7.1 Paving Systems: Rigid, Flexible & Unit Pavers
Landscape Architect Registration Examination L.A.R.E.
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Project Management, Legal Framework & Contracts
1.1 Professional Practice, Ethics & the HSW Mandate 1.2 Standard of Care, Responsible Charge & Sealing Documents 1.3 Professional Services Agreements & Contract Clauses 1.4 Fee Structures, Compensation Models & Billing 1.5 Project Scheduling, CPM & Budget Management 1.6 Risk Management, Professional Liability & Insurance
2 Chapter 2: Site Inventory, Surveying & Regulatory Framework
2.1 Boundary Surveys, Legal Descriptions & Survey Datums 2.2 Topographic Surveys, Easements & Encumbrances 2.3 Desktop Inventory, GIS Data & Field Reconnaissance 2.4 Policy Documents & Prior Planning Studies 2.5 Adjacent Land Use & Contextual Data Collection 2.6 Stakeholder Engagement & Public Participation 2.7 Zoning Frameworks, Dimensional Standards & FAR 2.8 Parking Standards, Buffer Yards & Zoning Relief 2.9 Clean Water Act Permitting & NEPA Review 2.10 ESA, Floodplain, Coastal & Historic Preservation Compliance
3 Chapter 3: Physical, Contextual & Environmental Site Analysis
3.1 Scoping Site Analysis & Synthesizing Opportunities and Constraints 3.2 Geotechnical Investigation & Soil Classification Systems 3.3 Problematic Soil Conditions & Agronomic Soil Quality 3.4 Topographic Interpretation & Slope Suitability 3.5 Watershed Mechanics, Stream Order & FEMA Flood Hazard Zones 3.6 Wetland Delineation, Classification & Riparian Buffers 3.7 Utility Analysis & Infrastructure Capacity 3.8 Visual Resource & Viewshed Analysis 3.9 Contextual Analysis: Appropriate Use & Future Development Impacts 3.10 Microclimates, Solar Orientation & Vegetation Analysis
4 Chapter 4: Stewardship, Climate Resiliency & Design Principles
4.1 SITES v2 & LEED Site Credit Rating Systems 4.2 Life-Cycle Assessment, Embodied Carbon & Ecosystem Services 4.3 Climate Resiliency, Adaptation & Urban Heat Island Mitigation 4.4 Environmental Justice & Social Equity in Site Design 4.5 Cultural Landscapes, Historic Preservation & Adaptive Reuse
5 Chapter 5: Master Planning, Programming & Land Use
5.1 Project Visioning, Goal Setting & Space Programming 5.2 Carrying Capacity Analysis & NRPA Park Classification Standards 5.3 Site Suitability Synthesis & Opportunities/Constraints Mapping 5.4 Land Use Allocation & Development Scenario Evaluation 5.5 Master Plan Deliverables & Design Guidelines 5.6 Capital Improvement Programming, Phasing & Implementation
6 Chapter 6: Schematic Design & Spatial Organization
6.1 Design Intent, Conceptual Diagrams & Form Generation 6.2 Basis of Design, Alternatives Evaluation & the Preferred Scheme 6.3 Spatial Hierarchy, Outdoor Rooms & Proportion 6.4 Pedestrian Circulation Networks & Environmental Wayfinding 6.5 ADA & PROWAG Accessible Route Design 6.6 Multimodal Transportation, Vehicular Circulation & Parking Layout
7 Chapter 7: Design Development, Materials & Planting Systems
7.1 Paving Systems: Rigid, Flexible & Unit Pavers 7.2 Retaining Walls, Earth Pressure & Wall Drainage 7.3 Wall System Selection, Fences, Screens & Gates 7.4 Site Furnishings: Selection, Materiality & Anchoring 7.5 Exterior Lighting, Photometrics, Dark Sky & Electrical Safety 7.6 Public Playground Safety: CPSC & ASTM Standards 7.7 Planting Design Principles & Ecological Matching 7.8 Water Conservation, Xeriscaping & Irrigation System Principles 7.9 Opinions of Probable Cost & Value Engineering
8 Chapter 8: Construction Drawings, Layout & Detailing
