10.4 Requests for Information (RFIs) & Technical Clarifications
Landscape Architect Registration Examination L.A.R.E.
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Project Management, Legal Framework & Contracts
1.1 Professional Practice, Ethics & the HSW Mandate 1.2 Standard of Care, Responsible Charge & Sealing Documents 1.3 Professional Services Agreements & Contract Clauses 1.4 Fee Structures, Compensation Models & Billing 1.5 Project Scheduling, CPM & Budget Management 1.6 Risk Management, Professional Liability & Insurance
2 Chapter 2: Site Inventory, Surveying & Regulatory Framework
2.1 Boundary Surveys, Legal Descriptions & Survey Datums 2.2 Topographic Surveys, Easements & Encumbrances 2.3 Desktop Inventory, GIS Data & Field Reconnaissance 2.4 Policy Documents & Prior Planning Studies 2.5 Adjacent Land Use & Contextual Data Collection 2.6 Stakeholder Engagement & Public Participation 2.7 Zoning Frameworks, Dimensional Standards & FAR 2.8 Parking Standards, Buffer Yards & Zoning Relief 2.9 Clean Water Act Permitting & NEPA Review 2.10 ESA, Floodplain, Coastal & Historic Preservation Compliance
3 Chapter 3: Physical, Contextual & Environmental Site Analysis
3.1 Scoping Site Analysis & Synthesizing Opportunities and Constraints 3.2 Geotechnical Investigation & Soil Classification Systems 3.3 Problematic Soil Conditions & Agronomic Soil Quality 3.4 Topographic Interpretation & Slope Suitability 3.5 Watershed Mechanics, Stream Order & FEMA Flood Hazard Zones 3.6 Wetland Delineation, Classification & Riparian Buffers 3.7 Utility Analysis & Infrastructure Capacity 3.8 Visual Resource & Viewshed Analysis 3.9 Contextual Analysis: Appropriate Use & Future Development Impacts 3.10 Microclimates, Solar Orientation & Vegetation Analysis
4 Chapter 4: Stewardship, Climate Resiliency & Design Principles
4.1 SITES v2 & LEED Site Credit Rating Systems 4.2 Life-Cycle Assessment, Embodied Carbon & Ecosystem Services 4.3 Climate Resiliency, Adaptation & Urban Heat Island Mitigation 4.4 Environmental Justice & Social Equity in Site Design 4.5 Cultural Landscapes, Historic Preservation & Adaptive Reuse
5 Chapter 5: Master Planning, Programming & Land Use
5.1 Project Visioning, Goal Setting & Space Programming 5.2 Carrying Capacity Analysis & NRPA Park Classification Standards 5.3 Site Suitability Synthesis & Opportunities/Constraints Mapping 5.4 Land Use Allocation & Development Scenario Evaluation 5.5 Master Plan Deliverables & Design Guidelines 5.6 Capital Improvement Programming, Phasing & Implementation
6 Chapter 6: Schematic Design & Spatial Organization
6.1 Design Intent, Conceptual Diagrams & Form Generation 6.2 Basis of Design, Alternatives Evaluation & the Preferred Scheme 6.3 Spatial Hierarchy, Outdoor Rooms & Proportion 6.4 Pedestrian Circulation Networks & Environmental Wayfinding 6.5 ADA & PROWAG Accessible Route Design 6.6 Multimodal Transportation, Vehicular Circulation & Parking Layout
7 Chapter 7: Design Development, Materials & Planting Systems
7.1 Paving Systems: Rigid, Flexible & Unit Pavers 7.2 Retaining Walls, Earth Pressure & Wall Drainage 7.3 Wall System Selection, Fences, Screens & Gates 7.4 Site Furnishings: Selection, Materiality & Anchoring 7.5 Exterior Lighting, Photometrics, Dark Sky & Electrical Safety 7.6 Public Playground Safety: CPSC & ASTM Standards 7.7 Planting Design Principles & Ecological Matching 7.8 Water Conservation, Xeriscaping & Irrigation System Principles 7.9 Opinions of Probable Cost & Value Engineering
8 Chapter 8: Construction Drawings, Layout & Detailing
8.1 Drawing Set Hierarchy, Sheet Standards & Drafting Conventions 8.2 Interdisciplinary Coordination & QA/QC Review 8.3 Demolition Plans & Tree Protection Requirements 8.4 Site Preparation: Clearing, Grubbing, Topsoil & Utility Abandonment 8.5 Layout, Dimensioning & Materials Plans 8.6 Planting Plans, Plant Schedules & Installation Details 8.7 Technical Detailing: Pavements, Curbs & Joint Assemblies 8.8 Retaining Wall, Stair & Ramp Detailing Standards
