Study guide
10.1 Gas Piping Installation, Testing & Purging
Maryland Journeyman Plumber Journey Plumber/Gas Fitter
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Maryland Licensing, Code Administration & the Exam
1.1 Maryland Plumbing Regulations & Licensing 1.2 The Journey Plumber/Gas Fitter Exam: Format, References & Open-Book Strategy
2 Chapter 2: Job-Site Safety & OSHA 29 CFR 1926
2.1 OSHA Construction Safety, PPE & Hazard Communication 2.2 Excavation & Trenching Safety (29 CFR 1926 Subpart P) 2.3 Confined Spaces, Ladders, Scaffolds & Hot Work
3 Chapter 3: Materials, Uses & Specifications
3.1 Approved Plumbing Materials, Pipes & Jointing 3.2 Hanger Spacing, Structural Protection & System Testing 3.3 Valves, Fittings, Fitting Selection & Prohibited Connections
4 Chapter 4: Sanitary Drainage & Waste Piping
4.1 Drainage Fixture Units (DFU) & Drain Pipe Sizing 4.2 Building Sewers, Cleanout Clearances & Underground Piping 4.3 Indirect & Special Waste Systems 4.4 Backwater Valves, Sump Pumps & Sewage Ejectors
5 Chapter 5: Venting Systems
5.1 Vent Sizing, Termination & Soil Stacks 5.2 Individual, Branch & Common Vents 5.3 Wet Venting & Circuit Venting 5.4 Air Admittance Valves (AAVs) & Special Venting
6 Chapter 6: Traps, Interceptors & Backwater Valves
6.1 Traps, Trap Seals & Trap Arm Requirements 6.2 Grease, Oil & Special-Waste Interceptors and Separators
7 Chapter 7: Water Supply & Distribution Systems
7.1 Water Supply Sizing & Fixture Unit (WSFU) Method 7.2 Water Heaters & Safety Devices 7.3 Pressure Regulation, Booster Systems & Disinfection 7.4 Water Service Piping, Meters, Valves & System Protection
8 Chapter 8: Backflow Prevention & Cross-Connection Control
8.1 Backflow Prevention & Cross-Connection Control 8.2 Air Gaps, Vacuum Breakers & Their Application Limits 8.3 Double Check & Reduced Pressure Principle (RPZ) Assemblies 8.4 Backflow Assembly Field Testing Procedures & Gauge Use 8.5 Maryland Backflow Program: 32-Hour Course, Certification & Reporting
9 Chapter 9: Fuel Gas Fundamentals, Materials & Pipe Sizing
9.1 Fuel Gas Properties, Heating Values & IFGC Scope 9.2 Fuel Gas Pipe Sizing & Materials 9.3 Approved Gas Piping Materials, CSST & Bonding 9.4 Gas Pipe Sizing Tables: Longest-Length & Branch-Length Methods 9.5 LP-Gas Systems, NFPA 58 & Propane-Specific Rules
10 Chapter 10: Gas Piping Installation, Testing & Purging
10.1 Gas Piping Installation, Testing & Purging 10.2 Gas Piping Support, Protection, Prohibited Locations & Concealed Piping 10.3 Shutoff Valves, Drips, Unions, Sediment Traps & Appliance Connectors 10.4 Gas Meters, Regulators, Pressure Levels & Overpressure Protection 10.5 Gas Leak Detection, Odorization & Emergency Response
11 Chapter 11: Gas Appliance Venting & Combustion Air
11.1 Gas Appliance Venting & Combustion Air 11.2 Appliance Categories I-IV, Vent Materials & Vent Connectors 11.3 Chimney & Vent Sizing Tables (Type B, Masonry & Common Venting) 11.4 Vent Termination, Clearances & Direct-Vent Systems 11.5 Combustion Air: Indoor & Outdoor Methods and Opening Sizing
12 Chapter 12: Gas Appliance Installation & Service
12.1 Gas Water Heaters, Furnaces & Boilers: Installation Rules 12.2 Appliance Clearances to Combustibles, Access & Location Limits 12.3 Gas Appliance Troubleshooting, Combustion Analysis & CO Safety
13 Chapter 13: Plumbing Fixtures, Fittings & Appliances
13.1 Fixture Clearances, Accessibility & Installation 13.2 Water Conservation Standards & Flow Rates 13.3 Commercial & Specialty Fixture Requirements
14 Chapter 14: Plumbing Mathematics
14.1 Plumbing Math I: Areas, Volumes, Capacities & Water Weight 14.2 Plumbing Math II: Offsets, Travel, Grade & Pipe Layout 14.3 Plumbing Math III: Gas Math, Meter Readings, BTU & Pressure Conversions
10.1 Gas Piping Installation, Testing & Purging
Key Takeaways Explain This Topic AI
Fuel gas piping support spacing requires horizontal hangers every 6 ft for 1/2-inch pipe, 8 ft for 3/4-inch and 1-inch pipe, and 10 ft for 1-1/4-inch or larger pipe, with vertical piping supported at every floor level.
