Study guide
13.1 Hydrologic Cycle, Watershed Delineation & Time of Concentration
Landscape Architect Registration Examination L.A.R.E.
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Project Management, Legal Framework & Contracts
1.1 Professional Practice, Ethics & the HSW Mandate 1.2 Standard of Care, Responsible Charge & Sealing Documents 1.3 Professional Services Agreements & Contract Clauses 1.4 Fee Structures, Compensation Models & Billing 1.5 Project Scheduling, CPM & Budget Management 1.6 Risk Management, Professional Liability & Insurance
2 Chapter 2: Site Inventory, Surveying & Regulatory Framework
2.1 Boundary Surveys, Legal Descriptions & Survey Datums 2.2 Topographic Surveys, Easements & Encumbrances 2.3 Desktop Inventory, GIS Data & Field Reconnaissance 2.4 Policy Documents & Prior Planning Studies 2.5 Adjacent Land Use & Contextual Data Collection 2.6 Stakeholder Engagement & Public Participation 2.7 Zoning Frameworks, Dimensional Standards & FAR 2.8 Parking Standards, Buffer Yards & Zoning Relief 2.9 Clean Water Act Permitting & NEPA Review 2.10 ESA, Floodplain, Coastal & Historic Preservation Compliance
3 Chapter 3: Physical, Contextual & Environmental Site Analysis
3.1 Scoping Site Analysis & Synthesizing Opportunities and Constraints 3.2 Geotechnical Investigation & Soil Classification Systems 3.3 Problematic Soil Conditions & Agronomic Soil Quality 3.4 Topographic Interpretation & Slope Suitability 3.5 Watershed Mechanics, Stream Order & FEMA Flood Hazard Zones 3.6 Wetland Delineation, Classification & Riparian Buffers 3.7 Utility Analysis & Infrastructure Capacity 3.8 Visual Resource & Viewshed Analysis 3.9 Contextual Analysis: Appropriate Use & Future Development Impacts 3.10 Microclimates, Solar Orientation & Vegetation Analysis
4 Chapter 4: Stewardship, Climate Resiliency & Design Principles
4.1 SITES v2 & LEED Site Credit Rating Systems 4.2 Life-Cycle Assessment, Embodied Carbon & Ecosystem Services 4.3 Climate Resiliency, Adaptation & Urban Heat Island Mitigation 4.4 Environmental Justice & Social Equity in Site Design 4.5 Cultural Landscapes, Historic Preservation & Adaptive Reuse
5 Chapter 5: Master Planning, Programming & Land Use
5.1 Project Visioning, Goal Setting & Space Programming 5.2 Carrying Capacity Analysis & NRPA Park Classification Standards 5.3 Site Suitability Synthesis & Opportunities/Constraints Mapping 5.4 Land Use Allocation & Development Scenario Evaluation 5.5 Master Plan Deliverables & Design Guidelines 5.6 Capital Improvement Programming, Phasing & Implementation
6 Chapter 6: Schematic Design & Spatial Organization
6.1 Design Intent, Conceptual Diagrams & Form Generation 6.2 Basis of Design, Alternatives Evaluation & the Preferred Scheme 6.3 Spatial Hierarchy, Outdoor Rooms & Proportion 6.4 Pedestrian Circulation Networks & Environmental Wayfinding 6.5 ADA & PROWAG Accessible Route Design 6.6 Multimodal Transportation, Vehicular Circulation & Parking Layout
7 Chapter 7: Design Development, Materials & Planting Systems
7.1 Paving Systems: Rigid, Flexible & Unit Pavers 7.2 Retaining Walls, Earth Pressure & Wall Drainage 7.3 Wall System Selection, Fences, Screens & Gates 7.4 Site Furnishings: Selection, Materiality & Anchoring 7.5 Exterior Lighting, Photometrics, Dark Sky & Electrical Safety 7.6 Public Playground Safety: CPSC & ASTM Standards 7.7 Planting Design Principles & Ecological Matching 7.8 Water Conservation, Xeriscaping & Irrigation System Principles 7.9 Opinions of Probable Cost & Value Engineering
8 Chapter 8: Construction Drawings, Layout & Detailing
