6.2 Utility Color Codes, the 18-Inch Safety Zone, Excavating Near Facilities & Damage Response

Massachusetts Crane Operator Hoisting Engineer License

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: Massachusetts Hoisting Law (MGL Chapter 146)

1.1 MGL Chapter 146 §§ 53–54A: The Hoisting License Mandate, Exemptions & Penalties 1.2 MGL Chapter 146 §§ 57–67: Applications, Examinations, Appeals, License Term & Renewal

2 Chapter 2: Licensing Under 230 CMR 6.00

2.1 License Classes & Restrictions Under 230 CMR 6.10 2.2 Applying, Medical Qualification, the OPSI Exam & Renewal (230 CMR 6.02) 2.3 Temporary Permits, Continuing Education, Apprentices & Company Exemptions (230 CMR 6.03–6.07)

3 Chapter 3: 230 CMR 6.00 Definitions, Operating Rules & Enforcement

3.1 230 CMR 6.01: Scope, Key Definitions, Exempt Equipment & Adopted Standards 3.2 Operating Procedures Under 230 CMR 6.08: Inspections, Attention, Signals & Stop Authority 3.3 Special Requirements Under 230 CMR 6.09: Cranes, Derricks, Pile Drivers, Forklifts & Excavators 3.4 Incident Reporting, Investigations, Discipline & Variances (230 CMR 6.11–6.13)

4 Chapter 4: Crane Types, Working Parts & Load Charts

4.1 Crane Types & Working Parts by Restriction: Lattice, Derrick, Tower, Telescopic & Hydraulic Machines 4.2 Load Chart Fundamentals: Structural Strength vs. Stability Limits 4.3 Capacity Deductions & Calculating Net Allowable Capacity 4.4 Quadrants of Operation, Working Radius & Boom Angle Dynamics

5 Chapter 5: Advanced Lift Calculations & Multi-Crane Operations

5.1 Boom Deflection, Ground Leveling & Side-Loading Hazards 5.2 Wire Rope Reeving, Parts of Line & Single-Line Pull Limits 5.3 Center of Gravity, Weight Distribution & Multi-Crane (Tandem) Lifts

6 Chapter 6: Dig Safe, Underground Utilities & Trench Safety

6.1 Massachusetts Dig Safe Law (MGL c. 82 §§ 40–40E, 220 CMR 99.00): Premarking & Notice 6.2 Utility Color Codes, the 18-Inch Safety Zone, Excavating Near Facilities & Damage Response 6.3 Trench Safety Law, Excavation Hazards, Setbacks & Utility-Strike Emergencies

7 Chapter 7: Power Lines, Ground Conditions & Weather

7.1 Power Line Safety: OSHA 1926.1408–1411, Table A & Table T 7.2 Ground Bearing Pressure, Outrigger Setup & Cribbing Sizing 7.3 Wind, Storms, Lightning, Ice & Cold: Weather Limits for Crane Work

8 Chapter 8: Rigging Principles, Slings & Hardware

8.1 Sling Types: Synthetic, Wire Rope, and Alloy Steel Chain Slings 8.2 Sling Angle Calculations & Tension Formulas 8.3 Rigging Hardware, Shackles, Hooks & Below-the-Hook Lifting Devices

9 Chapter 9: Wire Rope & Crane Inspection

9.1 Wire Rope Construction, Damage Assessment & Removal Criteria (OSHA 1926.1413) 9.2 Crane Inspections, Safety Devices & Operational Aids (230 CMR 6.08; OSHA 1926.1412, 1415, 1416)

10 Chapter 10: Hand Signals & Personnel Hoisting

10.1 Standard Hand Signals, Voice & Radio Signals and Signal Person Qualification 10.2 Crane-Suspended Personnel Platforms (230 CMR 6.09(6) & OSHA 29 CFR 1926.1431)

6.2 Utility Color Codes, the 18-Inch Safety Zone, Excavating Near Facilities & Damage Response

Key Takeaways Explain This Topic AI

Massachusetts marking colors are red for electric, yellow for gas and petroleum, orange for communications, blue for water, irrigation and slurry, green for sewer and drain, and white for the premark (MGL c. 82 § 40).

The safety zone is the width of the facility plus not more than 18 inches on each side of the marked center line (MGL c. 82 § 40; 220 CMR 99.06(2)).

Near marked facilities, non-mechanical means must be used to locate them; mechanical means may only break through pavement or rock first (220 CMR 99.07(3)).

A company must re-mark within 24 hours of a request, excluding weekends and holidays, and the excavator suspends work in that area for 24 hours (220 CMR 99.06(6), 99.07(5)).

If damage releases gas, the excavator must call 911 immediately, evacuate if needed, notify the facility owner, attempt no repairs and report to the DPU within 30 days (220 CMR 99.07(8)).