Underground fuel gas piping must be buried at a minimum depth of 12 inches below finished grade under IFGC 404.12, with an 8-inch exception for individual outdoor lights, grills and similar appliances (404.12.1), and equipped with an insulated yellow tracer wire (min #18 AWG) for non-metallic pipe.
Rough-in gas piping pressure tests must be conducted at a minimum of 3 psi (or 1.5 times the maximum working pressure) using air, nitrogen, or CO2 for a minimum duration of 10 minutes.
Oxygen must NEVER be used as a test medium for gas piping due to severe explosive hazards when mixed with residual hydrocarbons or oil.
Purging of gas lines larger than specified threshold diameters/lengths must be discharged outdoors to a safe location away from ignition sources to prevent flammable atmosphere accumulation indoors.
Last updated: July 2026
10.1 Gas Piping Installation, Testing & Purging
Proper physical support, underground burial protection, pressure testing, and safe purging protocols are vital components of fuel gas system installation under the International Fuel Gas Code (IFGC Section 406) and Maryland Plumbing Regulations. Journeyman candidates must know exact hanger spacing intervals, underground burial depths, pressure testing values, gauge limitations, and safety procedures for purging gas lines prior to commissioning.
1. Gas Piping Support & Hanger Spacing
Gas piping must be supported with pipe hooks, metal straps, bands, or hangers of suitable strength and material to prevent sagging, vibration, and strain on joints.
IFGC Pipe Support Spacing Requirements
- Piping Material & Size Max Horizontal Support Spacing Max Vertical Support Spacing
- 1/2" Steel Pipe 6 feet Every floor level
- 3/4" & 1" Steel Pipe 8 feet Every floor level
- 1-1/4" & Larger Steel Pipe (Horiz.) 10 feet Every floor level
- 1/2" O.D. Smooth-Wall Tubing 4 feet Every floor level
- 5/8" or 3/4" O.D. Smooth-Wall Tubing 6 feet Every floor level
- 7/8" or 1" O.D. Smooth-Wall Tubing 8 feet Every floor level
- CSST (any size) Per the CSST manufacturer's instructions Per the CSST manufacturer's instructions
Code Rule: Gas piping must not support other piping or structural loads. Support hangers must be attached directly to structural building members (joists, studs, concrete) and insulated from galvanic contact when supporting dissimilar metals.
2. Underground Gas Piping Installation Standards
Underground fuel gas piping requires specialized burial depth, corrosion protection, and location tracing to prevent accidental strike damage during future excavation:
Burial Depth Rules
Standard Minimum Cover: Underground piping must be installed with a minimum cover of 12 inches below finished grade.
The only exception is shallower, not deeper: IFGC 404.12.1 allows individual lines to outdoor lights, grills and similar appliances at 8 inches below finished grade where approved and not susceptible to physical damage. There is no 18-inch provision anywhere in IFGC Chapter 4 - the 18-inch increase for likely external damage is a Uniform Plumbing Code rule (UPC 1210.1.6) and a common distractor.
Trench Bedding: IFGC 404.13 requires only that the trench be graded so the pipe has a firm, substantially continuous bearing on the trench bottom ; clean sand or screened backfill is good practice rather than a code-stated material.
Wall Penetrations & Sleeves
IFGC 404.6 Underground Penetrations Prohibited is absolute: gas piping shall not penetrate building foundation walls at any point below grade . The piping must enter and exit the building above grade , and the annular space between pipe and wall must be sealed.
