Study guide

7.2 Grounding Electrode Conductor (GEC) Sizing (NEC Table 250.66)

Michigan Journeyman Electrician Study Guide Exam

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: Exam Overview & NEC General Requirements

1.1 Michigan LARA Electrical Licensing & Exam Format 1.2 NEC Article 90 & Code Structure 1.3 NEC Article 100 Essential Definitions 1.4 NEC Article 110 General Installation Requirements

2 Chapter 2: Branch Circuits & Outlets

2.1 Branch Circuit Ratings & Conductor Sizing 2.2 GFCI Protection Requirements (NEC 210.8) 2.3 AFCI & Tamper-Resistant Outlets (NEC 210.12 & 406.12) 2.4 Receptacle Outlets & Dwelling Unit Spacing (NEC 210.52 & 210.11) 2.5 Switches, Receptacles & Wiring Devices (NEC Articles 404 & 406)

3 Chapter 3: Load Calculations for Services & Feeders

3.1 General Lighting & Receptacle Load Calculations 3.2 Fixed Appliance, Dryer, & Cooking Unit Loads 3.3 Dwelling Unit Service & Feeder Calculations 3.4 Commercial & Non-Dwelling Load Calculations

4 Chapter 4: Wiring Methods, Conductors & Insulation

4.1 Conductor Types & Ampacity Sizing 4.2 Ampacity Adjustment & Correction Factors 4.3 Cable Assemblies (NM-B, MC, UF) 4.4 Raceways & Flexible Conduits (EMT, RMC, PVC, FMC)

5 Chapter 5: Conduit Fill, Box Fill & Panelboards

5.1 Raceway Fill Calculations 5.2 Outlet & Junction Box Sizing (NEC 314.16(A)) 5.3 Box Fill Volume Deductions (NEC 314.16(B)) 5.4 Panelboards, Switchboards & Cabinets (NEC Article 408)

6 Chapter 6: Overcurrent Protection Devices & Tap Rules

6.1 Fuses & Circuit Breakers (NEC Article 240) 6.2 Small Conductor Rules & Protection Limits (NEC 240.4(D)) 6.3 Feeder & Transformer Tap Rules (NEC 240.21) 6.4 Location, Enclosures & Overcurrent Protection Accessibility

7 Chapter 7: Grounding & Bonding Systems

7.1 Grounding Electrode Systems & Electrodes (NEC 250.50 & 250.52) 7.2 Grounding Electrode Conductor (GEC) Sizing (NEC Table 250.66) 7.3 Equipment Grounding Conductors (EGC) Sizing (NEC Table 250.122) 7.4 Bonding Requirements & Main Bonding Jumpers

8 Chapter 8: Motors, Generators & Transformers

8.1 Motor Full-Load Current (FLA) & Conductor Sizing (NEC Article 430) 8.2 Motor Short-Circuit & Ground-Fault Protection (Table 430.52) 8.3 Motor Overload Protection & Disconnecting Means 8.4 Transformer Sizing, Protection & Installation (NEC Article 450)

9 Chapter 9: Special Occupancies, Equipment & Conditions

9.1 Hazardous (Classified) Locations (NEC Articles 500-516) 9.2 Commercial Garages, Service Stations & Healthcare Facilities (Articles 511, 514, 517) 9.3 Swimming Pools, Fountains & Equipotential Bonding (NEC Article 680) 9.4 Renewable Energy Systems & Generators (NEC Articles 690, 700, 702)

10 Chapter 10: Michigan Electrical Law, Rules & Code Administration

10.1 Skilled Trades Regulation Act: License Classes, Scope & Supervision 10.2 Licensure, Examination Eligibility, Retakes & Continuing Education 10.3 Michigan Electrical Code Part 8 Rules & the 2023 NEC Adoption 10.4 Michigan Amendments & Key 2023 NEC Changes Enforced in Michigan 10.5 Stille-DeRossett-Hale Act, Permits, Inspections & the AHJ

11 Chapter 11: Electrical Theory & General Trade Knowledge

11.1 Ohm's Law, Power Formulas & Series/Parallel Circuits 11.2 Alternating Current, Single-Phase & Three-Phase Systems 11.3 Power Factor, Efficiency & Transformer Theory 11.4 Voltage Drop, Conductor Resistance & Trade Math

12 Chapter 12: Services & Feeders (Articles 230 & 215)

12.1 Service Conductors, Clearances & Service-Entrance Requirements 12.2 Service Disconnecting Means, Overcurrent Protection & Service Grounding 12.3 Feeders: Sizing, Overcurrent Protection & Article 215 Requirements

13 Chapter 13: Lighting, Appliances & Power-Limited Circuits

13.1 Luminaires & Lighting Installations (NEC Article 410) 13.2 Appliances & Fixed Electric Space Heating (NEC Articles 422 & 424) 13.3 Class 1, Class 2 & Class 3 Power-Limited Circuits (Articles 724 & 725) 13.4 Fire Alarm, Communications & Optical Fiber Systems (Articles 760, 770, 800-820)

7.2 Grounding Electrode Conductor (GEC) Sizing (NEC Table 250.66)

Key Takeaways Explain This Topic AI

NEC Table 250.66 establishes the minimum size of Grounding Electrode Conductors (GEC) based on the size of the largest ungrounded service-entrance conductor or equivalent area for parallel sets.

