Study guide
2.2 Excavation & Trenching Safety (29 CFR 1926 Subpart P)
Maryland Journeyman Plumber Journey Plumber/Gas Fitter
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Maryland Licensing, Code Administration & the Exam
1.1 Maryland Plumbing Regulations & Licensing 1.2 The Journey Plumber/Gas Fitter Exam: Format, References & Open-Book Strategy
2 Chapter 2: Job-Site Safety & OSHA 29 CFR 1926
2.1 OSHA Construction Safety, PPE & Hazard Communication 2.2 Excavation & Trenching Safety (29 CFR 1926 Subpart P) 2.3 Confined Spaces, Ladders, Scaffolds & Hot Work
3 Chapter 3: Materials, Uses & Specifications
3.1 Approved Plumbing Materials, Pipes & Jointing 3.2 Hanger Spacing, Structural Protection & System Testing 3.3 Valves, Fittings, Fitting Selection & Prohibited Connections
4 Chapter 4: Sanitary Drainage & Waste Piping
4.1 Drainage Fixture Units (DFU) & Drain Pipe Sizing 4.2 Building Sewers, Cleanout Clearances & Underground Piping 4.3 Indirect & Special Waste Systems 4.4 Backwater Valves, Sump Pumps & Sewage Ejectors
5 Chapter 5: Venting Systems
5.1 Vent Sizing, Termination & Soil Stacks 5.2 Individual, Branch & Common Vents 5.3 Wet Venting & Circuit Venting 5.4 Air Admittance Valves (AAVs) & Special Venting
6 Chapter 6: Traps, Interceptors & Backwater Valves
6.1 Traps, Trap Seals & Trap Arm Requirements 6.2 Grease, Oil & Special-Waste Interceptors and Separators
7 Chapter 7: Water Supply & Distribution Systems
7.1 Water Supply Sizing & Fixture Unit (WSFU) Method 7.2 Water Heaters & Safety Devices 7.3 Pressure Regulation, Booster Systems & Disinfection 7.4 Water Service Piping, Meters, Valves & System Protection
8 Chapter 8: Backflow Prevention & Cross-Connection Control
8.1 Backflow Prevention & Cross-Connection Control 8.2 Air Gaps, Vacuum Breakers & Their Application Limits 8.3 Double Check & Reduced Pressure Principle (RPZ) Assemblies 8.4 Backflow Assembly Field Testing Procedures & Gauge Use 8.5 Maryland Backflow Program: 32-Hour Course, Certification & Reporting
9 Chapter 9: Fuel Gas Fundamentals, Materials & Pipe Sizing
9.1 Fuel Gas Properties, Heating Values & IFGC Scope 9.2 Fuel Gas Pipe Sizing & Materials 9.3 Approved Gas Piping Materials, CSST & Bonding 9.4 Gas Pipe Sizing Tables: Longest-Length & Branch-Length Methods 9.5 LP-Gas Systems, NFPA 58 & Propane-Specific Rules
10 Chapter 10: Gas Piping Installation, Testing & Purging
10.1 Gas Piping Installation, Testing & Purging 10.2 Gas Piping Support, Protection, Prohibited Locations & Concealed Piping 10.3 Shutoff Valves, Drips, Unions, Sediment Traps & Appliance Connectors 10.4 Gas Meters, Regulators, Pressure Levels & Overpressure Protection 10.5 Gas Leak Detection, Odorization & Emergency Response
11 Chapter 11: Gas Appliance Venting & Combustion Air
11.1 Gas Appliance Venting & Combustion Air 11.2 Appliance Categories I-IV, Vent Materials & Vent Connectors 11.3 Chimney & Vent Sizing Tables (Type B, Masonry & Common Venting) 11.4 Vent Termination, Clearances & Direct-Vent Systems 11.5 Combustion Air: Indoor & Outdoor Methods and Opening Sizing
12 Chapter 12: Gas Appliance Installation & Service
12.1 Gas Water Heaters, Furnaces & Boilers: Installation Rules 12.2 Appliance Clearances to Combustibles, Access & Location Limits 12.3 Gas Appliance Troubleshooting, Combustion Analysis & CO Safety
13 Chapter 13: Plumbing Fixtures, Fittings & Appliances
13.1 Fixture Clearances, Accessibility & Installation 13.2 Water Conservation Standards & Flow Rates 13.3 Commercial & Specialty Fixture Requirements
14 Chapter 14: Plumbing Mathematics
14.1 Plumbing Math I: Areas, Volumes, Capacities & Water Weight 14.2 Plumbing Math II: Offsets, Travel, Grade & Pipe Layout 14.3 Plumbing Math III: Gas Math, Meter Readings, BTU & Pressure Conversions
2.2 Excavation & Trenching Safety (29 CFR 1926 Subpart P)
Key Takeaways Explain This Topic AI
A protective system is required in any excavation 5 feet or more deep unless it is made entirely in stable rock, or is under 5 feet and a competent person finds no indication of a potential cave-in (1926.652(a)(1)).