8.1 Drawing Set Hierarchy, Sheet Standards & Drafting Conventions 8.2 Interdisciplinary Coordination & QA/QC Review 8.3 Demolition Plans & Tree Protection Requirements 8.4 Site Preparation: Clearing, Grubbing, Topsoil & Utility Abandonment 8.5 Layout, Dimensioning & Materials Plans 8.6 Planting Plans, Plant Schedules & Installation Details 8.7 Technical Detailing: Pavements, Curbs & Joint Assemblies 8.8 Retaining Wall, Stair & Ramp Detailing Standards
9 Chapter 9: Construction Specifications & Bidding
9.1 CSI MasterFormat Divisions & SectionFormat Structure 9.2 Specification Writing Methods & the Drawings–Specifications Relationship 9.3 Project Manual, General Conditions & Front-End Documents 9.4 Bid Requirements, Bid Forms & Addenda Management 9.5 Pre-Bid Procedures, Bid Opening & Contractor Evaluation
10 Chapter 10: Construction Administration, Submittals & Changes
10.1 Pre-Construction Conference & Construction Administration Authority 10.2 Initial Decision Maker, Communication Protocols & Project Records 10.3 Submittals, Shop Drawings, Product Data & Samples 10.4 Requests for Information (RFIs) & Technical Clarifications 10.5 Change Orders, Construction Change Directives & Claims
11 Chapter 11: Field Observation, Quality Control & Close-Out
11.1 Field Observations, Site Reports & Non-Conforming Work 11.2 Quality Control, Material Testing & Inspections 11.3 Substantial Completion, Punch Lists & Retainage 11.4 Project Close-Out, Guarantees, Warranties & Final Acceptance
12 Chapter 12: Contour Interpretation, Grading & Earthwork Calculations
12.1 Contour Rules & Topographic Landform Interpretation 12.2 Spot Elevations & Contour Interpolation Calculations 12.3 Slope Formulas, Maximum Gradients & Cross Slopes 12.4 Earthwork Calculations: Average End Area & Grid Methods 12.5 Cut and Fill Balancing, Shrinkage, Swell & Mass Haul 12.6 Reviewing Grading Design: Error Detection & Constructability
13 Chapter 13: Stormwater Hydrology, Runoff & BMP Design
13.1 Hydrologic Cycle, Watershed Delineation & Time of Concentration 13.2 Peak Runoff Estimation: The Rational Method (Q = CiA) 13.3 NRCS Curve Number Method & Runoff Hydrographs 13.4 LID Principles, Water Quality Volume & Bioretention Design 13.5 Bioswales, Permeable Pavement, Green Roofs & Harvesting
14 Chapter 14: Site Drainage Systems, Hydraulics & Erosion Control
14.1 Open Channel Hydraulics, Manning’s Equation & Swale Design 14.2 Gutter Flow, Spread & Roadway Inlet Hydraulics 14.3 Subsurface Drainage, Catch Basins & Pipe Invert Calculations 14.4 Stormwater Storage: Detention, Retention & Water Quality Basins 14.5 Reviewing Drainage Plans & Evaluating Design Alternatives 14.6 Erosion Mechanics, RUSLE & the NPDES/SWPPP Framework 14.7 Erosion & Sediment Control BMPs, Basins & Site Stabilization
13.1 Hydrologic Cycle, Watershed Delineation & Time of Concentration
Key Takeaways Explain This Topic AI
The terrestrial hydrologic cycle balances precipitation through interception, depression storage, infiltration, percolation, evapotranspiration, and surface runoff, governed by the continuity equation P = R + I + ET + delta_S.
Catchment delineation establishes the drainage basin area draining to a specific pour point (outfall) by tracing ridgelines strictly perpendicular (at 90 degrees) to topographic contours, traversing saddles, and never cutting across swales or stream channels.
Stormwater runoff moves sequentially through three distinct flow regimes: sheet flow (thin uniform layer max 0.1 ft depth, restricted to a maximum length of 100 feet per TR-55 guidelines), shallow concentrated flow (rills and rivulets categorized as paved or unpaved), and open channel/pipe flow (governed by Manning's equation).
