Study guide
17.1 Impossibility, Impracticability, Frustration & Discharge
Multistate Bar Examination MBE
Track your progress as you read
Finished sections get a check mark.
1 MBE Overview, Scoring & Study Strategy
0.1 About the Multistate Bar Examination 0.2 MBE Question Mechanics & Test Pacing 0.3 High-Yield Preparation & Error Analysis Strategy
2 Civil Procedure I: Subject-Matter Jurisdiction, Removal & Governing Law
1.1 Subject-Matter Jurisdiction: Federal Question & Diversity 1.2 Supplemental Jurisdiction & Removal 1.3 The Erie Doctrine & Federal Common Law
3 Civil Procedure II: Personal Jurisdiction, Venue & Provisional Relief
2.1 Personal Jurisdiction & Service of Process 2.2 Venue, Transfer & Forum Non Conveniens 2.3 Preliminary Injunctions, TROs & Pretrial Conferences
4 Civil Procedure III: Pleadings, Joinder & Class Actions
3.1 Pleadings, Amendments & Rule 11 3.2 Joinder of Claims & Parties, Intervention & Interpleader 3.3 Class Actions & the Class Action Fairness Act
5 Civil Procedure IV: Discovery, Pretrial Motions & Jury Trials
4.1 Discovery, Disclosure & Sanctions 4.2 Rule 12 Motions, Summary Judgment, Defaults & Dismissals 4.3 Jury Trials: The Right to a Jury, Selection, Instructions & Verdicts
6 Civil Procedure V: Post-Trial Motions, Preclusion & Appeals
5.1 Judgment as a Matter of Law, New Trials & Relief from Judgment 5.2 Claim & Issue Preclusion 5.3 Appealability & Standards of Review
7 Constitutional Law I: The Federal Judicial Power
6.1 Judicial Review, Federal Jurisdiction & State Sovereign Immunity 6.2 Justiciability: Standing, Ripeness, Mootness & Political Questions
8 Constitutional Law II: The Powers of Congress
7.1 Enumerated Powers: Commerce, Taxing & Spending 7.2 War, Foreign Affairs, Civil Rights Enforcement & Other Congressional Powers
9 Constitutional Law III: The Presidency & Separation of Powers
8.1 Presidential Powers: Chief Executive, Commander in Chief, Foreign Affairs & Appointments 8.2 Interbranch Relations: Nondelegation, Presentment, Legislative Limits & Immunities
10 Constitutional Law IV: Federalism & State Power
9.1 The Tenth Amendment, Anti-Commandeering & Intergovernmental Immunities 9.2 Preemption, the Dormant Commerce Clause & Congressional Authorization
11 Constitutional Law V: State Action, Due Process & Equal Protection
10.1 State Action & Procedural Due Process 10.2 Substantive Due Process: Fundamental Rights & Other Liberty Interests 10.3 Equal Protection: Classifications, Scrutiny & Fundamental Rights
12 Constitutional Law VI: Takings & Other Economic Protections
11.1 The Takings Clause 11.2 Contracts Clause, Ex Post Facto Laws, Bills of Attainder & Privileges and Immunities
13 Constitutional Law VII: First Amendment Freedoms
12.1 Freedom of Religion: Establishment & Free Exercise 12.2 Freedom of Speech: Content Regulation, Forums, Unprotected Categories & Commercial Speech 12.3 Speech in Government Settings, Expressive Conduct, Prior Restraints, Press & Association
14 Contracts I: Formation—Offer, Acceptance & Consideration
13.1 Governing Law, Offers & Termination of the Power of Acceptance 13.2 Acceptance, Silence, Unilateral Contracts & the Battle of the Forms 13.3 Consideration, Modification, Promissory Estoppel & Restitution
15 Contracts II: Defenses to Enforcement
14.1 Capacity, Duress, Undue Influence, Unconscionability, Illegality & Public Policy 14.2 Mistake, Misunderstanding, Misrepresentation & Nondisclosure 14.3 The Statute of Frauds
16 Contracts III: Contract Terms, Interpretation & Warranties
15.1 Parol Evidence, Interpretation & Implied Terms 15.2 Warranties in the Sale of Goods
17 Contracts IV: Conditions, Performance & Breach
16.1 Conditions & Excuse of Conditions 16.2 Substantial Performance, Material Breach, Repudiation & Adequate Assurance 16.3 UCC Performance: Tender, Rejection, Cure, Revocation, Installments & Risk of Loss