9 Chapter 9: Construction Specifications & Bidding
9.1 CSI MasterFormat Divisions & SectionFormat Structure 9.2 Specification Writing Methods & the Drawings–Specifications Relationship 9.3 Project Manual, General Conditions & Front-End Documents 9.4 Bid Requirements, Bid Forms & Addenda Management 9.5 Pre-Bid Procedures, Bid Opening & Contractor Evaluation
10 Chapter 10: Construction Administration, Submittals & Changes
10.1 Pre-Construction Conference & Construction Administration Authority 10.2 Initial Decision Maker, Communication Protocols & Project Records 10.3 Submittals, Shop Drawings, Product Data & Samples 10.4 Requests for Information (RFIs) & Technical Clarifications 10.5 Change Orders, Construction Change Directives & Claims
11 Chapter 11: Field Observation, Quality Control & Close-Out
11.1 Field Observations, Site Reports & Non-Conforming Work 11.2 Quality Control, Material Testing & Inspections 11.3 Substantial Completion, Punch Lists & Retainage 11.4 Project Close-Out, Guarantees, Warranties & Final Acceptance
12 Chapter 12: Contour Interpretation, Grading & Earthwork Calculations
12.1 Contour Rules & Topographic Landform Interpretation 12.2 Spot Elevations & Contour Interpolation Calculations 12.3 Slope Formulas, Maximum Gradients & Cross Slopes 12.4 Earthwork Calculations: Average End Area & Grid Methods 12.5 Cut and Fill Balancing, Shrinkage, Swell & Mass Haul 12.6 Reviewing Grading Design: Error Detection & Constructability
13 Chapter 13: Stormwater Hydrology, Runoff & BMP Design
13.1 Hydrologic Cycle, Watershed Delineation & Time of Concentration 13.2 Peak Runoff Estimation: The Rational Method (Q = CiA) 13.3 NRCS Curve Number Method & Runoff Hydrographs 13.4 LID Principles, Water Quality Volume & Bioretention Design 13.5 Bioswales, Permeable Pavement, Green Roofs & Harvesting
14 Chapter 14: Site Drainage Systems, Hydraulics & Erosion Control
14.1 Open Channel Hydraulics, Manning’s Equation & Swale Design 14.2 Gutter Flow, Spread & Roadway Inlet Hydraulics 14.3 Subsurface Drainage, Catch Basins & Pipe Invert Calculations 14.4 Stormwater Storage: Detention, Retention & Water Quality Basins 14.5 Reviewing Drainage Plans & Evaluating Design Alternatives 14.6 Erosion Mechanics, RUSLE & the NPDES/SWPPP Framework 14.7 Erosion & Sediment Control BMPs, Basins & Site Stabilization
10.4 Requests for Information (RFIs) & Technical Clarifications
Key Takeaways Explain This Topic AI
A Request for Information (RFI) is a formal administrative instrument used by the contractor to seek interpretation or clarification of perceived ambiguities, conflicts, or omissions in Contract Documents.
Under modern contracts and Division 01 General Requirements, contractors must thoroughly coordinate contract documents and include a specific proposed solution on every RFI submitted.
Legitimate RFI uses include resolving drawing-specification conflicts and clarifying unforeseen site conditions; improper misuses include attempting product substitutions or seeking answers already clearly detailed in contract drawings.
An Architect's Supplemental Instruction (ASI / AIA Document G710) is a unilateral written order issued by the Landscape Architect directing minor changes in the work that do NOT adjust Contract Sum or Contract Time.
If a contractor believes an ASI causes an increase in cost or schedule duration, the contractor must not proceed under the ASI and must submit written notice of a claim within 21 days under AIA A201 Section 15.1.3.
Last updated: September 2026
Core Focus: Clarifications and interpretations are daily occurrences during construction administration. The LARE Section 3 exam tests candidates on the formal mechanics of Requests for Information (RFIs), recognizing acceptable versus abusive RFI practices, utilizing Architect's Supplemental Instructions (ASIs / AIA G710) for minor changes, and managing technical clarifications without unintentionally altering contract cost or time.