8.1 Drawing Set Hierarchy, Sheet Standards & Drafting Conventions 8.2 Interdisciplinary Coordination & QA/QC Review 8.3 Demolition Plans & Tree Protection Requirements 8.4 Site Preparation: Clearing, Grubbing, Topsoil & Utility Abandonment 8.5 Layout, Dimensioning & Materials Plans 8.6 Planting Plans, Plant Schedules & Installation Details 8.7 Technical Detailing: Pavements, Curbs & Joint Assemblies 8.8 Retaining Wall, Stair & Ramp Detailing Standards
9 Chapter 9: Construction Specifications & Bidding
9.1 CSI MasterFormat Divisions & SectionFormat Structure 9.2 Specification Writing Methods & the Drawings–Specifications Relationship 9.3 Project Manual, General Conditions & Front-End Documents 9.4 Bid Requirements, Bid Forms & Addenda Management 9.5 Pre-Bid Procedures, Bid Opening & Contractor Evaluation
10 Chapter 10: Construction Administration, Submittals & Changes
10.1 Pre-Construction Conference & Construction Administration Authority 10.2 Initial Decision Maker, Communication Protocols & Project Records 10.3 Submittals, Shop Drawings, Product Data & Samples 10.4 Requests for Information (RFIs) & Technical Clarifications 10.5 Change Orders, Construction Change Directives & Claims
11 Chapter 11: Field Observation, Quality Control & Close-Out
11.1 Field Observations, Site Reports & Non-Conforming Work 11.2 Quality Control, Material Testing & Inspections 11.3 Substantial Completion, Punch Lists & Retainage 11.4 Project Close-Out, Guarantees, Warranties & Final Acceptance
12 Chapter 12: Contour Interpretation, Grading & Earthwork Calculations
12.1 Contour Rules & Topographic Landform Interpretation 12.2 Spot Elevations & Contour Interpolation Calculations 12.3 Slope Formulas, Maximum Gradients & Cross Slopes 12.4 Earthwork Calculations: Average End Area & Grid Methods 12.5 Cut and Fill Balancing, Shrinkage, Swell & Mass Haul 12.6 Reviewing Grading Design: Error Detection & Constructability
13 Chapter 13: Stormwater Hydrology, Runoff & BMP Design
13.1 Hydrologic Cycle, Watershed Delineation & Time of Concentration 13.2 Peak Runoff Estimation: The Rational Method (Q = CiA) 13.3 NRCS Curve Number Method & Runoff Hydrographs 13.4 LID Principles, Water Quality Volume & Bioretention Design 13.5 Bioswales, Permeable Pavement, Green Roofs & Harvesting
14 Chapter 14: Site Drainage Systems, Hydraulics & Erosion Control
14.1 Open Channel Hydraulics, Manning’s Equation & Swale Design 14.2 Gutter Flow, Spread & Roadway Inlet Hydraulics 14.3 Subsurface Drainage, Catch Basins & Pipe Invert Calculations 14.4 Stormwater Storage: Detention, Retention & Water Quality Basins 14.5 Reviewing Drainage Plans & Evaluating Design Alternatives 14.6 Erosion Mechanics, RUSLE & the NPDES/SWPPP Framework 14.7 Erosion & Sediment Control BMPs, Basins & Site Stabilization
7.1 Paving Systems: Rigid, Flexible & Unit Pavers
Key Takeaways Explain This Topic AI
Rigid concrete pavement distributes load through beam action in the slab, while flexible asphalt pavement distributes load through the aggregate base, which is why base failure shows up immediately in asphalt.
A lower water-cement ratio (roughly 0.40 to 0.45) raises compressive strength, lowers permeability, and improves freeze-thaw and abrasion resistance, while excess mix water causes drying shrinkage, cracking, and surface dusting.
Concrete slabs require three distinct joint types: control (contraction) joints to induce cracking on a planned line, expansion (isolation) joints at fixed objects, and construction joints at pour stops.
Control joints must be cut to at least one quarter of slab thickness and spaced at roughly two to three times the slab thickness in inches converted to feet, and must be cut within the first 24 hours.
