Study guide

10.2 Crane-Suspended Personnel Platforms (230 CMR 6.09(6) & OSHA 29 CFR 1926.1431)

Massachusetts Crane Operator Hoisting Engineer License

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: Massachusetts Hoisting Law (MGL Chapter 146)

1.1 MGL Chapter 146 §§ 53–54A: The Hoisting License Mandate, Exemptions & Penalties 1.2 MGL Chapter 146 §§ 57–67: Applications, Examinations, Appeals, License Term & Renewal

2 Chapter 2: Licensing Under 230 CMR 6.00

2.1 License Classes & Restrictions Under 230 CMR 6.10 2.2 Applying, Medical Qualification, the OPSI Exam & Renewal (230 CMR 6.02) 2.3 Temporary Permits, Continuing Education, Apprentices & Company Exemptions (230 CMR 6.03–6.07)

3 Chapter 3: 230 CMR 6.00 Definitions, Operating Rules & Enforcement

3.1 230 CMR 6.01: Scope, Key Definitions, Exempt Equipment & Adopted Standards 3.2 Operating Procedures Under 230 CMR 6.08: Inspections, Attention, Signals & Stop Authority 3.3 Special Requirements Under 230 CMR 6.09: Cranes, Derricks, Pile Drivers, Forklifts & Excavators 3.4 Incident Reporting, Investigations, Discipline & Variances (230 CMR 6.11–6.13)

4 Chapter 4: Crane Types, Working Parts & Load Charts

4.1 Crane Types & Working Parts by Restriction: Lattice, Derrick, Tower, Telescopic & Hydraulic Machines 4.2 Load Chart Fundamentals: Structural Strength vs. Stability Limits 4.3 Capacity Deductions & Calculating Net Allowable Capacity 4.4 Quadrants of Operation, Working Radius & Boom Angle Dynamics

5 Chapter 5: Advanced Lift Calculations & Multi-Crane Operations

5.1 Boom Deflection, Ground Leveling & Side-Loading Hazards 5.2 Wire Rope Reeving, Parts of Line & Single-Line Pull Limits 5.3 Center of Gravity, Weight Distribution & Multi-Crane (Tandem) Lifts

6 Chapter 6: Dig Safe, Underground Utilities & Trench Safety

6.1 Massachusetts Dig Safe Law (MGL c. 82 §§ 40–40E, 220 CMR 99.00): Premarking & Notice 6.2 Utility Color Codes, the 18-Inch Safety Zone, Excavating Near Facilities & Damage Response 6.3 Trench Safety Law, Excavation Hazards, Setbacks & Utility-Strike Emergencies

7 Chapter 7: Power Lines, Ground Conditions & Weather

7.1 Power Line Safety: OSHA 1926.1408–1411, Table A & Table T 7.2 Ground Bearing Pressure, Outrigger Setup & Cribbing Sizing 7.3 Wind, Storms, Lightning, Ice & Cold: Weather Limits for Crane Work

8 Chapter 8: Rigging Principles, Slings & Hardware

8.1 Sling Types: Synthetic, Wire Rope, and Alloy Steel Chain Slings 8.2 Sling Angle Calculations & Tension Formulas 8.3 Rigging Hardware, Shackles, Hooks & Below-the-Hook Lifting Devices

9 Chapter 9: Wire Rope & Crane Inspection

9.1 Wire Rope Construction, Damage Assessment & Removal Criteria (OSHA 1926.1413) 9.2 Crane Inspections, Safety Devices & Operational Aids (230 CMR 6.08; OSHA 1926.1412, 1415, 1416)

10 Chapter 10: Hand Signals & Personnel Hoisting

10.1 Standard Hand Signals, Voice & Radio Signals and Signal Person Qualification 10.2 Crane-Suspended Personnel Platforms (230 CMR 6.09(6) & OSHA 29 CFR 1926.1431)

10.2 Crane-Suspended Personnel Platforms (230 CMR 6.09(6) & OSHA 29 CFR 1926.1431)

Key Takeaways Explain This Topic AI

Hoisting personnel on the load or hook is prohibited unless conventional access to the elevated worksite would be impossible or more hazardous (230 CMR 6.09(6)).