Time of Concentration (Tc) represents the duration required for runoff to travel from the hydraulically most remote point in the watershed to the outfall; standard civil and landscape architectural design enforces an absolute minimum Tc threshold of 5 minutes (for urban catchments) to 10 minutes (for rural/wooded basins).
Intensity-Duration-Frequency (IDF) curves mathematically link rainfall intensity (in/hr) inversely to storm duration and directly to return periods (e.g., 2-year channel protection, 10-year storm sewers, 100-year emergency spillways), requiring rainfall intensity to be evaluated at duration = Tc for peak discharge modeling.
Last updated: September 2026
Core Focus: Grading and drainage plans must respond directly to the natural physics of water movement. Mastering the hydrologic cycle, topographic catchment delineation, overland flow regimes, Time of Concentration (Tc) calculations, and design storm return periods provides the foundational engineering basis for all surface drainage and stormwater infrastructure tested in LARE Section 4.
1. The Terrestrial Hydrologic Cycle & Site Water Budget
The hydrologic cycle describes the continuous, closed-loop circulation of water between the earth's surface, subsurface strata, and the atmosphere. In undisturbed, pre-development ecosystems, precipitation is partitioned across multiple natural sinks, maintaining baseflow in streams and recharging groundwater aquifers.
Core Components of the Terrestrial Water Budget
Precipitation (P): Atmospheric moisture condensing and depositing onto the land surface as rain, snow, sleet, or hail.
Interception: Precipitation caught and retained by vegetative foliage, tree canopies, and architectural structures, evaporating back into the atmosphere without ever reaching the ground plane. Mature deciduous canopies intercept 10% to 25% of annual rainfall; dense coniferous stands can intercept up to 40%.
Depression Storage: Water temporarily captured in micro-topographic hollows, puddles, swale pockets, and surface irregularities. This moisture either infiltrates slowly into the soil or evaporates.
Infiltration: The downward entry of water into the immediate surface layer of the soil mantle. The infiltration rate depends heavily on soil texture, structure, compaction, and antecedent moisture.
Percolation: The deep vertical movement of infiltrated water through unsaturated soil layers (the vadose zone) into underlying groundwater aquifers and regional water tables.
Evapotranspiration (ET): The combined return of moisture to the atmosphere through direct evaporation from soil and water surfaces plus transpiration from plant vascular systems.
Surface Runoff (R): Precipitation that exceeds the combined capacity of interception, depression storage, and infiltration, flowing overland under gravity toward lower drainage courses.
The Site Hydrologic Continuity Equation
On any given site, the conservation of mass dictates the hydrologic continuity equation:
P = R + I + ET + delta_S
Where:
- P = Total precipitation
- R = Surface runoff
- I = Infiltration
- ET = Evapotranspiration
- delta_S = Change in surface and soil moisture storage
- Pre-Development vs. Post-Development Hydrologic Imbalance
Urbanization and site development fundamentally disrupt this equilibrium. Replacing porous native soils and dense plant canopies with impervious pavements and roofs produces severe hydrologic consequences: +-------------------------------------------------------------------------+
- | HYDROLOGIC BALANCE SHIFT UNDER SITE URBANIZATION |
- +-------------------------------------------------------------------------+
- | NATURAL GROUND COVER (Undisturbed) TYPICAL IMPERVIOUS SITE (75%-100%)|
- | - 40% Evapotranspiration - 30% Evapotranspiration |
- | - 25% Deep Aquifer Infiltration - 5% Deep Aquifer Infiltration |
- | - 25% Shallow Subsurface Infiltration - 10% Shallow Infiltration |
- | - 10% Surface Runoff - 55% Surface Runoff |
- +-------------------------------------------------------------------------+
This dramatic 5-fold increase in surface runoff volume accelerates stream channel incision, degrades aquatic habitats, elevates flood stages, and deprives underlying aquifers of vital recharge.
2. Principles & Mechanics of Watershed and Catchment Delineation
A watershed (also termed a drainage basin, catchment, or contributing area) is a geographically bounded land area that concentrates and conveys all surface runoff to a common outfall, discharge point, or hydraulic structure.