Flexible-set unit pavers require a continuous edge restraint, because without it the field creeps laterally under traffic and the joints open progressively from the perimeter inward.
Last updated: September 2026
Core Focus: The Design Development subdomain represents 22% of scored items on LARE Section 2 (Planning and Design). Candidates must demonstrate comprehensive mastery of paving systems (rigid, flexible, and unit), retaining wall engineering, lateral earth pressure dynamics, subsurface drainage, and structural failure modes.
1. Rigid Pavement Systems: Cast-in-Place Concrete
Cast-in-place (CIP) concrete is a rigid pavement system characterized by its high compressive strength, durability, and capacity to bridge minor subgrade deficiencies through beam action. Unlike flexible pavements that transfer wheel loads directly to the base course via localized aggregate interlock, rigid slabs distribute concentrated wheel and pedestrian loads across a broad slab area.
Concrete Mix Design & Engineering Properties
Compressive Strength ( f ′ c f'c f ′ c ): Specified in pounds per square inch (psi) cured at 28 days (ASTM C39). Pedestrian pathways and residential sidewalks typically specify 3,000 to 3,500 psi. Heavy urban pedestrian plazas, commercial driveways, and light vehicular fire lanes require 4,000 to 4,500 psi. Heavy municipal transit lanes, loading docks, and severe freeze-thaw applications require 5,000+ psi.
Water-Cement Ratio (w/c): The ratio of water weight to cementitious materials weight. A lower w/c ratio (0.40 to 0.45) significantly increases final compressive strength, lowers permeability, and improves abrasion and freeze-thaw resistance. Excess water elevates workability temporarily but drastically increases drying shrinkage, porosity, cracking, and surface dusting.
Air Entrainment: Concrete exposed to freeze-thaw cycles must incorporate microscopic, spherical air voids (ASTM C260) representing 4.0% to 7.0% of total concrete volume (depending on maximum coarse aggregate size). As absorbed water freezes within capillary pores, it expands by approximately 9%; entrained air voids act as pressure relief chambers, preventing internal hydraulic shattering. Air entrainment also improves workability without requiring additional water.
Slump Test (ASTM C143): Measures the consistency and workability of freshly mixed batch concrete using a 12-inch hollow slump cone. Typical specification for flatwork is a 3- to 4-inch slump (or up to 5 inches for lightly reinforced slabs). A slump exceeding 6 inches without superplasticizers indicates excessive batch water, resulting in weak, segregation-prone concrete. Slump Test Verification (ASTM C143)
- |--- 4" Top ---|
- | |
- / \ 12" High Mold
- / \ (Filled in 3 equal layers, rodded 25x each)
- / \
- / \
- |------- 8" Base ------|
- === Lift Cone ===
- [ Concrete ] <--- Measure slump (inches of drop)
- Concrete Jointing Mechanics
Uncontrolled concrete cracking is caused by tensile stresses developed during drying shrinkage (concrete shrinks roughly 1/16 inch per 10 linear feet as free moisture evaporates) and temperature fluctuations. Three distinct joint types must be detailed on site development plans:
1. Control / Contraction Joints
Function: Induce controlled cracking along a predetermined, weakened plane rather than allowing random, jagged shrinkage cracks across the slab surface.
Depth: Must be cut or grooved to a depth of at least 1/4 of the slab thickness ( D / 4 D/4 D /4 ) or a minimum of 1 inch (e.g., a 4-inch slab requires a 1-inch joint; a 6-inch slab requires a 1.5-inch joint).
Spacing Rule: Maximum joint spacing in feet must not exceed 2 to 3 times the slab thickness in inches (often expressed as 24 to 36 times slab thickness). For a 4-inch slab: 4 × 2 = 8 ft 4 \times 2 = 8\text{ ft} 4 × 2 = 8 ft to 4 × 3 = 12 ft 4 \times 3 = 12\text{ ft} 4 × 3 = 12 ft . For a 6-inch slab: 12 to 18 ft maximum. Slabs should be divided into square or near-square panels (length-to-width aspect ratio should never exceed 1.25:1 to 1.5:1; L-shaped panels must be avoided).