18 Contracts V: Excuse, Discharge & Remedies
17.1 Impossibility, Impracticability, Frustration & Discharge 17.2 Expectation Damages, Consequential Damages, Mitigation & UCC Damage Formulas 17.3 Reliance, Restitution, Liquidated Damages, Specific Performance & Rescission
19 Contracts VI: Third-Party Beneficiaries, Assignment & Delegation
18.1 Third-Party Beneficiaries 18.2 Assignment of Rights & Delegation of Duties
20 Criminal Law I: General Principles, Defenses, Inchoate Crimes & Parties
19.1 Criminal Acts, Mental States, Mistake, Causation & Jurisdiction 19.2 Responsibility & Defenses: Insanity, Intoxication, Infancy, Justification & Excuse 19.3 Inchoate Crimes: Solicitation, Conspiracy & Attempt 19.4 Parties to Crime: Principals, Accomplices & Accessories After the Fact
21 Criminal Law II: Homicide, Property Crimes & Crimes Against the Person
20.1 Homicide: Murder, Felony Murder & Manslaughter 20.2 Theft Offenses, Receiving Stolen Property, Robbery & Burglary 20.3 Assault, Battery, Sexual Offenses, Kidnapping, Arson & Possession Offenses
22 Criminal Procedure I: The Fourth Amendment & the Exclusionary Rule
21.1 Fourth Amendment: Searches, Seizures, Arrests & Warrants 21.2 Exceptions to the Warrant Requirement & Special Needs Searches 21.3 The Exclusionary Rule, Standing & Fruit of the Poisonous Tree
23 Criminal Procedure II: Confessions, Identification & the Right to Counsel
22.1 Confessions, Miranda & the Privilege Against Self-Incrimination 22.2 Pretrial Identification & the Sixth Amendment Right to Counsel
24 Criminal Procedure III: Trial Rights, Pleas, Double Jeopardy, Punishment & Appeals
23.1 Fair Trial, Jury & Confrontation Rights, Guilty Pleas & Burdens of Proof 23.2 Double Jeopardy, Cruel & Unusual Punishment, Appeal & Error
25 Evidence I: Presenting Evidence, Relevance & Witnesses
24.1 Introducing Evidence: Judge & Jury, Objections, Judicial Notice & Presumptions 24.2 Relevance, Rule 403 & Real, Demonstrative & Illustrative Evidence 24.3 Witnesses: Competency, Mode of Examination, Refreshing Recollection & Exclusion
26 Evidence II: Impeachment, Character & Other Acts
25.1 Impeachment: Bias, Inconsistent Statements, Capacity, Contradiction & Rehabilitation 25.2 Impeachment by Character for Truthfulness, Specific Instances & Criminal Convictions 25.3 Character Evidence: The Propensity Ban, Criminal-Case Exceptions & Methods of Proof 25.4 Other Crimes, Wrongs & Acts; Habit & Routine Practice; Sexual Misconduct Rules
27 Evidence III: Opinions, Authentication, Documents, Privileges & Policy Exclusions
26.1 Lay & Expert Opinion Testimony 26.2 Authentication & Identification 26.3 Best Evidence Rule, Summaries & the Rule of Completeness 26.4 Privileges: Attorney-Client, Spousal, Psychotherapist & Other Privileges 26.5 Policy Exclusions: Remedial Measures, Compromise, Medical Payments, Pleas & Insurance
28 Evidence IV: Hearsay & Its Exceptions
27.1 The Hearsay Definition & Statements That Are Not Hearsay 27.2 Hearsay Exclusions: Prior Statements of Testifying Witnesses & Opposing Party Statements 27.3 Hearsay Exceptions Not Requiring Unavailability (FRE 803) 27.4 Unavailability Exceptions, Residual Exception, Multiple Hearsay & Confrontation
29 Real Property I: Estates, Concurrent Ownership & Leaseholds
28.1 Present Estates, Future Interests & Waste 28.2 Rule Against Perpetuities, Restraints on Alienation, Fair Housing & Conflicts of Law 28.3 Concurrent Ownership: Tenancy in Common, Joint Tenancy & Tenancy by the Entirety 28.4 Landlord & Tenant: Tenancies, Duties, Remedies & Transfers
30 Real Property II: Rights in Land
29.1 Easements, Profits & Licenses 29.2 Real Covenants, Equitable Servitudes & Common Interest Communities 29.3 Fixtures 29.4 Support, Water Rights & Zoning