Last updated: October 2026

Standard color code

MGL c. 82 § 40 says companies mark facilities by methods that follow the Common Ground Alliance and American Public Works Association (APWA) standards. The statute and 220 CMR 99.02 assign these colors:

  • Color Facility
  • Red Electric power lines, cables, conduit and lighting cables
  • Yellow Gas, oil, petroleum, steam or other gaseous materials
  • Orange Communications cables or conduit, alarm or signal lines
  • Blue Water, irrigation and slurry lines
  • Green Sewer and drain lines
  • Purple Reclaimed water, such as irrigation or slurry lines (220 CMR 99.02)
  • White The excavator's premark of proposed excavation

Pink Premarks where white would interfere with traffic or be hard to see, temporary survey marks, or marks distinguished from other color codes

How utilities mark (220 CMR 99.06)

Timing: within 72 hours , excluding Saturdays, Sundays and legal holidays, of the notice reaching the Dig Safe Center (§ 40B allows an agreed time instead). For long excavations, the company marks the first portion within 72 hours and the rest within a reasonable time.

Method: visible marking material such as paint on the ground above the facility, or color-coded stakes, flags or brush-type markers. Companies use the center-line method on public and private property.

Where practicable , marks show the facility's width (if over 2 inches) , material , changes in direction and terminus points .

Marks extend at least 15 feet beyond the premarked area (§ 40B: within 15 feet in any direction of the premarking).

Offset marks may be used where the surface above will be removed, uniformly aligned and showing the distance to the facility.

Historical paved areas may be marked with chalk, stakes, flags or brush markers instead of paint.

New facilities are marked as they are backfilled or installed.

No facilities? The company tells the excavator or otherwise shows that no facilities are present.

The safety zone

The statute defines the safety zone as a zone marked on the surface with the standard colors that contains the width of the facilities plus not more than 18 inches on each side . 220 CMR 99.06(2) adds that the facility must lie completely within the safety zone, no more than the width of the facility plus 18 inches on each side of the designated center line .

Worked example. A 12-inch gas main is marked on its center line. The facility can be anywhere within 12 + 18 + 18 = 48 12 + 18 + 18 = 48 12 + 18 + 18 = 48 inches, so a 4-foot-wide band, centered on the mark. Bucket teeth do not go into that band to "find" the pipe.

Excavating near marked facilities (MGL c. 82 § 40C; 220 CMR 99.07)

Wait 72 hours. No excavation within 72 hours of notification (99.07(1)).

Non-mechanical means near facilities. When excavating close to underground facilities, use non-mechanical means as necessary to avoid damage while locating them. These are tools powered by people, including air vacuum and air blowing methods designed to minimize contact. Mechanical means may only be used for the initial penetration of pavement, rock or similar material , after which non-mechanical methods take over (99.07(3)).

Protect the facility after it is exposed. Further excavation uses reasonable precautions against damage, including weakening of structural or lateral support , penetration or destruction of the pipe, main, wire or conduit or its protective coating .

Keep the marks alive. The excavator is responsible for maintaining the marks or placing offset marks in the standard colors, or for asking Dig Safe for re-marking (99.07(4)).

Re-marks. The company re-marks within 24 hours of the request, excluding Saturdays, Sundays and legal holidays (99.06(6); § 40C). The excavator suspends excavation in that area for 24 hours after requesting a re-mark (99.07(5)).

Unmarked facility found. If there is clear evidence of an unmarked facility, suspend excavating until Dig Safe is notified, and protect the facility (99.07(6)).

Abandoned facilities are removed only with the owning company's authorization and direction (99.07(7)).

Tip

Hand-digging methods and vacuum excavation are the usual ways to expose a facility inside the safety zone. Choose blunt tools and work slowly. A sharp tool or a bucket tooth can cut plastic gas service or fiber before the operator feels any resistance.

If a facility is damaged (220 CMR 99.07(8)–(10); § 40C)

  • Step Requirement
  • Gas escaping Call 911 immediately if the damage releases any regulated natural or other gas
  • Protect people Evacuate nearby structures if necessary

Notify the owner Report the damage to the facility owner or operator at the earliest practical moment (§ 40C: "immediately"), including damage only to the protective coating

  • No repairs Attempt no repairs unless directed by the facility owner or operator
  • DPU report Report the damage to the Department of Public Utilities within 30 days on the DPU form

Anyone else Any person who causes or becomes aware of damage notifies the owning company at the earliest practical moment

Crane setups near marked facilities

A crane outrigger is not an excavation tool, but it puts a heavy, concentrated load on the ground. When marks show a shallow gas service, conduit bank or sewer under the planned outrigger position, treat it as a ground-condition hazard. OSHA 1926.1402(c)(2) requires the controlling entity to tell the operator about utilities, voids and tanks beneath the setup area that are shown in its documents or otherwise known. Move the setup, or have a qualified person design mats or bridging so the load stays off the facility (Section 7.2).

Scenario practice

The "gentle tooth." An operator scrapes inside a yellow safety zone with the corner of a backhoe bucket to locate a 2-inch plastic gas service. The tooth snags the service and gas escapes. This is mechanical excavation inside the zone where non-mechanical means were required (99.07(3)). Required response: 911 immediately , evacuate as needed, notify the gas company, no repairs , and report to the DPU within 30 days. As a 230 CMR 6.08(2)(c)18 issue, the operator's license is also at risk.

Rain washes out the paint. After a heavy storm, the red marks on a trench line are gone. The excavator requests a re-mark and suspends excavation in that area for 24 hours while the company re-marks.