Study guide

3.2 Hanger Spacing, Structural Protection & System Testing

Maryland Journeyman Plumber Journey Plumber/Gas Fitter

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: Maryland Licensing, Code Administration & the Exam

1.1 Maryland Plumbing Regulations & Licensing 1.2 The Journey Plumber/Gas Fitter Exam: Format, References & Open-Book Strategy

2 Chapter 2: Job-Site Safety & OSHA 29 CFR 1926

2.1 OSHA Construction Safety, PPE & Hazard Communication 2.2 Excavation & Trenching Safety (29 CFR 1926 Subpart P) 2.3 Confined Spaces, Ladders, Scaffolds & Hot Work

3 Chapter 3: Materials, Uses & Specifications

3.1 Approved Plumbing Materials, Pipes & Jointing 3.2 Hanger Spacing, Structural Protection & System Testing 3.3 Valves, Fittings, Fitting Selection & Prohibited Connections

4 Chapter 4: Sanitary Drainage & Waste Piping

4.1 Drainage Fixture Units (DFU) & Drain Pipe Sizing 4.2 Building Sewers, Cleanout Clearances & Underground Piping 4.3 Indirect & Special Waste Systems 4.4 Backwater Valves, Sump Pumps & Sewage Ejectors

5 Chapter 5: Venting Systems

5.1 Vent Sizing, Termination & Soil Stacks 5.2 Individual, Branch & Common Vents 5.3 Wet Venting & Circuit Venting 5.4 Air Admittance Valves (AAVs) & Special Venting

6 Chapter 6: Traps, Interceptors & Backwater Valves

6.1 Traps, Trap Seals & Trap Arm Requirements 6.2 Grease, Oil & Special-Waste Interceptors and Separators

7 Chapter 7: Water Supply & Distribution Systems

7.1 Water Supply Sizing & Fixture Unit (WSFU) Method 7.2 Water Heaters & Safety Devices 7.3 Pressure Regulation, Booster Systems & Disinfection 7.4 Water Service Piping, Meters, Valves & System Protection

8 Chapter 8: Backflow Prevention & Cross-Connection Control

8.1 Backflow Prevention & Cross-Connection Control 8.2 Air Gaps, Vacuum Breakers & Their Application Limits 8.3 Double Check & Reduced Pressure Principle (RPZ) Assemblies 8.4 Backflow Assembly Field Testing Procedures & Gauge Use 8.5 Maryland Backflow Program: 32-Hour Course, Certification & Reporting

9 Chapter 9: Fuel Gas Fundamentals, Materials & Pipe Sizing

9.1 Fuel Gas Properties, Heating Values & IFGC Scope 9.2 Fuel Gas Pipe Sizing & Materials 9.3 Approved Gas Piping Materials, CSST & Bonding 9.4 Gas Pipe Sizing Tables: Longest-Length & Branch-Length Methods 9.5 LP-Gas Systems, NFPA 58 & Propane-Specific Rules

10 Chapter 10: Gas Piping Installation, Testing & Purging

10.1 Gas Piping Installation, Testing & Purging 10.2 Gas Piping Support, Protection, Prohibited Locations & Concealed Piping 10.3 Shutoff Valves, Drips, Unions, Sediment Traps & Appliance Connectors 10.4 Gas Meters, Regulators, Pressure Levels & Overpressure Protection 10.5 Gas Leak Detection, Odorization & Emergency Response

11 Chapter 11: Gas Appliance Venting & Combustion Air

11.1 Gas Appliance Venting & Combustion Air 11.2 Appliance Categories I-IV, Vent Materials & Vent Connectors 11.3 Chimney & Vent Sizing Tables (Type B, Masonry & Common Venting) 11.4 Vent Termination, Clearances & Direct-Vent Systems 11.5 Combustion Air: Indoor & Outdoor Methods and Opening Sizing

12 Chapter 12: Gas Appliance Installation & Service

12.1 Gas Water Heaters, Furnaces & Boilers: Installation Rules 12.2 Appliance Clearances to Combustibles, Access & Location Limits 12.3 Gas Appliance Troubleshooting, Combustion Analysis & CO Safety