31 Real Property III: Real Estate Contracts
30.1 Real Estate Contracts: Brokers, Formation, Performance & Remedies 30.2 Marketable Title, Equitable Conversion, Options, Disclosure & Merger
32 Real Property IV: Mortgages & Security Devices
31.1 Mortgages & Security Devices: Theories, Pre-Foreclosure Rights & Transfers 31.2 Discharge, Foreclosure, Redemption & Priorities
33 Real Property V: Titles
32.1 Adverse Possession 32.2 Deeds, Delivery, Title Covenants & Transfers at Death 32.3 Recording Acts, Title Assurance & Liens
34 Torts I: Intentional Torts
33.1 Intent & Intentional Torts Against the Person 33.2 Intentional Torts Against Property 33.3 Defenses & Privileges for Intentional Torts
35 Torts II: Negligence—Duty, Standard of Care & Proof
34.1 Duty: Foreseeable Plaintiffs, Failure to Act & Control of Others 34.2 Standard of Care, Custom, Negligence Per Se & Res Ipsa Loquitur
36 Torts III: Negligence—Causation, Damages & Limits on Liability
35.1 Actual Cause, Joint & Several Liability, Contribution & Indemnity 35.2 Proximate Cause, Damages, Survival & Wrongful Death 35.3 Owners & Occupiers of Land 35.4 Negligent Infliction of Emotional Distress, Intangible Harms & Pure Economic Loss
37 Torts IV: Vicarious Liability & Negligence Defenses
36.1 Vicarious Liability: Employees, Independent Contractors & Others 36.2 Defenses to Negligence: Comparative Fault, Assumption of Risk & Immunities
38 Torts V: Strict Liability & Products Liability
37.1 Strict Liability: Animals & Abnormally Dangerous Activities 37.2 Products Liability: Theories, Defects & Defenses
39 Torts VI: Nuisance, Defamation, Privacy & Economic Torts
38.1 Private & Public Nuisance 38.2 Defamation & Invasion of Privacy 38.3 Misrepresentation & Interference with Business Relations
17.1 Impossibility, Impracticability, Frustration & Discharge
Key Takeaways Explain This Topic AI
A duty is discharged when, without the obligor's fault, a supervening event whose nonoccurrence was a basic assumption of the contract makes performance impracticable or substantially frustrates its principal purpose, unless the obligor assumed that risk (Restatement §§ 261, 265).
Classic impracticability events are the death or incapacity of a person necessary for performance, destruction of a specific thing necessary for performance, and supervening government regulation; increased cost excuses performance only when it is extreme and results from an unforeseen contingency (Transatlantic Financing).
Under UCC § 2-613, if goods identified when the contract was made are totally destroyed without fault before risk of loss passes, the contract is avoided; under § 2-615, a seller whose capacity is partly affected must allocate production fairly and notify buyers, who may terminate or accept their allocation (§ 2-616).
Frustration of purpose applies when both parties understood the principal purpose and an unforeseen event destroys the value of performance even though performance remains possible (Krell v. Henry).
Duties may also be discharged by mutual rescission of executory contracts, release, novation, substituted contract, or accord and satisfaction; an executory accord suspends the original duty, and if the debtor breaches it, the creditor may enforce either the accord or the original duty.
Last updated: September 2026
17.1 Impossibility, Impracticability, Frustration & Discharge
Excuse doctrines allocate the risk of events that neither party caused and the contract did not address. Before applying them, check the contract: a force majeure clause, a fixed-price term, or a risk-allocation clause may already answer the question. Discharge by later agreement is covered in the second half of this section.
