9.3 BD+C Project Types and Scope

LEED AP Building Design + Construction BD+C

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: Introduction & Exam Overview

1.1 Current Exam Facts 1.2 How to Use This Guide

2 Chapter 2: Integrative Process

2.1 Integrative Process Philosophy and Workflow 2.2 Integrative Process Credit (IP) 2.3 Prerequisites and Project Setup 2.4 Certification Levels and Scorecard

3 Chapter 3: Location & Transportation + Surroundings

3.1 LEED for Neighborhood Development Location 3.2 Sensitive Land Protection & High Priority Site 3.3 Surrounding Density and Diverse Uses 3.4 Access to Quality Transit 3.5 Bicycle Facilities, Reduced Parking, Green Vehicles 3.6 Building Surroundings and Joint Use

4 Chapter 4: Sustainable Sites (SS)

4.1 SS Prerequisite: Construction Activity Pollution Prevention 4.2 Site Assessment and Site Development 4.3 Open Space and Rainwater Management 4.4 Heat Island Reduction 4.5 Light Pollution Reduction

5 Chapter 5: Water Efficiency (WE)

5.1 WE Prerequisites 5.2 Outdoor and Indoor Water Use Reduction Credits 5.3 Cooling Tower Water Use, Process Water, and Metering 5.4 Non-Potable and Reclaimed Water Strategies

6 Chapter 6: Energy & Atmosphere (EA)

6.1 EA Prerequisites 6.2 Optimize Energy Performance 6.3 Enhanced Commissioning 6.4 Advanced Energy Metering and Grid Harmonization 6.5 Renewable Energy and Carbon Offsets 6.6 ASHRAE 90.1-2016 Fundamentals

7 Chapter 7: Materials & Resources (MR)

7.1 MR Prerequisites 7.2 Building Life-Cycle Impact Reduction (BLIR) 7.3 Building Product Disclosure and Optimization (BPDO) 7.4 Construction and Demolition Waste Management 7.5 PBT Source Reduction and Furniture Material

8 Chapter 8: Indoor Environmental Quality (EQ)

8.1 EQ Prerequisites 8.2 Enhanced IAQ Strategies and Low-Emitting Materials 8.3 Construction IAQ Management and Assessment 8.4 Thermal Comfort 8.5 Interior Lighting and Daylight 8.6 Quality Views and Acoustic Performance

9 Chapter 9: Innovation, Regional Priority & Project Types

9.1 Innovation Credits 9.2 Regional Priority Credits 9.3 BD+C Project Types and Scope 9.4 Project Registration, Documentation, and Certification Process 9.5 Last-Minute Exam Tips

9.3 BD+C Project Types and Scope

Key Takeaways Explain This Topic AI

LEED v4.1 BD+C covers 8 project types: New Construction (NC), Core & Shell (CS), Schools, Retail, Data Centers, Warehouses & Distribution Centers, Hospitality, and Healthcare.

The LEED project boundary is the portion of the site submitted for certification; it must include all contiguous land associated with the building and is distinct from the legal site/property line.

If a project occupies less than 40% of the building's gross floor area, BD+C does not apply — the project should pursue LEED ID+C (Interior Design and Construction) instead.

If a project includes more than 40% of the building's gross floor area, the entire building must pursue BD+C certification, including spaces not in the project scope.

Multiple-building projects may use Group Certification (one application, identical results) or Campus Certification (one shared application, individual results per building) when buildings sit on a single contiguous site with shared ownership.

Last updated: May 2026

The 8 BD+C Rating Systems

LEED v4.1 Building Design and Construction is a family of related rating systems. They share most credits but adjust thresholds, applicability, and a handful of category-specific credits to fit each building type.

Rating System Use For Notable Variations

NC — New Construction & Major Renovations Office, multifamily ≥4 stories, and any building type without its own rating system The default BD+C path

CS — Core and Shell Speculative or developer-led buildings where the owner controls structure and base building only Pre-certification available; modified IEQ credits for unfinished tenant space

Schools K-12 and higher-education classroom buildings Acoustic performance prerequisite; mold prevention; master site planning

Retail Stores, restaurants, banks with high customer traffic Process-energy credits; commercial kitchen ventilation

Data Centers Buildings ≥60% of gross floor area dedicated to data processing PUE-based energy benchmarking; redundancy-aware energy modeling

Warehouses & Distribution Centers Storage and shipping facilities with limited occupant density Reduced occupant-comfort thresholds; loading-dock IAQ

Hospitality Hotels, motels, resorts Guest-room water and energy submetering; in-suite controls

Healthcare Inpatient hospitals; some outpatient with 24/7 operation Acoustic performance; medical-equipment energy; chemical safety

If two rating systems could apply to a building (e.g., a mixed-use building with retail at grade and offices above), the team must use the 40/40/20 rule :

>40% of gross floor area in one use → that rating system is required .

<40% of gross floor area in one use and >40% in another → choose the rating system that applies to the majority use.

20–40% in a secondary use → the team may choose either applicable rating system.

The LEED Project Boundary

The LEED project boundary is the portion of the project site submitted for certification. It is distinct from the legal property line and from the building footprint .

Key rules:

The boundary must include all contiguous land associated with the building and its operations (parking, hardscape, landscape, stormwater features).

The boundary cannot exclude land to game a credit (for example, drawing the boundary tight around a building to avoid counting a parking lot in the heat-island calculation).

For Core & Shell projects, the boundary must include any tenant space that is part of the developer's certification scope.

The boundary must be reasonably and consistently applied across all credits — the same boundary is used for site, water, transportation, and density calculations.

MPR Reminder: Minimum Site Area

The Minimum Program Requirements (MPRs) require:

The project must be in a permanent location on existing land .

The project must use reasonable LEED boundaries .

The project must comply with applicable laws (environmental, zoning, etc.).

A project that violates an MPR cannot certify regardless of point total.

Substantial Completion and Occupancy

A BD+C project must be designed and constructed for occupancy. The exam expects you to know:

Substantial completion is when the building is sufficiently complete that the owner can use it for its intended purpose.

BD+C reviews begin at substantial completion (construction review) — though optional design review can happen earlier.

A building that has been occupied for more than 60 months (5 years) typically must pursue O+M (Operations and Maintenance) , not BD+C.

Phased Projects

Some large developments are built in multiple phases over months or years. LEED handles this through:

One application per phase — each phase certifies separately if it has a distinct LEED boundary and substantial completion date.

Master Site / Group Certification — a single application covers all phases when boundaries and ownership are shared.

Multiple-Building Projects

When multiple buildings are pursued together, two paths exist:

Path When To Use Outcome

Group Certification Buildings are nearly identical (e.g., a developer building 5 identical hotels) One certification application; all buildings receive the same certification level

Campus Certification Buildings share a site and shared systems (e.g., a corporate campus) but differ One shared application for site/shared credits; each building certifies individually

Both paths require:

  • A single contiguous site under shared ownership or control
  • Buildings that share the same LEED project boundary for site-level credits
  • All buildings pursuing the same rating system (e.g., all NC)
  • Pre-Certification (Core & Shell Only)

Pre-certification is a unique feature of the Core and Shell rating system. Developers can apply for pre-certification during design to market a building's expected LEED level to prospective tenants before construction is complete.

Pre-certification is marketing-only — it is not the same as final certification.

It is available only for CS projects.

The final CS certification is awarded after construction review.