9.4 Project Registration, Documentation, and Certification Process

LEED AP Building Design + Construction BD+C

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: Introduction & Exam Overview

1.1 Current Exam Facts 1.2 How to Use This Guide

2 Chapter 2: Integrative Process

2.1 Integrative Process Philosophy and Workflow 2.2 Integrative Process Credit (IP) 2.3 Prerequisites and Project Setup 2.4 Certification Levels and Scorecard

3 Chapter 3: Location & Transportation + Surroundings

3.1 LEED for Neighborhood Development Location 3.2 Sensitive Land Protection & High Priority Site 3.3 Surrounding Density and Diverse Uses 3.4 Access to Quality Transit 3.5 Bicycle Facilities, Reduced Parking, Green Vehicles 3.6 Building Surroundings and Joint Use

4 Chapter 4: Sustainable Sites (SS)

4.1 SS Prerequisite: Construction Activity Pollution Prevention 4.2 Site Assessment and Site Development 4.3 Open Space and Rainwater Management 4.4 Heat Island Reduction 4.5 Light Pollution Reduction

5 Chapter 5: Water Efficiency (WE)

5.1 WE Prerequisites 5.2 Outdoor and Indoor Water Use Reduction Credits 5.3 Cooling Tower Water Use, Process Water, and Metering 5.4 Non-Potable and Reclaimed Water Strategies

6 Chapter 6: Energy & Atmosphere (EA)

6.1 EA Prerequisites 6.2 Optimize Energy Performance 6.3 Enhanced Commissioning 6.4 Advanced Energy Metering and Grid Harmonization 6.5 Renewable Energy and Carbon Offsets 6.6 ASHRAE 90.1-2016 Fundamentals

7 Chapter 7: Materials & Resources (MR)

7.1 MR Prerequisites 7.2 Building Life-Cycle Impact Reduction (BLIR) 7.3 Building Product Disclosure and Optimization (BPDO) 7.4 Construction and Demolition Waste Management 7.5 PBT Source Reduction and Furniture Material

8 Chapter 8: Indoor Environmental Quality (EQ)

8.1 EQ Prerequisites 8.2 Enhanced IAQ Strategies and Low-Emitting Materials 8.3 Construction IAQ Management and Assessment 8.4 Thermal Comfort 8.5 Interior Lighting and Daylight 8.6 Quality Views and Acoustic Performance

9 Chapter 9: Innovation, Regional Priority & Project Types

9.1 Innovation Credits 9.2 Regional Priority Credits 9.3 BD+C Project Types and Scope 9.4 Project Registration, Documentation, and Certification Process 9.5 Last-Minute Exam Tips

9.4 Project Registration, Documentation, and Certification Process

Key Takeaways Explain This Topic AI

All LEED documentation flows through LEED Online at https://leedonline.usgbc.org , which hosts credit templates, the review platform, and the appeals process.

The certification workflow is: Register → Document credits → (Optional) Design review → Construction review → Final certification.

Each review round consists of a preliminary review, a comment-response cycle, and a final review — the team has the chance to add documentation in response to reviewer comments.

Project fees include registration (one-time, paid at registration), certification (paid before final review, scaled by project size), and appeal fees ($500 per appealed credit), all administered by GBCI.

Pre-certification is offered ONLY for the LEED BD+C: Core and Shell rating system; it is a design-phase marketing milestone, not the final certification.

Last updated: May 2026

Who Runs the Process

Two organizations split the work:

USGBC (U.S. Green Building Council) — develops and maintains the LEED rating systems.

GBCI (Green Business Certification Inc.) — administers third-party certification, reviews submitted documentation, and awards LEED certification levels.

All documentation, fee payment, and review communication runs through LEED Online at https://leedonline.usgbc.org .