Terminology & Control Features
Pour Point (Outfall / Design Point): The single lowest topographic point on the boundary of a catchment where all collected runoff exits the basin. Typical pour points on grading plans include a storm sewer catch basin grate, a culvert entrance, an inlet headwall, a proposed bioretention overflow weir, or the point where a swale crosses a property line.
Drainage Divide (Ridgeline): The elevated topographic boundary that separates adjacent watersheds. Runoff falling on opposite sides of a divide flows into completely different drainage systems.
Saddle (Col): A low point along a ridgeline situated between two higher summits. The boundary line must pass directly across the saddle along its highest elevation axis.
The Immutable Rules of Topographic Delineation
To delineate a watershed boundary accurately from topographic contours on the LARE, candidates must follow a rigorous geometric procedure:
Identify the Pour Point: Locate the exact downstream outfall structure or property boundary point. The entire catchment delineation begins and ends at this single coordinate.
Identify Topographic High Points & Saddles: Scan upstream from the pour point to locate all surrounding hilltops, ridges, knolls, and saddles that frame the tributary area.
Follow the Rule of Perpendicularity (90-Degree Rule): Because gravity pulls water strictly along the path of steepest slope, water flows exactly perpendicular (90 degrees) to contour lines. Consequently, the watershed boundary line must cut across contour lines at right angles.
Trace the Crest of Ridges: Along ridges and spurs (where contour lines form V or U shapes pointing downhill toward lower elevations), the boundary line traces along the absolute crest, splitting the slope so that water sheds outward away from the boundary on both sides.
Traverse Saddles Across Their High Axis: When encountering a saddle, the boundary line must cross the saddle perpendicular to the contours, connecting the two flanking summits.
NEVER Cross a Swale or Stream: Valleys, swales, and ravines (where contours form V or U shapes pointing uphill toward higher elevations) concentrate and convey water. The catchment boundary must never cut across a swale or drainage channel, because doing so would split a concentrated flow path in half. All swales that drain toward the pour point must remain entirely inside the delineated boundary.
Close the Boundary Loop: Continue tracing the divide around the perimeter until the line returns to the initial pour point, forming a continuous, closed polygon. +-------------------------------------------------------------------------+
- | WATERSHED DELINEATION GEOMETRY ACROSS CONTOURS |
- +-------------------------------------------------------------------------+
- | |
- | Summit [112.0'] |
- | | |
- | (Ridgeline Divide) |
- | (Traces crest) |
- | .-------+-------. |
- | / | / |
- | 110' / | / 110' |
- | / | / |
- | 108' / Inside Catchment: / 108' |
- | / Swale contours / |
- | 106' / point UPHILL / 106' |
- | / (V-shapes) / |
- | / Water concentrates / |
- | 104' / down centerline / 104' |
- | / | / |
- | | v | |
- | | [POUR POINT] | |
- | | Catch Basin | |
- | *-------------============------------* |
- | (IE) |
- +-------------------------------------------------------------------------+
- 3. Flow Paths & Hydraulic Conveyance Regimes
Once precipitation strikes the ground surface, runoff travels toward the pour point through three distinct, sequential hydraulic flow regimes defined by USDA NRCS Technical Release 55 (TR-55): +-------------------------------------------------------------------------+
- | TR-55 THREE-STAGE OVERLAND FLOW SEQUENCE |
- +-------------------------------------------------------------------------+
- | 1. SHEET FLOW 2. SHALLOW CONCENTRATED 3. CHANNEL / PIPE |
- | (Laminar Thin Film) (Rills & Micro-Swales) (Gutter, Ditch, Pipe|
- | Depth <= 0.1 ft Depth: 0.1 ft to 0.5 ft Open Channel / Pipe |
- | Max Length: 100 ft Velocity nomographs Manning's Equation |
- | Kinematic Wave Eq. Unpaved vs. Paved Full Hydraulic Radius
- +-------------------------------------------------------------------------+
- Stage 1: Sheet Flow (Overland Flow)
Sheet flow is the movement of a very shallow, uniform sheet of water over planar, broad ground surfaces without defined channels. The flow depth is extremely thin, typically less than 0.1 foot (1.2 inches) .