Timing: Tooled joints are formed with a groover during initial finishing. Saw-cut joints must be cut as soon as the concrete can support foot traffic without ravelling or dislodging aggregate—typically 4 to 12 hours after pour in warm weather, and never delayed beyond 24 hours.
2. Expansion / Isolation Joints
Function: Provide complete physical separation through the full depth of the slab to accommodate thermal expansion and isolate the pavement from immovable vertical structures (foundations, columns, catch basins, steps, retaining walls).
Detail: Full-depth, compressible filler material (such as asphalt-impregnated fiberboard, closed-cell polyethylene foam, or cork) typically 1/2 inch thick, recessed 1/2 inch below the surface and capped with an elastomeric polyurethane or polysulfide joint sealant.
Placement: Placed at all junctions where flatwork abuts rigid walls or curbs, at right-angle walk intersections, and at maximum intervals of 30 to 50 feet in continuous linear sidewalks.
3. Construction Joints
Function: Established where concrete placement operations conclude for the day or where adjoining pours are staged sequentially.
Detail: Keyed joints or smooth, greased steel slip dowels that allow horizontal contraction and expansion while preventing vertical shear displacement (faulting) across the pour interface.
Architectural Concrete Finishes
Finish Type Installation Technique Slip Resistance & Texture Typical Applications
Broom Finish Dragging a damp horsehair or synthetic broom transversely across newly floated/troweled slab before curing. Medium to high traction; meets ADA static coefficient of friction (SCOF >= 0.60). Standard urban sidewalks, accessible ramps, perimeter pathways.
Exposed Aggregate Spraying surface retarder immediately after screeding, then pressure washing/scrubbing cement paste within 12–24 hours to expose 1/8" to 3/8" stone. Excellent rough texture and traction; highly durable against surface abrasion. Civic plazas, feature crosswalks, park gathering nodes.
Stamped / Patterned Imprinting elastomeric texture mats into plastic concrete treated with color powder release agents. Variable; high-gloss acrylic sealers can become dangerously slippery when wet without non-skid additives. Decorative courtyard accents, pedestrian entry aprons.
Acid-Etched / Sandblasted Applying muriatic acid solution or abrasive blasting after full 28-day cure to lightly remove surface cream. Uniform, matte, stone-like texture; reveals fine sand matrix without exposing coarse stone. High-end institutional plazas, architectural retaining wall faces.
2. Flexible Pavement Systems: Asphaltic Concrete
Unlike rigid concrete slabs, asphalt is a flexible pavement system. It possesses minimal tensile strength, relying on layered aggregate shear resistance to distribute surface wheel loads downward to the natural subgrade soil. Standard Commercial Asphalt Pavement Cross-Section
- =======================================================
- | Surface Wear Course (1.5" - 2.0" Dense-Graded AC) |
- |-----------------------------------------------------|
- | Asphalt Binder Course (2.0" - 3.0" Coarse AC) |
- |-----------------------------------------------------|
- | Crushed Aggregate Base (CAB) (6.0" - 10.0" Crushed) |
- |-----------------------------------------------------|
- | Compacted Subgrade (95% Modified Proctor Density) |
- =======================================================
- Layered Pavement Cross-Section
Subgrade Preparation: The native soil bed excavated and compacted to 95% Modified Proctor density (ASTM D1557) . Soft, high-plasticity clay subgrades may require lime or Portland cement stabilization, or geotextile separation fabrics.
Crushed Aggregate Base (CAB): A dense-graded layer of crushed stone (typically 3/4-inch minus with balanced fines) compacted in lifts of 4 to 6 inches. Thickness ranges from 4 to 6 inches for light vehicular/parking stalls up to 8 to 12 inches for heavy truck lanes and bus turnouts .
Asphalt Binder Course (Base Course): Hot-mix asphalt (HMA) utilizing larger aggregates (3/4" to 1" nominal size) providing structural load-bearing capacity (typically 2 to 3 inches thick).
Asphalt Surface / Wear Course: A dense-graded, fine-aggregate HMA wearing layer (typically 1.5 to 2 inches thick) providing a smooth, skid-resistant, water-shedding riding surface.
