliance

3 Chapter 3: Physical, Contextual & Environmental Site Analysis

3.1 Scoping Site Analysis & Synthesizing Opportunities and Constraints 3.2 Geotechnical Investigation & Soil Classification Systems 3.3 Problematic Soil Conditions & Agronomic Soil Quality 3.4 Topographic Interpretation & Slope Suitability 3.5 Watershed Mechanics, Stream Order & FEMA Flood Hazard Zones 3.6 Wetland Delineation, Classification & Riparian Buffers 3.7 Utility Analysis & Infrastructure Capacity 3.8 Visual Resource & Viewshed Analysis 3.9 Contextual Analysis: Appropriate Use & Future Development Impacts 3.10 Microclimates, Solar Orientation & Vegetation Analysis

4 Chapter 4: Stewardship, Climate Resiliency & Design Principles

4.1 SITES v2 & LEED Site Credit Rating Systems 4.2 Life-Cycle Assessment, Embodied Carbon & Ecosystem Services 4.3 Climate Resiliency, Adaptation & Urban Heat Island Mitigation 4.4 Environmental Justice & Social Equity in Site Design 4.5 Cultural Landscapes, Historic Preservation & Adaptive Reuse

5 Chapter 5: Master Planning, Programming & Land Use

5.1 Project Visioning, Goal Setting & Space Programming 5.2 Carrying Capacity Analysis & NRPA Park Classification Standards 5.3 Site Suitability Synthesis & Opportunities/Constraints Mapping 5.4 Land Use Allocation & Development Scenario Evaluation 5.5 Master Plan Deliverables & Design Guidelines 5.6 Capital Improvement Programming, Phasing & Implementation

6 Chapter 6: Schematic Design & Spatial Organization

6.1 Design Intent, Conceptual Diagrams & Form Generation 6.2 Basis of Design, Alternatives Evaluation & the Preferred Scheme 6.3 Spatial Hierarchy, Outdoor Rooms & Proportion 6.4 Pedestrian Circulation Networks & Environmental Wayfinding 6.5 ADA & PROWAG Accessible Route Design 6.6 Multimodal Transportation, Vehicular Circulation & Parking Layout

7 Chapter 7: Design Development, Materials & Planting Systems

7.1 Paving Systems: Rigid, Flexible & Unit Pavers 7.2 Retaining Walls, Earth Pressure & Wall Drainage 7.3 Wall System Selection, Fences, Screens & Gates 7.4 Site Furnishings: Selection, Materiality & Anchoring 7.5 Exterior Lighting, Photometrics, Dark Sky & Electrical Safety 7.6 Public Playground Safety: CPSC & ASTM Standards 7.7 Planting Design Principles & Ecological Matching 7.8 Water Conservation, Xeriscaping & Irrigation System Principles 7.9 Opinions of Probable Cost & Value Engineering

8 Chapter 8: Construction Drawings, Layout & Detailing

8.1 Drawing Set Hierarchy, Sheet Standards & Drafting Conventions 8.2 Interdisciplinary Coordination & QA/QC Review 8.3 Demolition Plans & Tree Protection Requirements 8.4 Site Preparation: Clearing, Grubbing, Topsoil & Utility Abandonment 8.5 Layout, Dimensioning & Materials Plans 8.6 Planting Plans, Plant Schedules & Installation Details 8.7 Technical Detailing: Pavements, Curbs & Joint Assemblies 8.8 Retaining Wall, Stair & Ramp Detailing Standards

9 Chapter 9: Construction Specifications & Bidding

9.1 CSI MasterFormat Divisions & SectionFormat Structure 9.2 Specification Writing Methods & the Drawings–Specifications Relationship 9.3 Project Manual, General Conditions & Front-End Documents 9.4 Bid Requirements, Bid Forms & Addenda Management 9.5 Pre-Bid Procedures, Bid Opening & Contractor Evaluation

10 Chapter 10: Construction Administration, Submittals & Changes

10.1 Pre-Construction Conference & Construction Administration Authority 10.2 Initial Decision Maker, Communication Protocols & Project Records 10.3 Submittals, Shop Drawings, Product Data & Samples 10.4 Requests for Information (RFIs) & Technical Clarifications 10.5 Change Orders, Construction Change Directives & Claims

11 Chapter 11: Field Observation, Quality Control & Close-Out

11.1 Field Observations, Site Reports & Non-Conforming Work 11.2 Quality Control, Material Testing & Inspections 11.3 Substantial Completion, Punch Lists & Retainage 11.4 Project Close-Out, Guarantees, Warranties & Final Acceptance

12 Chapter 12: Contour Interpretation, Grading & Earthwork Calculations

12.1 Contour Rules & Topographic Landform Interpretation 12.2 Spot Elevations & Contour Interpolation Calculations 12.3 Slope Formulas, Maximum Gradients & Cross Slopes 12.4 Earthwork Calculations: Average End Area & Grid Methods 12.5 Cut and Fill Balancing, Shrinkage, Swell & Mass Haul 12.6 Reviewing Grading Design: Error Detection & Constructability