A crane or derrick used to hoist personnel must be uniformly level within one percent of level grade and on a firm foundation (230 CMR 6.09(6)(a)).

Wire rope used for personnel lifting must have a minimum safety factor of seven, and rotation-resistant rope a minimum safety factor of ten (230 CMR 6.09(6)(a)).

The loaded personnel platform and its rigging must not exceed 50% of the crane's rated capacity for the radius and configuration (230 CMR 6.09(6)(a); OSHA 1926.1431(d)).

The platform and rigging are proof tested to 125% of the platform's rated capacity and held suspended for five minutes before personnel are hoisted at a jobsite (230 CMR 6.09(6)(f); OSHA 1926.1431(j)).

Last updated: October 2026

When personnel hoisting is allowed

230 CMR 6.09(6) prohibits hoisting, lowering, swinging or traveling while anyone is on the load or hook , except when conventional means of access to an elevated worksite, such as scaffolds or ladders, would be impossible or more hazardous . OSHA 29 CFR 1926.1431 states the same test: the employer must show that conventional means would be more hazardous or not possible because of structural design or worksite conditions. Schedule pressure is never a reason.

The Massachusetts text refers to the older federal rule (29 CFR 1926.550(g)(3)–(8)). Today's federal rule is 29 CFR 1926.1431 . Under 230 CMR 6.08(1), where the two differ, the higher standard for safety prevails .

Crane or derrick requirements

Requirement 230 CMR 6.09(6) OSHA 1926.1431

Foundation and level Firm foundation; uniformly level within one percent of level grade Same 1%, on footing a qualified person has determined is sufficiently firm; all outriggers extended and locked, same extension

Operator At the controls whenever the engine is running and the platform is occupied; full control of platform movement; moves slowly and cautiously without jerking Operator at the controls, on site and in view, while the platform is occupied (platforms without controls)

Wire rope Personnel wire rope safety factor at least 7 ; rotation-resistant rope at least 10 Rigging hardware and hooks capable of 5× the maximum intended load; 10× for rotation-resistant rope slings

Capacity Loaded platform plus rigging not over 50% of rated capacity for the radius and configuration Total load including hook, load line and rigging not over 50% (except during proof testing)

Brakes When the occupied platform is stationary, all brakes and locking devices set Load and boom hoist brakes, swing brakes and pawls or dogs engaged

Instruments Boom angle indicator visible to the operator (variable-angle booms); boom length indicator or an accurate radius determination before the lift (telescoping booms); anti-two-block device or two-block damage-prevention feature Required devices must work. No alternative measures are allowed during personnel hoisting. Controlled load lowering; free fall prohibited

  • Other load lines No lifts on another load line while personnel are hoisted Same, except pile driving
  • Platform design and condition

Designed with a minimum safety factor of five , by a professional engineer or a qualified person competent in structural design . The suspension system minimizes tipping as occupants move. OSHA adds that the platform must stay within 10 degrees of level .

Standard guardrail system , enclosed from the toeboard to the mid-rail (OSHA: solid material or expanded metal with openings no larger than ½ inch); an inside grab rail ; adequate headroom ; a plate or permanent marking showing the platform's weight and rated capacity .

Overhead protection and hard hats where occupants are exposed to falling objects.

Access gates must not swing outward during hoisting and must have a restraining device against accidental opening. OSHA allows an outward-swinging gate only where an inward gate is infeasible, such as on a one-person platform.

Rough edges ground smooth . Welding done by a qualified (certified) welder familiar with the weld grades and materials in the design.

Loading and rigging

Never load beyond the platform's rated capacity . Carry only instructed personnel with the tools, equipment and materials for the task, secured and evenly distributed .

A wire rope bridle connects to a master link or shackle so the load divides evenly among the legs. Bridles and rigging for the platform are used for no other purpose.

Hooks must be closed and locked to eliminate the throat opening, or use an alloy anchor-type shackle with a bolt, nut and retaining pin . "Mousing" (wrapping wire across the hook opening) is not permitted.