1. Purpose and Mechanics of Requests for Information (RFIs)
A Request for Information (RFI) is a formal written administrative communication initiated by the General Contractor to obtain professional interpretation, technical clarification, or resolution regarding perceived ambiguities, discrepancies, conflicts, or omissions within the Contract Documents (AIA Document A201 Section 3.2). +--------------------------------------------------------------------------+
- | STANDARD RFI LIFECYCLE |
- +--------------------------------------------------------------------------+
- | Subcontractor / GC identifies field ambiguity or document discrepancy |
- | │ |
- | ▼ |
- | General Contractor conducts internal document review: |
- | ├─ Checks all drawings, details, schedules, and specification sections |
- | ├─ Formulates contractor's recommended solution |
- | └─ Completes formal RFI Form with exact sheet/spec references |
- | │ |
- | ▼ |
- | Landscape Architect receives RFI & logs into tracking system |
- | │ |
- | ├────────────────────────────────────────┐ |
- | ▼ (Legitimate Inquiry) ▼ (Frivolous / Clear) |
- | Landscape Architect Evaluates Issue REJECTED / RETURNED |
- | ├─ Coordinates with Subconsultant "Information clearly |
- | │ (Civil, Structural, Irrigation) detailed on Sheet L-502, |
- | └─ Formulates written/graphic response Detail 3. No change." |
- | │ |
- | ▼ |
- | Landscape Architect issues formal written response within contractual |
- | timeframe (e.g., 7–14 calendar days) |
- | │ |
- | ├────────────────────────────────────────┐ |
- | ▼ (Zero Cost/Time Impact) ▼ (Cost/Time Impact) |
- | Work proceeds per clarification Proposal Request (PR) or |
- | (or ASI issued if minor graphic change) Construction Change Directive|
- +--------------------------------------------------------------------------+
- The Standard RFI Form Architecture
A legally robust RFI form must contain specific standardized fields:
Unique Tracking Number: Sequential alphanumeric code (e.g., RFI-042 ).
Date Submitted & Required Response Date: Establishes contractual review windows.
Originator & Trade: General Contractor contact and originating subcontractor.
Contract Document References: Exact drawing sheet numbers, detail references, and MasterFormat specification section and paragraph numbers.
Description of Issue / Ambiguity: Clear, concise statement of the perceived conflict or condition.
Contractor's Proposed Solution: Under standard Division 01 requirements, the contractor is required to provide a recommended solution . This prevents contractors from passively dumping field coordination problems onto the design team.
Contractor's Assessment of Impact: Checkboxes indicating whether the contractor believes the inquiry impacts Contract Sum (Cost) or Contract Time (Schedule).
Landscape Architect's Formal Response: Clear technical directive, often accompanied by supplemental sketches (SKL sheets).
Design Signature & Date Returned: Formal closure of the inquiry.
2. Acceptable RFI Uses vs. Process Abuse
Understanding the boundary between legitimate technical inquiries and improper RFI submissions is critical for construction administration and LARE questions. RFI EVALUATION MATRIX
- │
- +---------------------------------+---------------------------------+
- │ │
- ACCEPTABLE / LEGITIMATE USES PROCESS MISUSE / ABUSE
- ├─ Resolving drawing vs. spec conflicts ├─ Submitting unapproved substitutions
- ├─ Clarifying unforeseen site conditions ├─ Asking questions answered on drawings
- ├─ Addressing uncoordinated utility crossings ├─ Shifting trade coordination to designer
- └─ Requesting missing geometric control points └─ Manufacturing paper trails for delay claims
- Acceptable and Legitimate Uses of RFIs
Resolving Inherent Document Conflicts: Reconciling discrepancies where drawings and specifications disagree (e.g., Sheet L-102 calls for 60mm unit pavers, while Specification Section 32 14 00 specifies 80mm vehicular pavers).
Unforeseen or Differing Site Conditions: Clarifying how to proceed when field excavation reveals an undocumented abandoned utility vault or high groundwater table not indicated in geotechnical boring logs.
Dimensional or Geometric Ambiguities: Inquiring about missing spot elevations, conflicting curb radii, or irregular property boundary coordinate intersections.
Inter-Disciplinary Design Conflicts: Highlighting spatial clashes between different engineering disciplines (e.g., an irrigation mainline conflicting with a civil storm drainage pipe elevation).
