Study guide

7.4 Bonding Requirements & Main Bonding Jumpers

Michigan Journeyman Electrician Study Guide Exam

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: Exam Overview & NEC General Requirements

1.1 Michigan LARA Electrical Licensing & Exam Format 1.2 NEC Article 90 & Code Structure 1.3 NEC Article 100 Essential Definitions 1.4 NEC Article 110 General Installation Requirements

2 Chapter 2: Branch Circuits & Outlets

2.1 Branch Circuit Ratings & Conductor Sizing 2.2 GFCI Protection Requirements (NEC 210.8) 2.3 AFCI & Tamper-Resistant Outlets (NEC 210.12 & 406.12) 2.4 Receptacle Outlets & Dwelling Unit Spacing (NEC 210.52 & 210.11) 2.5 Switches, Receptacles & Wiring Devices (NEC Articles 404 & 406)

3 Chapter 3: Load Calculations for Services & Feeders

3.1 General Lighting & Receptacle Load Calculations 3.2 Fixed Appliance, Dryer, & Cooking Unit Loads 3.3 Dwelling Unit Service & Feeder Calculations 3.4 Commercial & Non-Dwelling Load Calculations

4 Chapter 4: Wiring Methods, Conductors & Insulation

4.1 Conductor Types & Ampacity Sizing 4.2 Ampacity Adjustment & Correction Factors 4.3 Cable Assemblies (NM-B, MC, UF) 4.4 Raceways & Flexible Conduits (EMT, RMC, PVC, FMC)

5 Chapter 5: Conduit Fill, Box Fill & Panelboards

5.1 Raceway Fill Calculations 5.2 Outlet & Junction Box Sizing (NEC 314.16(A)) 5.3 Box Fill Volume Deductions (NEC 314.16(B)) 5.4 Panelboards, Switchboards & Cabinets (NEC Article 408)

6 Chapter 6: Overcurrent Protection Devices & Tap Rules

6.1 Fuses & Circuit Breakers (NEC Article 240) 6.2 Small Conductor Rules & Protection Limits (NEC 240.4(D)) 6.3 Feeder & Transformer Tap Rules (NEC 240.21) 6.4 Location, Enclosures & Overcurrent Protection Accessibility

7 Chapter 7: Grounding & Bonding Systems

7.1 Grounding Electrode Systems & Electrodes (NEC 250.50 & 250.52) 7.2 Grounding Electrode Conductor (GEC) Sizing (NEC Table 250.66) 7.3 Equipment Grounding Conductors (EGC) Sizing (NEC Table 250.122) 7.4 Bonding Requirements & Main Bonding Jumpers

8 Chapter 8: Motors, Generators & Transformers

8.1 Motor Full-Load Current (FLA) & Conductor Sizing (NEC Article 430) 8.2 Motor Short-Circuit & Ground-Fault Protection (Table 430.52) 8.3 Motor Overload Protection & Disconnecting Means 8.4 Transformer Sizing, Protection & Installation (NEC Article 450)

9 Chapter 9: Special Occupancies, Equipment & Conditions

9.1 Hazardous (Classified) Locations (NEC Articles 500-516) 9.2 Commercial Garages, Service Stations & Healthcare Facilities (Articles 511, 514, 517) 9.3 Swimming Pools, Fountains & Equipotential Bonding (NEC Article 680) 9.4 Renewable Energy Systems & Generators (NEC Articles 690, 700, 702)

10 Chapter 10: Michigan Electrical Law, Rules & Code Administration

10.1 Skilled Trades Regulation Act: License Classes, Scope & Supervision 10.2 Licensure, Examination Eligibility, Retakes & Continuing Education 10.3 Michigan Electrical Code Part 8 Rules & the 2023 NEC Adoption 10.4 Michigan Amendments & Key 2023 NEC Changes Enforced in Michigan 10.5 Stille-DeRossett-Hale Act, Permits, Inspections & the AHJ

11 Chapter 11: Electrical Theory & General Trade Knowledge

11.1 Ohm's Law, Power Formulas & Series/Parallel Circuits 11.2 Alternating Current, Single-Phase & Three-Phase Systems 11.3 Power Factor, Efficiency & Transformer Theory 11.4 Voltage Drop, Conductor Resistance & Trade Math

12 Chapter 12: Services & Feeders (Articles 230 & 215)

12.1 Service Conductors, Clearances & Service-Entrance Requirements 12.2 Service Disconnecting Means, Overcurrent Protection & Service Grounding 12.3 Feeders: Sizing, Overcurrent Protection & Article 215 Requirements

13 Chapter 13: Lighting, Appliances & Power-Limited Circuits

13.1 Luminaires & Lighting Installations (NEC Article 410) 13.2 Appliances & Fixed Electric Space Heating (NEC Articles 422 & 424) 13.3 Class 1, Class 2 & Class 3 Power-Limited Circuits (Articles 724 & 725) 13.4 Fire Alarm, Communications & Optical Fiber Systems (Articles 760, 770, 800-820)

7.4 Bonding Requirements & Main Bonding Jumpers

Key Takeaways Explain This Topic AI

Bonding (NEC 250 Part V) ensures electrical continuity and conductivity between metal parts to safely conduct any fault current likely to be imposed.