13 Chapter 13: Plumbing Fixtures, Fittings & Appliances

13.1 Fixture Clearances, Accessibility & Installation 13.2 Water Conservation Standards & Flow Rates 13.3 Commercial & Specialty Fixture Requirements

14 Chapter 14: Plumbing Mathematics

14.1 Plumbing Math I: Areas, Volumes, Capacities & Water Weight 14.2 Plumbing Math II: Offsets, Travel, Grade & Pipe Layout 14.3 Plumbing Math III: Gas Math, Meter Readings, BTU & Pressure Conversions

3.2 Hanger Spacing, Structural Protection & System Testing

Key Takeaways Explain This Topic AI

Horizontal PEX pipe requires support every 32 inches, whereas horizontal PVC/ABS requires support every 4 feet and horizontal copper 1-1/2 inches and smaller requires support every 6 feet.

Joist notching is limited to D/6 of member depth at the outer thirds of span only; notching in the middle third of a joist span is strictly prohibited.

Nail protection plates (minimum 16-gauge steel) must extend 2 inches beyond member edges whenever piping passes through studs within 1.5 inches of the framing edge.

DWV systems must withstand a 10-foot head water column test for 15 minutes or a 5 psi air test for 15 minutes without measurable pressure drop.

Last updated: July 2026

3.2 Hanger Spacing, Structural Protection & System Testing

Quick Answer: Piping support, structural protection, and hydrostatic/pneumatic testing are governed by IPC Chapter 3 and COMAR 09.20. Horizontal hanger spacing ranges from 32 inches for PEX to 4 feet for PVC/ABS, 5 feet for Cast Iron, and 6–10 feet for Copper. Joist notching is limited to D/6 at outer thirds only (no notching in middle third). DWV systems must pass a 10-foot water head column test or 5 psi air test for 15 minutes.

Ensuring structural integrity, preventing pipe sagging, protecting piping from mechanical damage, and executing rigorous pressure tests are critical duties for every Journeyman Plumber.

Pipe Support & Hanger Spacing Standards

Piping must be supported at intervals close enough to maintain alignment, prevent sag (which creates water traps in drainage lines), and minimize stress on joints. IPC Table 308.5 specifies maximum support intervals and hanger material requirements.

Hanger Spacing Summary Table (IPC Table 308.5)

Piping Material Maximum Horizontal Spacing Maximum Vertical Spacing Support & Hanger Notes

ABS & PVC DWV 4 feet (48 inches) 10 feet Mid-story guide required on vertical stacks; hangers must be plastic-coated or engineered strap.

Cast Iron Soil Pipe 5 feet (60 inches)* 15 feet *May increase to 10 feet if 10-foot pipe lengths are installed; support at every joint and change of direction.

Copper tubing (1-1/4" and smaller) 6 feet (72 inches) 10 feet Hangers must be copper-plated or isolated to prevent galvanic action with steel hangers.

Copper tubing (1-1/2" and larger) 10 feet (120 inches) 10 feet Rigid clevis or roll hangers recommended for horizontal mains.

Copper pipe 12 feet 10 feet Copper pipe is supported further apart than copper tubing — a classic table trap.

PEX Tubing (1" and smaller) 32 inches (2.67 feet) 10 feet Guide required midway between vertical supports for sizes 2" and smaller; allow slack for thermal movement.

PEX Tubing (1-1/4" and larger) 4 feet (48 inches) 10 feet Larger PEX is stiffer and permits wider spacing.

CPVC (1" and smaller) 3 feet (36 inches) 10 feet Plastic hangers; avoid over-tightening which restricts axial movement.

CPVC (1-1/4" and larger) 4 feet (48 inches) 10 feet Guide midway between vertical supports for sizes 2" and smaller.

Steel Pipe 12 feet 15 feet Heavy clevis hangers or pipe rolls.

Structural Protection: Joist & Stud Framing Limits

Plumbers frequently cut framing members to install soil stacks, waste branches, and water lines. IPC Section 307 prohibits cutting, notching, or boring structural members beyond strict engineering limits without structural engineer approval.

Floor Joist Notching & Boring Rules (IPC 307.2)

Notching Span Restrictions:

Notches on floor joists are permitted ONLY in the outer thirds of the joist span.