1. Supervening Changed Circumstances: Impossibility, Impracticability & Frustration
After contract formation, external events may fundamentally disrupt the contractual equilibrium. Modern contract law recognizes three distinct doctrines that excuse performance: ┌───────────────────────┬────────────────────────────────────────────────────────┐
- │ Doctrine │ Core Focus & Legal Threshold │
- ├───────────────────────┼────────────────────────────────────────────────────────┤
- │ Impossibility │ OBJECTIVE impossibility: performance cannot physically │
- │ │ or legally be done by ANYONE ('The thing cannot be │
- │ │ done', not 'I cannot do it'). │
- ├───────────────────────┼────────────────────────────────────────────────────────┤
- │ Impracticability │ Extreme, excessive, unreasonable cost, difficulty, or │
- │ (UCC § 2-615 / R. 261)│ injury caused by unforeseen supervening contingency; │
- │ │ non-occurrence was a basic assumption of contract. │
- ├───────────────────────┼────────────────────────────────────────────────────────┤
- │ Frustration of Purpose│ Value of performance virtually destroyed; mutually │
- │ (*Krell v. Henry*) │ understood principal foundation eliminated by event. │
- └───────────────────────┴────────────────────────────────────────────────────────┘
- A. Common Doctrinal Elements
To discharge contractual performance under any of the three doctrines, four baseline elements must be met:
- A supervening event occurred after contract formation;
- The non-occurrence of that event was a basic assumption on which the contract was made;
- The event occurred without the fault or negligence of the party seeking excuse; AND
The party seeking excuse did not explicitly or implicitly assume the risk of the event under the terms of the contract or trade usage.
B. Objective Impossibility
Impossibility discharges performance only when it is objective ("no one can do this") rather than subjective ("I personally cannot do this due to insolvency, lack of funds, or personal inability").
The Three Classical Categories of Impossibility:
Death or Incapacity of an Essential Person:
Applies only where the contract contemplates personal performance by a specific individual possessing unique skill, talent, or personal characteristics (e.g., portrait painter, famous singer, specialized consultant).
Does not apply to ordinary service contracts, construction agreements, or payment obligations, which bind the promisor's estate.
Destruction or Deterioration of Subject Matter ( Taylor v. Caldwell (1863)):
In Taylor v. Caldwell , the defendant agreed to rent the Surrey Gardens and Music Hall for a series of concerts. Before the first concert, the hall accidentally burned to the ground. The court held that because the continued existence of the specific hall was essential to the performance, destruction of the hall discharged both parties from their obligations.
Source Specificity Requirement: Destruction of goods excuses a seller only if the specific source of supply was identified in the contract (e.g., "all oranges grown on my 40-acre Sunny Valley orchard"). If a seller contracts simply to sell "10,000 bushels of oranges" (fungible goods) and the seller's orange grove freezes, performance is not impossible —the seller must purchase substitute oranges on the open market.
Contractor Rule (New Construction vs. Renovation):
New Construction: Destruction of a building under construction by storm or fire does not discharge the builder, who can still rebuild and remains bound, although courts may excuse the resulting delay.
Renovation / Repair of Existing Structure: Destruction of the existing building discharges the contractor, who can recover in restitution for the value of work completed prior to destruction.
Supervening Illegality or Government Prohibition:
If a statute, executive order, or judicial decree enacted after contract formation makes the promised performance illegal, performance is discharged.
C. Commercial Impracticability (UCC § 2-615 & Restatement § 261)
Under modern law, actual physical impossibility is not required. Performance is excused under commercial impracticability if performance can only be accomplished at excessive and unreasonable cost, difficulty, or hazard.
The Extreme Cost Threshold
Market Fluctuations Do Not Excuse: Ordinary increases in performance costs, inflation, supply shortages, or market price collapses do not discharge duties. Fixed-price contracts are designed precisely to allocate the risk of ordinary market fluctuations.
Catastrophic Events: To discharge performance, the cost increase must be catastrophic, severe, and triggered by an unforeseen contingency (e.g., war, international embargo, crop blight, canal closure) that alters the essential nature of performance.
UCC § 2-615 Partial Impracticability (Allocation): If an unforeseen contingency affects only a portion of the seller's capacity to deliver (e.g., an international fuel embargo), the seller is not completely discharged. The seller must allocate production and deliveries among customers in a manner that is fair and reasonable, seasonably notifying buyers of the estimated quotas.
D. Frustration of Purpose ( Krell v. Henry (1903))
Under the doctrine of frustration of purpose , performance remains completely physically and legally possible, but a supervening event has completely or virtually destroyed the mutually understood principal purpose and value of the transaction for one party.