The Modern 100-Foot Length Threshold: Historically, engineering texts permitted sheet flow lengths up to 300 feet. However, extensive field research by the NRCS demonstrated that natural micro-topography, vegetation tussocks, and soil irregularities inevitably concentrate sheet flow into tiny rivulets (rills) within a short distance. Consequently, modern TR-55 guidelines strictly limit the maximum allowable sheet flow length to 100 feet . On the LARE, any design assumption exceeding 100 feet for sheet flow is considered hydrologically invalid.
Manning's Kinematic Wave Equation for Sheet Flow: Tt = [0.007 * (n * L)^0.8] / [(P2)^0.5 * s^0.4]
Where:
- Tt = Travel time (hours)
- n = Manning's roughness coefficient for sheet flow (dimensionless)
- L = Flow length (feet; <= 100 ft)
- P2 = 2-year, 24-hour design rainfall depth (inches)
- s = Land surface slope (ft/ft)
- Common Manning's Roughness Coefficients (n) for Sheet Flow
Notice that Manning's n for sheet flow is significantly higher than for channel flow because the thin film of water interacts with the entire micro-texture of the surface:
- Smooth impervious surfaces (concrete, asphalt): 0.011
- Fallow / bare tilled soil: 0.050
- Cultivated soils (short residue): 0.060
- Short grass prairie / mowed lawn: 0.150
- Dense bluegrass / turf grass: 0.240
- Bermuda grass: 0.410
- Woods with light underbrush: 0.400
- Woods with dense underbrush and forest litter: 0.800
- Stage 2: Shallow Concentrated Flow
After a maximum of 100 feet, sheet flow gathers into shallow rills, rivulets, and minor depressions with flow depths ranging from 0.1 foot to 0.5 foot . In this regime, surface tension is broken, and flow transitions into turbulent, concentrated flow.
Velocity Determination: Average velocity is determined from the ground slope (s, in ft/ft) and surface condition using the NRCS unpaved and paved velocity equations:
- Unpaved surfaces: V = 16.1345 * sqrt(s) (ft/s)
- Paved surfaces: V = 20.3282 * sqrt(s) (ft/s)
- Travel Time Calculation: Tt = L / (3600 * V) (hours) or Tt = L / (60 * V) (minutes)
- Stage 3: Open Channel & Conduit Flow
When runoff enters well-defined physical drainage courses—such as vegetated swales, concrete gutters, roadside ditches, natural streams, or closed storm sewer pipes—it operates under channel flow .
Manning's Equation for Open Channel Velocity: V = (1.486 / n) * R^(2/3) * s^(1/2)
Where:
- V = Mean flow velocity (ft/s)
- n = Manning's channel roughness coefficient
R = Hydraulic radius (A / Pw, in feet), where A is cross-sectional flow area (sq ft) and Pw is wetted perimeter (feet)
s = Longitudinal slope of the hydraulic energy grade line (ft/ft)
Channel Travel Time: Tt = L / (60 * V) (minutes).
4. Time of Concentration (Tc) Mechanics & Sizing Rules
The Time of Concentration (Tc) is the total time required for a drop of water to travel hydraulically from the most remote point of the watershed to the outfall (pour point). "Most remote" refers to the point with the longest travel time , which is not necessarily the point with the longest physical distance.
- Cumulative Travel Time Equation
- Tc = Tt(sheet) + Tt(shallow concentrated) + Tt(channel / pipe)
- Minimum Tc Design Thresholds
In highly urbanized sites with small catchments (e.g., a 0.5-acre parking lot or an isolated building roof), calculating Tc using kinematic formulas might yield values as short as 1 to 3 minutes.
The Engineering Rule: Standard municipal engineering codes and LARE grading criteria enforce an absolute minimum Tc threshold of 5.0 minutes (for heavily paved urban sites) to 10.0 minutes (for residential, suburban, or natural catchments).