Misuse and Abuse of the RFI Process
Bypassing the Substitution Protocol: Contractors frequently attempt to use an RFI to submit an alternative, cheaper product (e.g., "Manufacturer X cannot deliver the specified benches in 6 weeks; can we use Manufacturer Y?"). This is an administrative violation. Substitutions must follow formal Division 01 substitution procedures , including proof of equivalency, cost credits, and warranty verifications.
The "Nuisance" or "Frivolous" RFI: Submitting RFIs for information that is plainly and clearly shown on the Contract Documents. Contractors sometimes flood the design team with hundreds of frivolous RFIs to build a false narrative that the contract documents are defective, laying the groundwork for a cumulative delay claim.
Subcontractor Coordination Transfer: Asking the landscape architect to resolve basic trade coordination issues (e.g., "Should the electrician trench before or after the irrigation installer lays lateral lines?"). Under AIA A201 Section 3.3.1, trade coordination is the General Contractor's exclusive responsibility.
Attempting to Create Scope Changes: Phrasing an RFI to induce the landscape architect into verbally or casually approving an alteration that the contractor later claims increased the contract price.
Contractual Remedies for RFI Abuse
Modern project manuals include RFI Limiting Provisions in Division 01 General Requirements. These clauses specify that if the contractor submits an RFI requesting information that is readily discernible from a reasonable review of the Contract Documents, the Owner reserves the right to back-charge the contractor for the Landscape Architect's additional professional service hourly fees incurred in researching and responding to the frivolous submission.
3. Architect's Supplemental Instructions (ASI / AIA Document G710)
When the Landscape Architect needs to issue a clarification, provide a supplemental detail, or direct a minor adjustment that does NOT alter the Contract Sum or Contract Time, the formal instrument utilized is an Architect's Supplemental Instruction (ASI) , standardized as AIA Document G710 .
Legal Definition & Authority
Under AIA Document A201 Section 7.4: "The Architect has authority to order minor changes in the Work that are consistent with the intent of the Contract Documents and do not involve an adjustment in the Contract Sum or an extension of the Contract Time. The Architect's order for minor changes shall be in writing. If the Contractor believes that the proposed minor change in the Work will affect the Contract Sum or Contract Time, the Contractor shall notify the Architect and shall not proceed to implement the change in the Work." +--------------------------------------------------------------------------+
- | THE ASI ADMINISTRATIVE LIMIT |
- +--------------------------------------------------------------------------+
- | LANDSCAPE ARCHITECT |
- | │ |
- | Issues AIA Document G710 |
- | (Architect's Supplemental |
- | Instruction - ASI) |
- | │ |
- | ┌─────────────────┴─────────────────┐ |
- | ▼ ▼ |
- | CONTRACT SUM (COST) CONTRACT TIME (SCHEDULE) |
- | ADJUSTMENT: ADJUSTMENT: |
- | $0.00 0 DAYS |
- | (ZERO DOLLARS ONLY) (ZERO DAYS ONLY) |
- +--------------------------------------------------------------------------+
- Valid Landscape Architecture Applications of an ASI
Shifting the location of three decorative shade trees by 3 feet to optimize clearance from an underground conduit.
Modifying the joint layout pattern of concrete unit pavers within a courtyard without changing the overall square footage or paver type.
Adjusting the color mix ratio of two pre-approved integrally colored concrete pigments.
Issuing a supplemental drawing sketch (SKL) illustrating the exact rebar dowel clearance around an area drain basin.
Clarifying the planting bed edge radius at a walkway junction.
The Contractor's Recourse & The 21-Day Rule
If the Contractor receives an ASI and determines that the directed adjustment will, in fact, cause an increase in construction cost (e.g., requires additional labor, extra saw cuts, or specialized equipment) or extend the project schedule, the contractor must NOT execute the work under the ASI .
Under AIA Document A201 Section 15.1.3, the Contractor must give written notice of a claim to the Owner and Landscape Architect within 21 calendar days of receiving the ASI and before proceeding to execute the work.
If the contractor proceeds with the work without providing timely written notice, the contractor legally waives the right to seek additional compensation or time, and the work is deemed completed at no additional cost under the ASI.
4. Field Orders & Written Interpretations
Landscape architects frequently make on-site determinations during field observations. Managing the legal status of field communications is vital.