The Main Bonding Jumper (MBJ) per NEC 250.28 connects the grounded neutral conductor to the service equipment enclosure at each service disconnect.

System Bonding Jumpers (SBJ) per NEC 250.30 serve the same role for separately derived systems (transformers, generators) and are installed at the source or first disconnecting means.

Sizing of MBJ, SBJ, and supply-side bonding jumpers is governed by NEC Table 250.102(C)(1) based on the size of the ungrounded service/supply conductors; if phase conductors exceed 1100 kcmil Cu / 1750 kcmil Al, the jumper must be at least 12.5% of the total kcmil area.

Service raceway terminations and enclosures require specialized bonding methods under NEC 250.92 (bonding bushings, jumpers around concentric knockouts); standard locknuts alone are strictly prohibited for service equipment terminations.

Last updated: August 2026

7.4 Bonding Requirements & Main Bonding Jumpers

Exam Focus: Grounding vs. bonding definitions, Main Bonding Jumper (MBJ) function (250.28), System Bonding Jumper (SBJ) for separately derived systems (250.30), sizing per Table 250.102(C)(1), the 12.5% rule for conductors > 1100 kcmil Cu, water/gas/steel bonding rules (250.104), and service equipment knockout bonding (250.92).

While grounding connects electrical circuits to the earth, bonding connects non-current-carrying metallic parts of electrical equipment, raceways, and building systems together. Bonding creates an electrically continuous low-impedance path back to the electrical source so that ground-fault currents can flow unimpeded to trip overcurrent devices instantly.

  • Main Bonding Jumper (MBJ) & System Bonding Jumper (SBJ)
  • 1. Main Bonding Jumper (NEC 250.28)

In a grounded service, the Main Bonding Jumper (MBJ) connects the grounded system conductor (neutral) to the service equipment enclosure and equipment grounding bus at each service disconnecting means.

Function: Establishes the fault-return bridge between metallic equipment enclosures and the neutral conductor coming from the utility transformer.

Permitted Materials (250.28(A)): Wire, busbar, screw (with green finish visible), or similar suitable conductor.

Un-grounded Systems: On ungrounded systems, the MBJ bonds the service enclosure to the grounding electrode conductor. MAIN BONDING JUMPER (MBJ) LOCATION

  • +-------------------------------------------------------------------------+
  • | UTILITY TRANSFORMER |
  • | Neutral Center Tap ---------------------------------+ |
  • +-----------------------------------------------------|-------------------+
  • | Grounded Neutral
  • v
  • +-------------------------------------------------------------------------+
  • | SERVICE DISCONNECT ENCLOSURE |
  • | Neutral BusBar <=======[ MAIN BONDING JUMPER ]=======> Enclosure / |
  • | | (NEC 250.28) Ground Bus |
  • | v | |
  • | GEC to Earth v |
  • | EGC to Panel |
  • +-------------------------------------------------------------------------+
  • 2. System Bonding Jumper (NEC 250.30)

For a separately derived system (SDS) —such as a step-down transformer or generator—a System Bonding Jumper (SBJ) connects the grounded conductor of the derived system to the equipment grounding conductor and source enclosure. It must be installed at the source of the SDS or at the first disconnecting means, but NOT at both locations.

Sizing MBJs, SBJs, and Supply-Side Jumpers (NEC Table 250.102(C)(1))

Main bonding jumpers, system bonding jumpers, and supply-side bonding jumpers are sized using NEC Table 250.102(C)(1) based on the area of the largest ungrounded supply conductor.

Size of Largest Ungrounded Supply Conductor or Equivalent Area for Parallel Conductors Minimum Size of Equipment Bonding Jumper or Main Bonding Jumper

  • Copper (Cu) Aluminum or Cu-Clad Al Copper (Cu) Aluminum or Cu-Clad Al
  • 2 AWG or smaller 1/0 AWG or smaller 8 AWG 6 AWG
  • 1 AWG or 1/0 AWG 2/0 AWG or 3/0 AWG 6 AWG 4 AWG
  • 2/0 AWG or 3/0 AWG 4/0 AWG or 250 kcmil 4 AWG 2 AWG
  • Over 3/0 AWG thru 350 kcmil Over 250 kcmil thru 500 kcmil 2 AWG 1/0 AWG
  • Over 350 kcmil thru 600 kcmil Over 500 kcmil thru 900 kcmil 1/0 AWG 3/0 AWG
  • Over 600 kcmil thru 1100 kcmil Over 900 kcmil thru 1750 kcmil 2/0 AWG 4/0 AWG
  • Over 1100 kcmil Over 1750 kcmil See 12.5% Rule Below

Important

The 12.5% Rule for Large Services (Table 250.102(C)(1) Note 1): Where the ungrounded supply conductors exceed 1100 kcmil Copper or 1750 kcmil Aluminum , the bonding jumper shall have an area not less than 12.5% of the total area of the ungrounded supply conductors per phase.