  • The 5-Step Workflow 1. Register the project (pay registration fee, choose rating system)
  • ↓
  • 2. Document credits in LEED Online (templates, calculations, narratives, attachments)
  • ↓
  • 3. (Optional) Design Review — submit design-phase credits early
  • ↓
  • 4. Construction Review — submit all remaining credits after substantial completion
  • ↓
  • 5. Final Certification award (Certified / Silver / Gold / Platinum)
  • Step 1 — Register

The owner or owner's representative registers the project on LEED Online and pays the registration fee (a flat amount that varies by member status and project type). Registration triggers the creation of a project workspace where team members are added and credits are tracked.

Step 2 — Document Credits

Each credit has a credit template form in LEED Online with the required calculations and documentation. Teams upload:

  • Template forms filled in with calculations and declarations
  • Calculation spreadsheets (e.g., energy model output, water-use spreadsheet, transportation calculator)
  • Narratives explaining design strategies and decisions

Supporting documentation — drawings, photos, cut sheets, manufacturer data, contracts, third-party reports (e.g., commissioning reports, EPDs, HPDs, FSC chain-of-custody)

Step 3 — Design Review (Optional)

A design review lets teams submit design-phase credits (typically site selection, water-use design, energy-model design credits, daylighting design) before construction is complete. This is optional but useful for:

  • Risk reduction — flagging credit problems before they are baked into construction
  • Marketing — anticipated points can be referenced in leasing and PR
  • Cost smoothing — review fees are split between design and construction phases

Design-phase credits that earn an 'Anticipated' ruling in design review are typically confirmed at construction review unless something changes.

Step 4 — Construction Review (Required)

At substantial completion, the team submits all remaining construction-phase credits . Each review round includes:

Preliminary Review — GBCI evaluates the submission and issues a credit-by-credit ruling (Anticipated, Awarded, Denied, Pending-Clarification).

Comment-Response Cycle — the team has a set window (typically 25 business days) to respond to comments, add documentation, or revise calculations on Pending credits.

Final Review — GBCI issues final rulings.

Two review rounds are included in the certification fee; additional reviews trigger added fees.

Step 5 — Final Certification

GBCI tallies awarded points and assigns the certification level:

  • Level Point Range (out of 110)
  • Certified 40–49 points
  • Silver 50–59 points
  • Gold 60–79 points
  • Platinum 80+ points

The owner receives a certification plaque and the project appears in the public LEED Project Directory .

Appeals

If a team disagrees with a credit ruling after the final review, they can appeal the decision through LEED Online. Appeal rules:

One credit per appeal — each appealed credit is filed and paid for separately.

Appeal fee — typically $500 per credit for member-rate projects; check current GBCI fee schedule.

One appeal per credit — a denied appeal cannot be re-appealed.

The appeal is reviewed by a different reviewer than the original review.

Credit Interpretation Rulings (CIRs)

A Credit Interpretation Ruling (CIR) is a formal request to GBCI for clarification on how a credit's requirements apply to a unique project condition. CIRs are:

Submitted before the team commits to a documentation strategy, not after a credit is denied

Project-specific — the ruling applies to that project only, though USGBC may publish anonymized rulings as guidance

Fee-based — there is a small fee per CIR submission

The appeal process is the correct path for challenging a denied credit ; a CIR is the correct path for clarifying ambiguity before submission.

Certification Fees Summary

  • Fee When Paid Purpose
  • Registration At project registration Opens the LEED Online workspace
  • Certification (flat or per-sf) Before review submission Funds two rounds of credit review
  • Expedited review Optional, at submission Faster review turnaround for an added fee
  • CIR At each CIR submission Per-CIR fee
  • Appeal At each appealed credit ~$500 per credit

USGBC members receive discounted rates on most fees.

Pre-Certification (Core & Shell Only)

As noted in Section 9.3, pre-certification is a unique offering for Core and Shell projects. The team submits design-phase documentation and receives a marketing-only certification level indication before construction completes. It is not a substitute for the final CS certification, which still requires construction review.