Field Orders
A Field Order is an immediate written directive issued on site by the Landscape Architect or Owner's representative instructing the contractor to perform minor field adjustments that do not impact cost or time. A field order is essentially a field-issued predecessor to an ASI. To maintain legal validity, any verbal guidance or field order given on site must be formalized in writing and recorded in the subsequent Field Observation Report or followed up with a formal AIA Document G710.
Warning
The Peril of Verbal Directives: Verbal agreements or informal field remarks (e.g., telling a contractor during a site walk, "Sure, that looks fine to shift over") carry immense legal risk. Contractors may proceed with extensive changes and later claim the landscape architect verbally authorized extra costs. The golden rule of CA is: If it is not in writing, it does not exist.
Written Interpretations (AIA A201 Section 4.2.11)
The Landscape Architect will interpret and decide matters concerning performance under, and requirements of, the Contract Documents on written request of either the Owner or Contractor. These written interpretations become part of the binding project record and must be consistent with the intent reasonably inferable from the Contract Documents.
5. Administrative Clarification Tools Comparison
Instrument AIA Form Initiated By Purpose & Application Cost / Time Adjustment Allowed?
Request for Information (RFI) None (Standard Form) General Contractor Inquires about perceived ambiguities, discrepancies, or missing details in documents. No (RFI itself cannot alter contract sum or time)
Architect's Supplemental Instruction (ASI) AIA G710 Landscape Architect Unilaterally directs minor design refinements consistent with contract intent. Strictly NO ($0 cost and 0 days adjustment only)
Field Order None (Custom / Memo) Landscape Architect Immediate on-site written instruction for minor field adjustments. Strictly NO (Must have zero cost and schedule impact)
Proposal Request (PR) / Bulletin AIA G709 Landscape Architect Solicits contractor cost and time quotation for a proposed change in scope. Inquiry only (Does not authorize work or alter contract)
Change Order (CO) AIA G701 LA, Owner, GC (All 3) Formal mutual agreement amending scope, contract sum, and contract schedule. YES (Formal mechanism for adjusting price and time)
6. Real-World Case Scenario: The Irrigation vs. Tree Trenching RFI Dispute
Scenario: During installation of a 100-tree allée, the landscape subcontractor encounters an existing active primary electric duct bank running parallel to the tree line at a depth of 30 inches. The planting detail on Sheet L-502 requires a 36-inch-deep planting pit, meaning 12 tree root balls would sit directly atop the high-voltage duct bank. The General Contractor immediately submits RFI-018 explaining the conflict, providing exact survey elevations of the duct bank, and proposing to shift the 12 trees 5 feet north into an adjacent turf panel, which avoids all utilities and preserves the design rhythm. The landscape architect coordinates with the campus electrical engineer, confirms the clearance, and issues a formal response approving the 5-foot shift, attaching a revised sketch (SKL-04) and issuing an ASI (AIA G710) because no additional materials or labor are required. Two weeks later, the contractor submits an invoice for $6,200 for "RFI design changes."
Contractual Analysis & Resolution:
Validity of RFI & ASI: The contractor used the RFI process correctly to report a legitimate unforeseen condition and proposed a practical solution. The landscape architect acted within authority by issuing an ASI directing a minor shift with zero cost impact.
Failure to Provide Claim Notice: If the contractor believed shifting the trees 5 feet incurred extra costs (e.g., additional grading), the contractor was legally required under AIA A201 Section 15.1.3 to submit written notice of a claim within 21 days of receiving the ASI and prior to planting the trees .
Resolution: Because the contractor executed the planting without filing a timely 21-day claim notice, the contractor waived any claim for additional payment. The invoice is legitimately rejected.
7. Exam Traps & Pitfalls
The "ASI Can Adjust Cost" Trap: An ASI (AIA Document G710) can NEVER alter the Contract Sum or Contract Time. If an exam question asks which document to use to authorize a minor change that costs $500, the answer is a Change Order , not an ASI.
The "RFI Authorizes Work" Trap: An RFI response that provides clarification does not authorize the contractor to perform extra work for additional money. If an RFI response impacts cost or time, it must be formalized via a Change Order or Construction Change Directive before the contractor can bill for it.
The Substitution via RFI Trap: Watch out for questions where a contractor submits an RFI asking to substitute a plant species or paver manufacturer. The landscape architect cannot approve substitutions via an RFI; substitutions require a formal Division 01 Substitution Request.
The Verbal Instruction Trap: Any exam scenario involving an oral instruction or verbal agreement between the designer and contractor on site is contractually unenforceable until reduced to written form.