13 Chapter 13: Stormwater Hydrology, Runoff & BMP Design

13.1 Hydrologic Cycle, Watershed Delineation & Time of Concentration 13.2 Peak Runoff Estimation: The Rational Method (Q = CiA) 13.3 NRCS Curve Number Method & Runoff Hydrographs 13.4 LID Principles, Water Quality Volume & Bioretention Design 13.5 Bioswales, Permeable Pavement, Green Roofs & Harvesting

14 Chapter 14: Site Drainage Systems, Hydraulics & Erosion Control

14.1 Open Channel Hydraulics, Manning’s Equation & Swale Design 14.2 Gutter Flow, Spread & Roadway Inlet Hydraulics 14.3 Subsurface Drainage, Catch Basins & Pipe Invert Calculations 14.4 Stormwater Storage: Detention, Retention & Water Quality Basins 14.5 Reviewing Drainage Plans & Evaluating Design Alternatives 14.6 Erosion Mechanics, RUSLE & the NPDES/SWPPP Framework 14.7 Erosion & Sediment Control BMPs, Basins & Site Stabilization

2.10 ESA, Floodplain, Coastal & Historic Preservation Compliance

Key Takeaways Explain This Topic AI

Within FEMA regulatory floodways, proposed development or fill is strictly prohibited without an engineering hydraulic analysis ('No-Rise Certification') proving 0.00 feet of increase in Base Flood Elevations (BFE).

Section 106 of the National Historic Preservation Act (NHPA) compels federal agencies to evaluate and resolve adverse effects on historic properties through consultation with State and Tribal Historic Preservation Officers (SHPO/THPO).

Endangered Species Act Section 7 consultation applies when a federal agency action may affect a listed species, while Section 10 incidental take permits and Habitat Conservation Plans apply to purely private actions.

The Coastal Zone Management Act requires federal actions affecting a state's coastal zone to be consistent to the maximum extent practicable with the state's approved coastal management program.

Section 106 and NEPA are separate obligations that are often coordinated on one schedule; satisfying NEPA does not by itself satisfy Section 106 consultation.

Last updated: September 2026

Endangered Species Act (ESA) Compliance

The Endangered Species Act of 1973 (ESA) protects federally listed endangered (in danger of extinction throughout all or a significant portion of its range) and threatened (likely to become endangered in the foreseeable future) plant and animal species, as well as designated critical habitat .

Administering Agencies: The U.S. Fish and Wildlife Service (USFWS) oversees terrestrial and freshwater species; the National Marine Fisheries Service (NOAA Fisheries / NMFS) oversees marine species and anadromous fish (salmon, sturgeon).

Section 9 "Take" Prohibition: Makes it illegal for any person or entity to "take" an endangered animal species. "Take" is broadly defined to include harass, harm, pursue, hunt, shoot, wound, kill, trap, capture, or collect. Critical for landscape architects: "harm" includes significant habitat modification or degradation that impairs essential behavioral patterns, including breeding, feeding, or sheltering.

Section 7 Interagency Consultation (Federal Nexus): Mandatory whenever a project requires federal approval, funding, or permits (e.g., a USACE 404 permit or federal grant):

Informal Consultation: The applicant prepares a Biological Assessment (BA) . If USFWS/NMFS concurs that the action is "Not Likely to Adversely Affect" listed species, consultation concludes.

Formal Consultation: Triggered if the action "Is Likely to Adversely Affect" species. USFWS/NMFS issues a Biological Opinion (BiOp) detailing whether the action will jeopardize the species' existence. If no jeopardy is found, the BiOp includes an Incidental Take Statement specifying binding Reasonable and Prudent Measures (RPMs) (such as seasonal tree-clearing restrictions to protect roosting Indiana or Northern Long-Eared Bats).

Section 10 Incidental Take Permit (ITP): For non-federal private projects lacking a federal nexus. The private applicant must prepare a comprehensive Habitat Conservation Plan (HCP) that minimizes and mitigates the impacts of authorized incidental take.

Floodplain Management & FEMA NFIP Regulations

The Federal Emergency Management Agency (FEMA) administers the National Flood Insurance Program (NFIP) under federal regulations ( 44 CFR Part 60 ). Participating municipalities adopt local floodplain management ordinances that carry strict legal requirements for development.

The Anatomy of a Regulatory Floodplain

Base Flood: The flood having a 1% annual chance of being equaled or exceeded in any given year (commonly referred to as the 100-year flood ).

Base Flood Elevation (BFE): The computed water surface elevation of the base flood, referenced to NAVD88 on official FEMA Flood Insurance Rate Maps (FIRMs) . Regulatory Floodplain Cross-Section

  • |<------------------------- 100-Year Floodplain ------------------------->|
  • | |<------ Regulatory ------>| |
  • | Flood Fringe | Floodway | Flood Fringe |
  • | | | |
  • | (Development | (NO-RISE REQUIRED: | (Development |
  • | permitted if | Must not increase BFE | permitted if |
  • | elevated/fill) | by > 0.00 ft locally) | elevated/fill) |
  • |==================|~~~~~~~~~~~~~~~~~~~~~~~~~~|==========================|
  • | | ~~~~~~~~ River ~~~~~~ | |
  • | | ~~~~~~ Channel ~~~~~~ | |
  • +------------------+--------------------------+--------------------------+
  • |<--- SFHA Zone AE --->|<--- Regulatory --->|<------- SFHA Zone AE ------->|
  • The Regulatory Floodway vs. Flood Fringe

Regulatory Floodway: The channel of a river or stream and the adjacent land areas that must be reserved to discharge the base flood without cumulatively increasing the water surface elevation by more than a designated height (federally 1.0 foot, but 0.00 feet in most progressive local ordinances).