Canonical Origin: Krell v. Henry
The defendant rented a flat with a balcony overlooking the royal procession route for two days for the sole purpose of viewing the coronation procession of King Edward VII. The coronation was postponed due to the King's acute appendicitis surgery. The landlord sued for the unpaid balance.
Holding: The English Court of Appeal discharged the renter. Although the physical rooms were still available, the coronation procession was the known foundation of the contract. The supervening cancellation completely destroyed the purpose of the agreement.
Required Elements for Frustration of Purpose:
The supervening event must virtually destroy the entire value of the transaction to the party;
The principal purpose must have been understood by both parties at the time of contracting (a unilateral secret purpose does not suffice);
The non-occurrence of the frustrating event was a basic assumption of the contract;
The party seeking discharge was not at fault and did not assume the risk.
Example of No Frustration: A retailer leases a storefront in a shopping mall to sell athletic shoes. The mall's anchor department store goes bankrupt, reducing customer foot traffic by 40%. The retailer's lease is not frustrated; the storefront can still be used for retail sales, and reduced profitability is an inherent business risk.
Comparison: Impossibility vs. Impracticability vs. Frustration of Purpose
Doctrinal Issue Objective Impossibility Commercial Impracticability Frustration of Purpose
Governing Authority Restatement (Second) §§ 262–264 (specific applications of § 261) UCC § 2-615 / Restatement § 261 Restatement (Second) § 265
Physical Feasibility Performance physically or legally impossible Performance physically possible but excessively burdensome Performance 100% physically and commercially possible
Core Threshold No human being can perform ("It cannot be done") Severe, extreme, unforeseen cost or difficulty Value of performance completely destroyed for one party
Classic Fact Patterns Death of unique artisan; destruction of identified subject matter; supervening law War, embargo, unforeseen natural disaster shutting down sole source Cancellation of unique event that was the mutual reason for contracting
Price / Market Shifts Never an excuse Insufficient unless catastrophic spike caused by unforeseen embargo Never an excuse for profitability decline
Risk Allocation Party assuming risk cannot claim excuse Party assuming risk cannot claim excuse Party assuming risk cannot claim excuse
- Applying the Excuse Doctrines
- Cost Increases and Changed Routes
Excused: A contractor that agreed to take gravel from a landowner's property was excused when the remaining gravel lay below water and could be extracted only at about ten times the normal cost ( Mineral Park Land Co. v. Howard , Cal. 1916).
Not excused: A shipper that had to sail around the Cape of Good Hope when the Suez Canal closed was not excused, because the longer route was still practicable and increased costs by only a modest percentage ( Transatlantic Financing Corp. v. United States , D.C. Cir. 1966).
UCC Rules for Goods
Casualty to identified goods (§ 2-613): If goods identified when the contract was made are destroyed without fault of either party before risk of loss passes to the buyer, a total loss avoids the contract. If the loss is partial, or the goods have deteriorated so they no longer conform, the buyer may either avoid the contract or accept the goods with an allowance from the price, but has no further claim against the seller.
Substituted performance (§ 2-614): If the agreed berthing, loading, unloading, or type of carrier becomes unavailable without fault, but a commercially reasonable substitute is available, that substitute must be tendered and accepted.
Allocation and notice (§ 2-615): A seller excused in part must allocate production and deliveries among customers in a fair and reasonable manner and must seasonably notify buyers of any delay or nondelivery and of their estimated quota.
Buyer's response (§ 2-616): After receiving notice, a buyer may terminate the unexecuted portion of the contract or modify it by agreeing to take its available quota. If the buyer does not respond within a reasonable time not exceeding 30 days, the contract lapses as to the affected deliveries.
Temporary and Partial Excuse; Restitution
Temporary impracticability suspends the duty only while it lasts, unless performance after the delay would be materially more burdensome (Restatement § 269).
Partial impracticability leaves a duty to render whatever part of the performance remains practicable (Restatement § 270).
Restitution after excuse: Either party may recover the value of benefits conferred by part performance before the discharging event, and courts may protect reliance to avoid injustice (Restatement §§ 272, 377). A painter whose client's house burns down midway through the job may recover the reasonable value of work done before the fire.
Force majeure clauses: Contract clauses excusing performance for listed events are enforced according to their terms and may be broader or narrower than the common-law doctrines.