Trenches 4 feet or more deep require a stairway, ladder, or ramp located within 25 feet of lateral travel (1926.651(c)(2)).
Appendix B maximum allowable slopes for excavations less than 20 feet deep are vertical for stable rock, 3/4:1 (53 degrees) for Type A, 1:1 (45 degrees) for Type B, and 1-1/2:1 (34 degrees) for Type C.
Spoil piles, materials, and equipment must be kept at least 2 feet back from the edge of an excavation (1926.651(j)(2)).
Maryland's Miss Utility law (Public Utilities Article Sec. 12-124) requires a start-work date no sooner than 3 business days and no later than 12 business days after the ticket is initiated.
Last updated: July 2026
2.2 Excavation & Trenching Safety (29 CFR 1926 Subpart P)
Quick Answer: Under 1926.652(a)(1) , every employee in an excavation must be protected from cave-ins by an adequate protective system when the excavation is 5 feet or more deep - unless the excavation is made entirely in stable rock , or it is less than 5 feet deep and a competent person examines the ground and finds no indication of a potential cave-in. The separate 4-foot rule at 1926.651(c)(2) governs the ladder, and spoil must stay 2 feet back from the edge under 1926.651(j)(2).
Excavation Versus Trench
Subpart P (1926.650 through 1926.652 plus Appendices A through F) is the highest-value OSHA material on this exam, because building sewers, water services, and storm laterals are trench work.
An excavation is any man-made cut, cavity, trench, or depression in an earth surface formed by earth removal.
A trench is a narrow excavation made below the surface of the ground. In general the depth is greater than the width, and the width measured at the bottom is not greater than 15 feet . If forms or other structures installed in an excavation reduce the bottom dimension to 15 feet or less, the excavation is also a trench.
Every trench is an excavation; not every excavation is a trench. The distinction matters because a few Subpart P provisions - the means-of-egress rule and the shield-system rule at 1926.652(g)(2) - are written specifically for trench excavations.
The Depth Numbers That Decide Everything
Depth or condition Requirement Citation
Trench 4 ft or more deep Stairway, ladder, ramp, or other safe means of egress located so as to require no more than 25 ft of lateral travel 1926.651(c)(2)
Excavation greater than 4 ft deep Test the atmosphere before entry where oxygen deficiency (below 19.5 percent ) or another hazardous atmosphere exists or could reasonably be expected 1926.651(g)(1)
5 ft or more deep Protective system required unless made entirely in stable rock 1926.652(a)(1)
Less than 5 ft deep A competent person may determine no protective system is needed if examination shows no indication of a potential cave-in 1926.652(a)(1)
6 ft or more deep Fall protection - guardrail, fence, barricade, or cover - at the edge of an excavation, well, pit, or shaft 1926.501(b)(7)
More than 20 ft deep Protective system must be designed by a registered professional engineer , or based on tabulated data prepared or approved by an RPE 1926.652(b) and (c); Appendix F
Any depth Excavated soil, materials, and equipment kept at least 2 ft from the edge (or retained by a retaining device) 1926.651(j)(2)
Notice that four separate numbers - 4, 5, 6, and 20 feet - control four separate obligations. PSI writes distractors by swapping them.