The annular space between the pipe and sleeve must be sealed with a flexible, non-hardening, water-tight sealant to prevent gas or water infiltration into the basement.
PE Plastic Underground Rules & Tracer Wire
Polyethylene (PE) pipe must be installed underground only.
Tracer Wire Requirement: An insulated, continuous copper tracer wire (minimum #18 AWG yellow insulated wire ) must be buried alongside non-metallic plastic piping. One end of the tracer wire must terminate above grade at an accessible riser location to allow electronic pipe locators to trace the buried line.
3. Fuel Gas Pressure Testing Protocols (IFGC Section 406)
Prior to appliance connection or concealment within walls/floors, all new, extended, or altered fuel gas piping systems must undergo a rough-in hydrostatic or pneumatic pressure test.
Required Test Pressure & Duration
System Type Minimum Test Pressure Minimum Duration Permissible Test Media
Standard Low-Pressure Gas (< 0.5 psi) 3 psig (or 1.5x working pressure) 10 minutes Air, Nitrogen, C O 2 CO_2 C O 2 , Inert Gas
Any higher working pressure 1.5x max working pressure, never below 3 psig (406.4.1) Sized by volume , not pressure: 1/2 hour per 500 cu ft of pipe volume or fraction (406.4.2) Air, Nitrogen, C O 2 CO_2 C O 2 , Inert Gas
- Prohibited Media NEVER USE OXYGEN N/A OXYGEN IS STRICTLY PROHIBITED
- Test Gauge Requirements
IFGC 406.4 : mechanical gauges used to measure test pressure must have a range such that the highest end of the scale is not greater than 5 times the test pressure . The rule governs the gauge's full-scale range , not its dial increment.
For a standard 3 psi pressure test, the test gauge must have a full-scale range no greater than 0 to 15 psi , with increments of 0.1 psi 0.1\text{ psi} 0.1 psi or 0.2 psi 0.2\text{ psi} 0.2 psi .
Using a 0-100 psi or 0-200 psi gauge for a 3 psi test is a direct code violation because small pressure drops cannot be visually detected on large scale dials.
4. Gas Line Purging Procedures & Safety (IFGC Section 406.7)
After pressure testing passes and prior to initial light-off, gas piping systems must be purged of air or test medium to prevent combustible fuel-air mixtures inside the piping.
Purging Execution Standards
Piping Thresholds: IFGC 406.7.1 sends a system outdoors when either the design operating pressure exceeds 2 psig , or the piping contains a section meeting the paired size-and-length criteria of Table 406.7.1.1: 2-1/2 to under 3 in. and over 50 ft; 3 to under 4 in. and over 30 ft; 4 to under 6 in. and over 15 ft; 6 to under 8 in. and over 10 ft; 8 in. and larger at any length. Size alone never triggers it - a 2-1/2-inch, 30-foot run falls outside the table.
Outdoor Discharge Location: IFGC 406.7.1.3 sets three different distances: not less than 10 feet from sources of ignition , not less than 10 feet from building openings , and not less than 25 feet from mechanical air intake openings . The discharge point is valved, continuously attended and monitored with a combustible gas indicator, and anyone not involved is kept 10 feet clear.
Safety Precautions:
Eliminate all open flames, electrical switches, or hot work in the immediate area.
Monitor the discharge with a Combustible Gas Indicator (CGI) . IFGC 406.7.1.3, item 4 requires purging that introduces fuel gas to be stopped when 90 percent fuel gas by volume is detected in the pipe - not at 100 percent.
5. Exam Traps & Inspection Guidelines
Prohibited Test Media Trap: Any test question suggesting Oxygen ( O 2 O_2 O 2 ) as a pressure test gas is an immediate explosive hazard and a false choice.
Burial Depth Confusions: IFGC gives 12 inches standard and 8 inches for individual outdoor appliances. The 18-inch "under driveways" figure is a UPC rule and does not appear in the IFGC.
Tracer Wire Specification: Minimum #18 AWG insulated copper tracer wire for PE plastic pipe.
Gauge Range Rule: Remember that gauge range cannot exceed 5x test pressure (max 15 psi gauge for a 3 psi test).