Why Enforce a Minimum Tc? Rainfall Intensity-Duration-Frequency (IDF) curves spike exponentially toward infinity as storm duration approaches zero. Calculating runoff using an unconstrained Tc of 2 minutes would produce an absurdly extreme rainfall intensity, resulting in grossly oversized, economically wasteful, and hydraulically unstable storm pipes.
5. Design Storm Frequency, Return Periods & IDF Curves
Stormwater infrastructure cannot be engineered for the largest storm imaginable; systems are designed to balance public safety against construction cost based on statistical probability.
Return Period (T) vs. Annual Exceedance Probability (P)
The return period (recurrence interval, T) represents the long-term average recurrence interval between storms exceeding a given magnitude. The annual exceedance probability (P) is the statistical chance that a storm of that magnitude will be equaled or exceeded in any single calendar year :
- P = 1 / T +-------------------------------------------------------------------------+
- | DESIGN STORM FREQUENCY & REGULATORY APPLICATION |
- +-------------------------------------------------------------------------+
- | RETURN PERIOD | ANNUAL PROBABILITY | TYPICAL LANDSCAPE ARCHITECTURE USAGE|
- +---------------+--------------------+-------------------------------------+
- | 2-Year | 50.0% (1 in 2) | Stream scour prevention; BMP water |
- | | | quality channel protection; bioswales|
- | 5-Year | 20.0% (1 in 5) | Minor residential drainage, lawns |
- | 10-Year | 10.0% (1 in 10) | Storm sewer pipe systems; parking |
- | | | lot inlets; roadside gutters |
- | 25-Year | 4.0% (1 in 25) | Culverts under arterial collector |
- | | | roads; regional detention outfalls |
- | 50-Year | 2.0% (1 in 50) | Major highway bridges & culverts |
- | 100-Year | 1.0% (1 in 100) | Emergency spillways; floodplains; |
- | | | Finished Floor Elevations (FFE) |
- +-------------------------------------------------------------------------+
- Intensity-Duration-Frequency (IDF) Curves
An IDF curve is a graphical or mathematical tool that provides the design rainfall intensity (i, in inches per hour) for a specific geographic location based on two inputs:
Storm Duration (D): In peak runoff calculations, storm duration is set equal to the watershed's Time of Concentration (D = Tc).
Return Period (T): The regulatory design frequency (e.g., 10-year).
Mathematical Principles of IDF Relationships
Inverse Relationship with Duration: As storm duration increases, average rainfall intensity (i) decreases . A brief 5-minute cloudburst delivers water at a much higher intensity (e.g., 6.5 in/hr) than a continuous 24-hour soaking rain (e.g., 0.25 in/hr).
Direct Relationship with Return Period: As return period increases (rarer storms), rainfall intensity increases for any given duration. A 100-year event has a substantially higher intensity than a 2-year event of identical duration.
6. Comprehensive Comparison: Hydraulic Flow Regimes
- Attribute Sheet Flow Shallow Concentrated Flow Open Channel / Pipe Flow
- Flow Depth <= 0.1 ft (thin film) 0.1 ft to 0.5 ft (rills/rivulets) > 0.5 ft (defined cross-section)
Maximum Length Strictly <= 100 ft (TR-55) Variable (typically 100-500 ft) Variable (hundreds to thousands of ft)
Governing Equation Manning's Kinematic Wave NRCS Nomograph / Empirical Equations Manning's Open Channel Equation
Roughness Factor Manning's n for sheet (0.011-0.80) Surface condition (Paved vs. Unpaved) Manning's n for channel (0.012-0.060)
- Hydraulic Radius Approximates sheet depth Not directly calculated R = A / Pw (geometry dependent)
- Typical Velocity Very slow (0.1-0.5 ft/s) Moderate (1.0-3.5 ft/s) Rapid (3.0-12.0 ft/s)
- 7. Real-World Case Scenario: Delineating a Catchment & Computing Tc
Scenario: A landscape architect is designing a surface drainage system for a proposed environmental education pavilion on a 6.2-acre parcel. The design outfall (pour point) is a proposed catch basin grate located at the lowest corner of the property (elevation 180.00'). Topographic mapping reveals three flow segments connecting the hydraulically most remote point of the basin (a wooded ridge crest at elevation 224.00') to the outfall:
Segment 1 (Sheet Flow): Begins at the ridge crest (elevation 224.00') and travels across dense woods with forest litter for a horizontal distance of 100.0 feet to elevation 218.00'. (P2 = 3.2 inches, n = 0.60).