Trial lift, inspection and proof test

Trial lift: the unoccupied platform, loaded at least to the anticipated lift weight , is lifted from ground level (or the entry point) to each location where it will be positioned, immediately before placing personnel on it. OSHA requires the trial lift immediately prior to each shift in which personnel will be hoisted, and again whenever the crane is moved to a new location, returned to a previous one , or the lift route changes (unless a competent person finds no new hazard).

During the trial lift the operator checks that systems, controls and safety devices work, that there are no interferences , and that every configuration needed stays within the 50% limit .

After the trial lift, the platform is hoisted a few inches and inspected to confirm it is secure and balanced .

Before employees are hoisted, check that hoist ropes are free of kinks , multiple-part lines are not twisted around each other, the primary attachment is centered over the platform , there is no slack in the wire rope, and all ropes are properly seated on drums and sheaves.

A competent person visually inspects the crane or derrick, the platform and the base support or ground for defects or adverse effects. Defects are corrected before hoisting personnel.

Proof test: when the platform is first brought to the jobsite and after any repair or modification , before personnel are hoisted, the platform and rigging are loaded to 125% of the platform's rated capacity , with the load evenly distributed, and held suspended for five minutes . A competent person inspects. Any problem is fixed and the test repeated. OSHA allows the proof test to run concurrently with the trial lift.

Pre-lift meeting

Held before the trial lift at each new work site , and repeated for any newly assigned employee. Attendees: the crane or derrick operator, signal person(s), the employees to be lifted, and the person responsible for the hoisting operation . The meeting reviews the requirements and the procedures to be followed.

Safe work practices

Occupants:

Use tag lines unless doing so creates an unsafe condition.

Keep all body parts inside the platform while it is raised, lowered or positioned.

Secure the platform to the structure before entering or exiting, unless that creates an unsafe condition.

Wear a body harness with a lanyard . 230 CMR 6.09(6)(h)4 allows the lanyard to attach to the lower load block or overhaul ball, or to a structural member within the platform . OSHA 1926.1431(k)(10) requires attachment to a structural member within the personnel platform . Because the higher standard prevails, tie off to the platform's structural member . Over water, the over-water rules apply instead (OSHA 1926.106).

Stay in view of, or in direct communication with , the operator or signal person.

Operators:

Never leave the controls while the engine is running or the platform is occupied.

Stop all hoisting when there are signs of dangerous weather or other impending danger. Under OSHA, if wind (sustained or gusts) exceeds 20 mph at the platform , a qualified person must decide whether lifting is safe, and it must not begin or continue if not.

No lifts on any other load line while personnel are hoisted.

OSHA 1926.1431(n): no personnel hoisting within 20 feet of a power line up to 350 kV, or within 50 feet of one over 350 kV (except work under OSHA Subpart V).

Moving the crane with personnel aboard (230 CMR 6.09(6)(i))

Travel is prohibited unless the employer shows it is the least hazardous way, or portal, tower or locomotive cranes are used. When traveling: travel is restricted to a fixed track or runway , limited to the boom's radius during the lift, with the boom parallel to the direction of travel , after a complete trial run . For rubber-tired cranes, check tire condition and pressure and apply chart capacities that keep the lift under the 50% limit .

Worked capacity check

A crane's chart rates 9,600 lb at the planned radius and configuration. The platform weighs 950 lb and is rated 1,000 lb . The bridle and shackles weigh 120 lb , and the hook block 380 lb .

50% limit: 9,600 × 0.50 = 4,800 9{,}600 \times 0.50 = 4{,}800 9 , 600 × 0.50 = 4 , 800 lb total.

Fixed weight counted against it (OSHA counts hook, load line and rigging): 950 + 120 + 380 = 1,450 950 + 120 + 380 = 1{,}450 950 + 120 + 380 = 1 , 450 lb.

Available for people, tools and materials under the crane limit: 4,800 − 1,450 = 3,350 4{,}800 - 1{,}450 = 3{,}350 4 , 800 − 1 , 450 = 3 , 350 lb. But the platform's own rating of 1,000 lb governs , because the platform may never be loaded beyond its rated capacity.

Proof test load: 1,000 × 1.25 = 1,250 1{,}000 \times 1.25 = 1{,}250 1 , 000 × 1.25 = 1 , 250 lb, evenly distributed, held for 5 minutes.