2. Discharge of Duties
An absolute contractual duty may be discharged without breach by events occurring after contract formation: ┌───────────────────────┬────────────────────────────────────────────────────────┐
- │ Discharge Mechanism │ Core Legal Requirements & Effects │
- ├───────────────────────┼────────────────────────────────────────────────────────┤
- │ Accord & Satisfaction │ Accord: agreement to accept different performance to │
- │ │ satisfy existing duty. Suspends original duty. │
- │ │ Satisfaction: execution of accord. Discharges both. │
- ├───────────────────────┼────────────────────────────────────────────────────────┤
- │ Novation │ Agreement substituting a new obligor for an original │
- │ │ obligor. Requires consent of ALL parties. Discharges. │
- ├───────────────────────┼────────────────────────────────────────────────────────┤
- │ Mutual Rescission │ Mutual agreement to discharge executory duties. │
- │ │ Both parties must have remaining performance due. │
- ├───────────────────────┼────────────────────────────────────────────────────────┤
- │ Release │ Writing signed by obligee releasing obligor from duty. │
- │ │ Supported by consideration (or statutory substitute). │
- ├───────────────────────┼────────────────────────────────────────────────────────┤
- │ Account Stated │ Agreement between parties settling liquidated balance. │
- └───────────────────────┴────────────────────────────────────────────────────────┘
- A. Accord and Satisfaction
The Accord: An agreement in which an obligee promises to accept a substituted, different performance in full satisfaction of an existing contractual duty.
Effect of Accord: An accord does not extinguish the original duty; it merely suspends the obligee's right to enforce the original contract until the accord performance is completed or breached.
The Satisfaction: The actual performance of the accord agreement.
Effect of Satisfaction: Once satisfaction occurs, both the accord agreement and the original underlying duty are completely discharged.
Breach of the Accord:
If Debtor Breaches: The creditor may sue either on the original underlying obligation OR on the accord agreement.
If Creditor Breaches (sues on original debt before debtor breaches the accord): Debtor can raise the accord as an equitable defense to suspend or dismiss the action.
Unliquidated / Disputed Debts ("Check Cashing"): Under UCC § 3-311, if a debtor sends a check marked "Payment in full" for an unliquidated or honestly disputed debt, and the creditor cashes/deposits the check, an accord and satisfaction is achieved immediately, discharging the debt even if the creditor writes "Under protest" on the check.
B. Novation
A novation occurs when the parties to an existing contract enter into a new agreement that substitutes a new party to take over the performance obligations of an original party, with the express or implied agreement of all three parties (obligee, original obligor, and new obligor).
Legal Effect: A valid novation completely discharges the original obligor from all further contractual liability.
MBE Distinction (Novation vs. Delegation):
In a delegation , the delegator remains secondarily liable on the contract if the delegatee defaults.
In a novation , the obligee expressly agrees to release the original obligor and look solely to the new party. The original party's liability is extinguished.
C. Mutual Rescission
An agreement between the parties to cancel their contract.
Executory Requirement: Mutual rescission is legally effective only if both parties still have executory duties remaining to be performed under the contract.
Unilateral Performance Complete: If one party has fully performed their contractual duties, a mutual rescission agreement is void for lack of consideration , because the fully performing party is giving up rights without receiving any legal return value (unless supported by a formal release or new consideration).
D. Release and Destruction of Subject Matter
Release: A formal written document signed by the obligee releasing the obligor from a contractual duty. Under modern law, a signed writing or formal release discharges the duty without separate consideration in most commercial jurisdictions.
Destruction of Subject Matter: If the specific, unique subject matter essential to performance is destroyed without fault of either party, all executory duties are discharged under the doctrine of impossibility (e.g., concert hall burns down before scheduled performance).
Substituted Contracts Versus Executory Accords
Executory accord: The creditor agrees to accept a different performance in the future. The original duty is suspended, not discharged, until the substituted performance is rendered (Restatement § 281).
Substituted contract: If the creditor agrees to accept the new promise itself—rather than its performance—in immediate satisfaction of the original duty, the original duty is discharged at once, and the creditor's only remedy is on the new contract (Restatement § 279).
How to tell: Courts look at the parties' intent. When the original claim was disputed or unliquidated, or the new agreement is formal and comprehensive, courts more readily find a substituted contract; when the creditor bargains for actual performance of a small, undisputed debt, courts usually find an executory accord.