Segment 2 (Shallow Concentrated Flow): Runoff gathers into an unpaved grass swale depression, traveling 350.0 feet from elevation 218.00' to elevation 198.00'.
Segment 3 (Channel Flow): Runoff enters a concrete-lined roadside valley gutter (n = 0.015, flow area A = 0.75 sq ft, wetted perimeter Pw = 2.50 ft), traveling 400.0 feet from elevation 198.00' to the catch basin grate at elevation 180.00'.
Step-by-Step Calculation:
Segment 1: Sheet Flow Travel Time:
Slope: s = (224.0' - 218.0') / 100.0' = 6.0' / 100.0' = 0.060 ft/ft.
Apply Manning's kinematic wave equation:
Tt1 = [0.007 * (0.60 * 100)^0.8] / [(3.2)^0.5 * (0.060)^0.4]
Tt1 = [0.007 * (60)^0.8] / [1.789 * 0.324] = [0.007 * 26.54] / 0.580 = 0.1858 / 0.580 = 0.320 hours = 19.2 minutes
Segment 2: Shallow Concentrated Flow Travel Time:
Slope: s = (218.0' - 198.0') / 350.0' = 20.0' / 350.0' = 0.0571 ft/ft.
Velocity (unpaved surface): V = 16.1345 * sqrt(0.0571) = 16.1345 * 0.239 = 3.86 ft/s.
Travel time: Tt2 = 350.0' / (3.86 ft/s * 60) = 1.51 minutes .
Segment 3: Channel Flow Travel Time:
Slope: s = (198.0' - 180.0') / 400.0' = 18.0' / 400.0' = 0.045 ft/ft.
Hydraulic radius: R = A / Pw = 0.75 / 2.50 = 0.30 ft.
Velocity via Manning's equation:
V = (1.486 / 0.015) * (0.30)^(2/3) * (0.045)^(1/2) = 99.07 * 0.448 * 0.212 = 9.41 ft/s.
Travel time: Tt3 = 400.0' / (9.41 ft/s * 60) = 0.71 minutes .
Total Time of Concentration: Tc = 19.2 + 1.51 + 0.71 = 21.42 minutes .
This value exceeds the 5-minute and 10-minute minimum design thresholds. The landscape architect inputs D = 21.4 minutes into the regional IDF table to determine the design rainfall intensity for a 10-year storm.
8. Exam Traps & Pitfalls
The 100-Foot Sheet Flow Trap: A widespread error on the LARE is calculating sheet flow over distances of 200 to 300 feet because older reference manuals permitted it. Modern NRCS TR-55 standards cap sheet flow at 100 feet maximum . Any segment beyond 100 feet must be modeled as shallow concentrated flow.
Delineating Across a Swale: Never draw a watershed divide line across a swale, draw, or valley. A swale gathers water; it does not separate it. Catchment boundaries must run along ridges (where contours point downhill) and cut perpendicular to contours.
Longest Distance vs. Longest Travel Time: Do not assume the hydraulically most remote point is simply the point furthest away horizontally on the plan. A distant point on a steep, smooth asphalt parking lot can have a travel time of 4 minutes, while a closer point in a dense, flat wetland buffer can have a travel time of 25 minutes. The point with the longest travel time (Tc) governs the design.
The Unconstrained Urban Tc Error: If your calculated Tc for a small impervious plaza is 1.8 minutes, you cannot use 1.8 minutes on an IDF curve. You must apply the standard municipal minimum Tc of 5.0 minutes to avoid obtaining non-physical, astronomically high peak runoff rates.
IDF Curve Axis Inversion: Meticulously verify curve units. In rainfall graphs, storm duration sits on the horizontal X-axis (minutes or hours), while rainfall intensity sits on the vertical Y-axis (inches per hour). Do not confuse total cumulative storm depth (inches) with rainfall intensity (in/hr).