Maximum size exceptions apply for specific sole-connection electrodes: ground rods/pipes require max 6 AWG Cu (250.66(A)), concrete-encased Ufer electrodes require max 4 AWG Cu (250.66(B)), and ground rings require max the size of the ring conductor (250.66(C)).

NEC 250.64(C) mandates that GECs must be continuous without splices or joints, except where connected by irreversible compression connectors, exothermic welding, or busbar extension.

Under NEC 250.64(E), any ferrous metal raceway or enclosure containing a GEC must be bonded at both ends to the GEC to prevent inductive reactance choke effect during high-frequency fault/lightning surges.

When service conductors are run in parallel, GEC sizing is determined by calculating the total equivalent circular mil area of all parallel conductors per phase.

Last updated: August 2026

7.2 Grounding Electrode Conductor (GEC) Sizing (NEC Table 250.66)

Exam Focus: Sizing GECs per NEC Table 250.66, parallel service conductor calculations, sole connection exceptions (250.66(A), (B), (C)), GEC physical protection (250.64(B)), splice prohibitions (250.64(C)), and ferrous raceway bonding at both ends (250.64(E)).

The Grounding Electrode Conductor (GEC) is the conductor that connects the grounded system conductor (neutral) or equipment enclosure at the service disconnecting means to the grounding electrode system in the earth. Because the GEC carries lightning surges, utility transients, and high-frequency fault currents to ground, proper sizing and physical protection are vital for facility safety.

Grounding Electrode Conductor Sizing Table (NEC Table 250.66)

GEC sizing is determined by the cross-sectional area of the largest ungrounded service-entrance conductor (or equivalent area for parallel conductors per phase).

Size of Largest Ungrounded Service-Entrance Conductor or Equivalent Area for Parallel Conductors Size of Grounding Electrode Conductor (GEC)

  • Copper (Cu) Aluminum or Cu-Clad Al Copper (Cu) Aluminum or Cu-Clad Al
  • 2 AWG or smaller 1/0 AWG or smaller 8 AWG 6 AWG
  • 1 AWG or 1/0 AWG 2/0 AWG or 3/0 AWG 6 AWG 4 AWG
  • 2/0 AWG or 3/0 AWG 4/0 AWG or 250 kcmil 4 AWG 2 AWG
  • Over 3/0 AWG thru 350 kcmil Over 250 kcmil thru 500 kcmil 2 AWG 1/0 AWG
  • Over 350 kcmil thru 600 kcmil Over 500 kcmil thru 900 kcmil 1/0 AWG 3/0 AWG
  • Over 600 kcmil thru 1100 kcmil Over 900 kcmil thru 1750 kcmil 2/0 AWG 4/0 AWG
  • Over 1100 kcmil Over 1750 kcmil 3/0 AWG 250 kcmil

Note

Parallel Conductor Sizing Method: When service-entrance conductors are installed in parallel in multiple raceways, you must add the circular mil areas of the parallel conductors per phase. For example, two 350 kcmil Cu conductors per phase equal 350 + 350 = 700 kcmil 350 + 350 = 700\text{ kcmil} 350 + 350 = 700 kcmil . Looking at Table 250.66, 700 kcmil Cu falls into the "Over 600 kcmil thru 1100 kcmil" bracket, requiring a 2/0 AWG Cu GEC.