Engineering Strengths & Vulnerabilities
Strengths: Lower initial installation cost than concrete; seamless surface; flexible adaptation to minor subgrade settling; quick return to traffic (hours vs. 7–28 days for concrete).
Vulnerabilities: Susceptible to chemical softening and dissolution from gasoline, oil, and diesel spills; subject to rutting and depression under prolonged static loads (such as parked dumpsters or bus idling stops); requires periodic sealcoating every 3 to 5 years and structural milling/resurfacing every 15 to 20 years.
3. Unit Paving Systems & Setting Beds
Unit paving systems utilize modular manufactured units (concrete pavers, extruded or molded clay bricks, natural stone slabs, or granite setts) laid in geometric bonding patterns (herringbone, running bond, basketweave, stack bond).
Setting Bed Typologies
Sand-Set (Flexible Assembly): Pavers installed over a 1-inch uniform layer of uncompacted, sharp, washed concrete sand (ASTM C33) resting on a compacted crushed aggregate base (ASTM D2940). Joints are filled with dry silica or polymeric sand swept into joints and vibrated into place with a plate compactor. Advantages: Accommodates minor freeze-thaw movement without cracking; 100% salvageable when accessing underground utilities.
Bituminous-Set (Semi-Rigid Assembly): Pavers installed over a 3/4-inch layer of neoprene-modified asphalt adhesive screeded over a cured concrete base slab, primed with asphalt primer. Joints are filled with polymeric sand or stone dust. Advantages: Provides high shear strength and resistance to horizontal braking/turning forces; the standard for high-traffic municipal streetscapes and urban bus loading aprons.
Mortar-Set (Rigid Assembly): Pavers installed over a 1/2- to 1-inch thick cementitious mortar bed (Type M or Type S) supported by a reinforced concrete slab, with joints grouted with mortar. Vulnerabilities: Rigid and unyielding; any subgrade settlement or freeze-thaw expansion cracks the joints; trapped moisture beneath units leads to severe efflorescence, spalling, and debonding in freezing climates. SAND-SET (FLEXIBLE) BITUMINOUS-SET (SEMI-RIGID)
- +-------------------------------+ +-------------------------------+
- | Modular Pavers (ASTM C936) | | Modular Pavers (ASTM C936) |
- +-------------------------------+ +-------------------------------+
- | 1" Washed Sand (ASTM C33) | | 3/4" Neoprene-Modified Bitumen|
- +-------------------------------+ +-------------------------------+
- | Compacted Aggregate Base | | Reinforced Concrete Slab Base |
- +-------------------------------+ +-------------------------------+
- | Compacted Subgrade | | Compacted Aggregate Subbase |
- +-------------------------------+ +-------------------------------+
- The Critical Role of Edge Restraints
Without rigid edge restraints, unit paver installations inevitably fail through lateral creep —traffic loads push the perimeter units outward, opening joint spaces, destroying aggregate interlock, and allowing water to infiltrate and wash away the bedding sand. Acceptable edge restraints include:
Poured cast-in-place concrete curbs or flush concrete header ribbons.
Troweled concrete toe encasements (submerged concrete haunches) extending down into the base course.
Heavy-duty commercial steel or aluminum edging secured with 10- to 12-inch steel spikes driven directly into the compacted aggregate base (never driven into loose topsoil).
Permeable Interlocking Concrete Pavers (PICP)
PICP systems function as on-site stormwater infiltration systems. Paver units have specialized spacer lugs creating open joints (typically 8% to 12% surface void ratio). Sand bedding and joint sand are strictly prohibited because fine sand clogs and seals voids. Instead, the assembly uses washed, open-graded crushed aggregate :
Joint fill and 2-inch setting bed: ASTM No. 8 or No. 89 stone (1/4" to 3/8" crushed chip stone).
Base reservoir course: ASTM No. 57 crushed stone (4 inches thick).
Subbase detention reservoir: ASTM No. 2 crushed stone (6 to 18 inches thick, providing 30% to 40% void storage space for runoff).