NOTCHING IN THE MIDDLE THIRD OF A JOIST SPAN IS STRICTLY PROHIBITED.

Maximum notch depth is D/6 (one-sixth of the actual joist depth).

Maximum notch length is D/3 (one-third of the joist depth).

Joist Boring Restrictions:

Bored holes must be located at least 2 inches from the top or bottom edge of the joist.

The diameter of a bored hole cannot exceed D/3 (one-third of joist depth).

Holes must not be closer than 2 inches to any other hole or notch.

Wall Stud Notching & Boring Rules (IPC 307.3)

Stud Location / Type Max Notch Depth Max Bored Hole Diameter Special Requirements

Bearing Wall Stud 25% of stud depth 40% of stud depth Hole may be increased to 60% if stud is doubled and max 2 consecutive studs are bored.

Non-Bearing Wall Stud 40% of stud depth 60% of stud depth No doubling required for non-bearing studs up to 60%.

Physical Protection & Freeze Protection

Piping must be safeguarded from mechanical damage, thermal stress, and environmental freezing.

Steel Nail Shield Plates (IPC Section 305.6)

In concealed locations, where piping other than cast-iron or galvanized steel passes through holes or notches in studs, joists, rafters or similar members and the pipe sits less than 1-1/4 inches (32 mm) from the nearest framing edge, protective steel shield plates must be installed.

Plate Specifications: Must be constructed of minimum 16-gauge steel (0.0575 inch thick).

Coverage: Shield plates must extend at least 2 inches above sole plates and 2 inches below top plates to protect piping from drywall screws and finish nails.

Protection Against Freezing (IPC Section 305.4)

Water supply lines, drain lines, and traps must not be installed in exterior unconditioned walls, attics, or crawl spaces unless adequate insulation, heat trace, or structural shielding is provided.

Underground Frost Line: Per IPC 305.4, exterior water supply piping must be installed not less than 6 inches below the frost line and not less than 12 inches below grade — both conditions apply, so a shallow frost line does not permit burial above 12 inches (in Maryland, outdoor water service burial depths generally range from 24 to 30 inches below grade depending on local county/WSSC specifications).

Mandatory System Pressure Testing (IPC Section 312)

Before any plumbing system is approved by the inspector, it must undergo a rigorous pressure test to verify leak-free integrity.

DWV Gravity Water Test

Execution: System test openings are plugged (using inflatable test balls or mechanical plugs). The DWV piping is filled with water to a minimum head height of 10 feet of water column (equivalent to 4.34 psi hydrostatic pressure) at the highest point of the test section.

Duration: The water level must remain stable without adding water for at least 15 minutes .

DWV Pneumatic (Air) Test

Execution: DWV piping is pressurized with air to 5 psi (34.5 kPa) using an air compressor and test gauge calibrated in 0.1 psi increments.

Duration: Must maintain 5 psi for 15 minutes without measurable pressure drop.

Potable Water Supply Test

Water Test: System tested under a water pressure not less than the working pressure of the system (typically 50–80 psi).

Air Test: IPC 312.5 permits an air test of not less than 50 psi held for 15 minutes only for piping systems other than plastic . Plastic water-supply piping must be proved tight by the water test — compressed air in plastic pipe stores dangerous energy and is prohibited for this test.

Exam Trap: On the exam, remember that air testing of plastic (PVC/ABS) DWV piping is permitted by IPC Section 312, but some local jurisdictions or plastic manufacturers restrict air testing due to safety hazards if brittle plastic ruptures. However, for standard state exam code questions, the IPC standard rule of 5 psi air test for 15 minutes or 10-foot water column for 15 minutes is the required answer!

System Testing Quick Reference Table

System Being Tested Test Type Minimum Pressure Required Test Duration Pass Criteria

DWV Drainage & Vent Water Head Test 10 feet of water column (4.34 psi) 15 minutes Zero drop in water level.

DWV Drainage & Vent Air Pressure Test 5 psi (34.5 kPa) 15 minutes Zero drop on test gauge.

Potable Water Supply (non-plastic piping only) Air Test 50 psi minimum 15 minutes Gauge stays rock-steady. Not permitted on plastic piping.

Potable Water Supply Working Water Test System working pressure (min 50 psi) 15 minutes No visible leaks at joints.