Maximum Size Exceptions for Sole Connections (NEC 250.66(A), (B), (C))

NEC Table 250.66 specifies baseline conductor sizes, but the code provides three critical maximum-size exceptions when the GEC connects solely to specific electrode types. These exceptions frequently appear on Journeyman licensing exams! GEC MAXIMUM SIZE EXCEPTIONS SUMMARY

  • +-------------------------------------------------------------------------+
  • | 1. GROUND ROD / PIPE / PLATE ELECTRODE (NEC 250.66(A)) |
  • | --> Maximum required size is 6 AWG Copper (or 4 AWG Aluminum). |
  • | --> Regardless of whether the service is 200A or 4000A! |
  • +-------------------------------------------------------------------------+
  • | 2. CONCRETE-ENCASED UFER ELECTRODE (NEC 250.66(B)) |
  • | --> Maximum required size is 4 AWG Copper. |
  • +-------------------------------------------------------------------------+
  • | 3. GROUND RING ELECTRODE (NEC 250.66(C)) |
  • | --> Max size NOT required to be larger than the ring conductor size. |
  • +-------------------------------------------------------------------------+

Caution

The "Water Pipe Trap" on Exams: If a GEC connects to a metal underground water pipe electrode (which then bonds to ground rods), the GEC section connecting to the water pipe MUST be sized for the full Table 250.66 rating (e.g. 2/0 AWG for a 1000 kcmil service). The 6 AWG cap ONLY applies to the tap conductor that connects solely to the ground rod!

  • GEC Installation & Physical Protection (NEC 250.64)
  • 1. Physical Protection Rules (NEC 250.64(B))

8 AWG Copper: Must be installed in rigid metal conduit (RMC), intermediate metal conduit (IMC), electrical metallic tubing (EMT), rigid polyvinyl chloride conduit (PVC), reinforced thermosetting resin conduit (RTRC), or cable armor.

6 AWG Copper: May be run along the surface of the building structure if free from exposure to physical damage; otherwise, it must be enclosed in raceway or armor.

4 AWG Copper and Larger: Permitted to be attached directly to building surfaces without raceway protection, provided it is not exposed to severe physical damage.

2. Continuous Requirement & Splice Rules (NEC 250.64(C))

Grounding electrode conductors must be installed in one continuous length without splice or joint , except under the following permitted methods:

Splicing by exothermic welding (Thermit process).

Splicing with irreversible compression-type connectors listed for grounding.

Connections to a copper busbar (minimum 1/4 in. thick x 2 in. wide) situated at an accessible location. FERROUS RACEWAY INDUCTIVE CHOKE EFFECT

  • +-------------------------------------------------------------------------+
  • | UNBONDED STEEL CONDUIT (VIOLATION) |
  • | High surge current through GEC --> Creates magnetic field in steel pipe |
  • | --> Inductive Reactance Choke severely blocks fault current from earth! |
  • +-------------------------------------------------------------------------+
  • | BONDED STEEL CONDUIT (NEC 250.64(E) COMPLIANT) |
  • | Bonding jumper connected to GEC at BOTH top and bottom of steel pipe |
  • | --> Places steel pipe in parallel with GEC, eliminating choke effect! |
  • +-------------------------------------------------------------------------+
  • 3. Bonding Ferrous Raceways Enclosing a GEC (NEC 250.64(E))

When a GEC is enclosed inside a ferrous metal raceway (such as steel RMC, IMC, or EMT), high-frequency transient currents (like lightning strikes) create an intense magnetic field inside the iron/steel pipe. This creates high inductive reactance (the choke effect), severely restricting surge current flow to ground.

NEC 250.64(E) Mandate: Ferrous metal raceways and enclosures containing a GEC must be bonded at each end of the raceway to the GEC.

The bonding jumper must be sized at least as large as the enclosed GEC.

Nonferrous raceways (such as PVC conduit or aluminum conduit) do NOT exhibit this choke effect and do not require end-to-end bonding jumpers.

Worked Calculation Example: Service GEC Sizing

Scenario: A 120/208V, 3-phase, 4-wire commercial service consists of three parallel runs of 400 kcmil THHN copper per phase in PVC raceways. The grounding electrode system consists of a metal underground water pipe and a supplemental concrete-encased Ufer electrode. What size copper GEC is required for (a) the main water pipe connection, and (b) the sole connection to the Ufer electrode?

Step 1: Calculate Total Equivalent Phase Conductor Area:

Three parallel runs of 400 kcmil per phase = 3 × 400 kcmil = 1 , 200 kcmil 3 \times 400\text{ kcmil} = 1,200\text{ kcmil} 3 × 400 kcmil = 1 , 200 kcmil copper per phase.

Step 2: Size GEC for Water Pipe Electrode (Table 250.66):

Equivalent area = 1,200 kcmil Cu.

Table 250.66 column for copper service conductors: 1,200 kcmil exceeds 1100 kcmil.

Minimum required GEC for water pipe = 3/0 AWG Copper .

Step 3: Size GEC for Concrete-Encased Ufer Electrode (250.66(B)):

NEC 250.66(B) caps the sole connection to a concrete-encased electrode at 4 AWG Copper .

Conclusion: The GEC run from the service neutral to the water pipe entrance must be 3/0 AWG Cu , while the tap GEC to the Ufer electrode needs only be 4 AWG Cu .