Worked Calculation Example: 12.5% Rule Sizing

Scenario: A 2000A 480V service is supplied by four parallel runs of 500 kcmil copper conductors per phase (total 4 × 500 = 2 , 000 kcmil 4 \times 500 = 2,000\text{ kcmil} 4 × 500 = 2 , 000 kcmil copper per phase). What minimum size copper Main Bonding Jumper is required?

Step 1: Check Total kcmil Area:

Total ungrounded conductor area per phase = 2,000 kcmil Cu .

2,000 kcmil exceeds 1100 kcmil, so Table 250.102(C)(1) cap applies: 12.5% Rule .

Step 2: Calculate Required Minimum cmil Area: Required MBJ cmil = 2 , 000 , 000 cmil × 0.125 = 250 , 000 cmil (250 kcmil) \text{Required MBJ cmil} = 2,000,000\text{ cmil} \times 0.125 = 250,000\text{ cmil} \text{ (250 kcmil)} Required MBJ cmil = 2 , 000 , 000 cmil × 0.125 = 250 , 000 cmil (250 kcmil)

Step 3: Select Conductor Size:

250 kcmil Copper minimum MBJ wire or equivalent busbar.

Specific Building Bonding Requirements (NEC 250.104)

NEC 250.104 dictates bonding rules for interior metal piping and structural building frames: BUILDING BONDING REQUIREMENTS SUMMARY

  • +-------------------------------------------------------------------------+
  • | INTERIOR METAL WATER PIPING (NEC 250.104(A)) |
  • | - Bonded to service enclosure, GEC, or grounding electrode system. |
  • | - Sized per Table 250.102(C)(1) based on service conductor size. |
  • +-------------------------------------------------------------------------+
  • | METAL GAS PIPING (NEC 250.104(B)) |
  • | - Bonded to service equipment, GEC, or circuit EGC. |
  • | - Sized per Table 250.122 based on OCPD of circuit likely to energize it.|
  • +-------------------------------------------------------------------------+
  • | STRUCTURAL METAL FRAMING (NEC 250.104(C)) |
  • | - Exposed structural steel likely to become energized must be bonded. |
  • | - Sized per Table 250.102(C)(1) based on service conductor size. |
  • +-------------------------------------------------------------------------+
  • 1. Bonding Metal Water Piping (NEC 250.104(A))

Interior metal water piping systems must be bonded to the service equipment enclosure, the grounded conductor at the service, the GEC, or one or more electrodes.

Sizing: Sized per Table 250.102(C)(1) based on largest service conductor.

2. Bonding Other Metal Piping / Gas Piping (NEC 250.104(B))

Metal gas piping and other metal piping systems likely to become energized must be bonded to the service enclosure, GEC, or grounded conductor.

Sizing: Sized per Table 250.122 based on the rating of the circuit likely to energize the piping (e.g., gas furnace branch circuit, gas water heater circuit).

Practical Note: The equipment grounding conductor (EGC) of the appliance branch circuit supplying the equipment (e.g. 12 AWG Cu for a 20A furnace circuit) is explicitly permitted to satisfy the gas pipe bonding requirement!

Service Equipment & Knockout Bonding (NEC 250.92)

Service equipment raceways and enclosures require a much higher level of bonding integrity than standard branch circuit equipment. Why? Because service conductors have no line-side overcurrent protection ahead of them to trip during a fault! SERVICE ENCLOSURE BONDING VS BRANCH CIRCUITS

  • +-------------------------------------------------------------------------+
  • | SERVICE RACEWAY TERMINATION (NEC 250.92) |
  • | - Standard locknuts or double locknuts ALONE ARE PROHIBITED! |
  • | - MUST USE: Bonding bushings with bonding jumpers, threaded hubs, or |
  • | bonding locknuts with wedge teeth. |
  • | - Concentric / Eccentric knockouts REQUIRE bonding jumpers around rings!|
  • +-------------------------------------------------------------------------+
  • | BRANCH CIRCUIT RACEWAY TERMINATION (< 250V to Ground) |
  • | - Standard locknuts on painted enclosures permitted. |
  • +-------------------------------------------------------------------------+

Caution

Knockout Exam Trap (NEC 250.92(B)): Where service raceways enter service enclosures through concentric or eccentric knockouts , standard locknuts cannot guarantee electrical continuity. A grounding bushing with a bonding jumper sized per Table 250.102(C)(1) must be installed around the knockout ring to ensure a low-impedance ground-fault return path.