Flood Fringe: The portion of the 100-year floodplain outside the regulatory floodway. Development is permitted within the flood fringe provided all buildings have their lowest finished floor elevated at or above the BFE (plus local freeboard , typically +1 to +3 feet) and compensatory flood storage is excavated.

Exam Trap: The "No-Rise" Certification: Any proposed encroachment within the regulatory floodway—including fill, retaining walls, pavilions, boardwalk footings, or landscape re-grading—is strictly prohibited unless the landscape architect provides a No-Rise Certification . This engineering document requires detailed step-backwater hydraulic modeling (e.g., HEC-RAS ) proving that the proposed construction will cause 0.00 feet of increase in existing Base Flood Elevations during a 100-year flood event!

  • Coastal Zone Management & Historic Preservation
  • Coastal Zone Management Act (CZMA)

Enacted in 1972, the CZMA empowers coastal and Great Lakes states to develop state-specific Coastal Zone Management Programs overseen by NOAA. State acts (e.g., North Carolina's CAMA, California's Coastal Act):

Establish strict oceanfront setback lines based on long-term annual coastal erosion rates (e.g., setbacks equal to 30 to 60 times the annual shoreline erosion rate).

Enforce coastal estuarine shoreline buffers (e.g., 30- to 100-foot natural vegetative riparian zones where grading and clearing are restricted).

Protect public beach access corridors and regulate coastal shoreline hardening (seawalls, bulkheads).

Section 106 of the National Historic Preservation Act (NHPA)

Section 106 of the NHPA (1966) mandates that federal agencies account for the effects of their undertakings on historic properties listed on, or eligible for listing on, the National Register of Historic Places (NRHP) .

The Section 106 Process:

Initiate Consultation: Engage the State Historic Preservation Officer (SHPO) , Tribal Historic Preservation Officers (THPO), and local preservation boards.

Identify Historic Properties: Determine the Area of Potential Effects (APE) —encompassing direct physical disturbance and indirect visual, auditory, or atmospheric impacts—and survey historic buildings, archaeological sites, and cultural landscapes.

Assess Adverse Effects: An adverse effect occurs when an undertaking alters, directly or indirectly, the characteristics that qualify the property for the NRHP (e.g., introducing visual out-of-scale elements, cutting historic trees, altering historic grading).

Resolve Adverse Effects: The agency, SHPO/THPO, and applicant negotiate to avoid, minimize, or mitigate the adverse effect, executing a legally binding Memorandum of Agreement (MOA) that stipulates mitigation commitments (e.g., historic landscape salvage, interpretive signage, vegetative visual screening).

Comprehensive Environmental Permitting Matrix

Regulatory Statute Governing Agency Primary Permitting Trigger Mandated Application / Document Typical Approval Timeline

CWA Section 404 U.S. Army Corps of Engineers (USACE) Discharging dredged or fill material into jurisdictional wetlands or WOTUS Nationwide Permit (NWP) PCN or Individual Permit (IP) with 404(b)(1) LEDPA analysis NWP: 45–90 days; Individual Permit: 6–18 months

CWA Section 401 State Environmental Protection Agency Federal license/permit (e.g., 404 IP) causing potential water quality discharge State Water Quality Certification application with sediment/thermal modeling 60 days to 1 year (concurrent with 404)

CWA Section 402 Delegated State Environmental Agency / EPA Ground disturbance ≥ 1.0 acre from clearing, grading, or excavating Notice of Intent (NOI) for Construction General Permit (CGP) + written SWPPP 14–30 days prior to ground disturbance

NEPA Lead Federal Action Agency Project involving federal funding, federal land, or major federal license/permit Categorical Exclusion (CATEX), Environmental Assessment (EA), or EIS with ROD CATEX: 1–3 months; EA: 6–12 months; EIS: 1–3 years

ESA Section 7 US Fish & Wildlife Service (USFWS) / NMFS Federal project or permit that may affect listed endangered/threatened species Biological Assessment (BA) leading to Concurrence or formal Biological Opinion (BiOp) Informal: 30–60 days; Formal: 135 days

FEMA NFIP (44 CFR) Local Municipal Floodplain Administrator Development, grading, fill, or structures within a 100-year regulatory floodway Engineering No-Rise Certification backed by step-backwater HEC-RAS hydraulic models 60–120 days

NHPA Section 106 Advisory Council on Historic Preservation / SHPO Federal undertaking with potential direct or visual effect on NRHP-eligible sites Section 106 Assessment of Effect report; Memorandum of Agreement (MOA) for mitigation 60 days to 6 months