Study guide

12.3 Feeders: Sizing, Overcurrent Protection & Article 215 Requirements

Michigan Journeyman Electrician Study Guide Exam

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: Exam Overview & NEC General Requirements

1.1 Michigan LARA Electrical Licensing & Exam Format 1.2 NEC Article 90 & Code Structure 1.3 NEC Article 100 Essential Definitions 1.4 NEC Article 110 General Installation Requirements

2 Chapter 2: Branch Circuits & Outlets

2.1 Branch Circuit Ratings & Conductor Sizing 2.2 GFCI Protection Requirements (NEC 210.8) 2.3 AFCI & Tamper-Resistant Outlets (NEC 210.12 & 406.12) 2.4 Receptacle Outlets & Dwelling Unit Spacing (NEC 210.52 & 210.11) 2.5 Switches, Receptacles & Wiring Devices (NEC Articles 404 & 406)

3 Chapter 3: Load Calculations for Services & Feeders

3.1 General Lighting & Receptacle Load Calculations 3.2 Fixed Appliance, Dryer, & Cooking Unit Loads 3.3 Dwelling Unit Service & Feeder Calculations 3.4 Commercial & Non-Dwelling Load Calculations

4 Chapter 4: Wiring Methods, Conductors & Insulation

4.1 Conductor Types & Ampacity Sizing 4.2 Ampacity Adjustment & Correction Factors 4.3 Cable Assemblies (NM-B, MC, UF) 4.4 Raceways & Flexible Conduits (EMT, RMC, PVC, FMC)

5 Chapter 5: Conduit Fill, Box Fill & Panelboards

5.1 Raceway Fill Calculations 5.2 Outlet & Junction Box Sizing (NEC 314.16(A)) 5.3 Box Fill Volume Deductions (NEC 314.16(B)) 5.4 Panelboards, Switchboards & Cabinets (NEC Article 408)

6 Chapter 6: Overcurrent Protection Devices & Tap Rules

6.1 Fuses & Circuit Breakers (NEC Article 240) 6.2 Small Conductor Rules & Protection Limits (NEC 240.4(D)) 6.3 Feeder & Transformer Tap Rules (NEC 240.21) 6.4 Location, Enclosures & Overcurrent Protection Accessibility

7 Chapter 7: Grounding & Bonding Systems

7.1 Grounding Electrode Systems & Electrodes (NEC 250.50 & 250.52) 7.2 Grounding Electrode Conductor (GEC) Sizing (NEC Table 250.66) 7.3 Equipment Grounding Conductors (EGC) Sizing (NEC Table 250.122) 7.4 Bonding Requirements & Main Bonding Jumpers

8 Chapter 8: Motors, Generators & Transformers

8.1 Motor Full-Load Current (FLA) & Conductor Sizing (NEC Article 430) 8.2 Motor Short-Circuit & Ground-Fault Protection (Table 430.52) 8.3 Motor Overload Protection & Disconnecting Means 8.4 Transformer Sizing, Protection & Installation (NEC Article 450)

9 Chapter 9: Special Occupancies, Equipment & Conditions

9.1 Hazardous (Classified) Locations (NEC Articles 500-516) 9.2 Commercial Garages, Service Stations & Healthcare Facilities (Articles 511, 514, 517) 9.3 Swimming Pools, Fountains & Equipotential Bonding (NEC Article 680) 9.4 Renewable Energy Systems & Generators (NEC Articles 690, 700, 702)

10 Chapter 10: Michigan Electrical Law, Rules & Code Administration

10.1 Skilled Trades Regulation Act: License Classes, Scope & Supervision 10.2 Licensure, Examination Eligibility, Retakes & Continuing Education 10.3 Michigan Electrical Code Part 8 Rules & the 2023 NEC Adoption 10.4 Michigan Amendments & Key 2023 NEC Changes Enforced in Michigan 10.5 Stille-DeRossett-Hale Act, Permits, Inspections & the AHJ

11 Chapter 11: Electrical Theory & General Trade Knowledge

11.1 Ohm's Law, Power Formulas & Series/Parallel Circuits 11.2 Alternating Current, Single-Phase & Three-Phase Systems 11.3 Power Factor, Efficiency & Transformer Theory 11.4 Voltage Drop, Conductor Resistance & Trade Math

12 Chapter 12: Services & Feeders (Articles 230 & 215)

12.1 Service Conductors, Clearances & Service-Entrance Requirements 12.2 Service Disconnecting Means, Overcurrent Protection & Service Grounding 12.3 Feeders: Sizing, Overcurrent Protection & Article 215 Requirements

13 Chapter 13: Lighting, Appliances & Power-Limited Circuits

13.1 Luminaires & Lighting Installations (NEC Article 410) 13.2 Appliances & Fixed Electric Space Heating (NEC Articles 422 & 424) 13.3 Class 1, Class 2 & Class 3 Power-Limited Circuits (Articles 724 & 725) 13.4 Fire Alarm, Communications & Optical Fiber Systems (Articles 760, 770, 800-820)

12.3 Feeders: Sizing, Overcurrent Protection & Article 215 Requirements

Key Takeaways Explain This Topic AI

A feeder is defined in Article 100 as all circuit conductors between the service equipment, the source of a separately derived system, or another power supply source and the final branch-circuit overcurrent device.

NEC 215.2(A)(1) requires feeder conductors to have an ampacity not less than the noncontinuous load plus 125 percent of the continuous load, before applying any adjustment or correction factors.

NEC 215.3 requires the feeder overcurrent device to have a rating not less than the noncontinuous load plus 125 percent of the continuous load.

NEC 215.10 requires ground-fault protection of equipment on feeder disconnects rated 1,000 amperes or more on solidly grounded wye systems of more than 150 volts to ground but not exceeding 1,000 volts phase-to-phase, unless that protection is already provided upstream at the service.

NEC 215.12 requires feeder conductors to be identified by phase or line and system where a premises has feeders supplied from more than one nominal voltage system, using color coding, tagging, or another approved means documented at each feeder distribution equipment location.

Last updated: August 2026

12.3 Feeders: Sizing, Overcurrent Protection & Article 215 Requirements

Exam Focus: The Article 100 feeder definition, 215.2 conductor sizing, 215.3 overcurrent device sizing, feeder EGC and grounded conductor sizing, 215.10 GFPE, and 215.12 identification.

Feeders are the middle tier of the distribution system, and the PSI subject list names them separately from services and branch circuits. Article 215 is short, which makes it a reliable source of quick points if you know where its five or six substantive rules live.

What Makes a Conductor a Feeder

Article 100 defines a feeder as all circuit conductors between:

  • the service equipment ,
  • the source of a separately derived system , or
  • another power supply source (a generator, a photovoltaic system, an energy storage system),

and the final branch-circuit overcurrent device . +-------------------------------------------------------------------------+

  • | IDENTIFYING THE THREE CONDUCTOR TIERS |
  • | |
  • | Utility --> [service point] --> SERVICE CONDUCTORS |
  • | | |
  • | [ SERVICE DISCONNECT ] |
  • | | |
  • | FEEDER CONDUCTORS <-- Article 215 |
  • | | |
  • | [ Subpanel / MDP ] |
  • | | |
  • | FEEDER CONDUCTORS (still a feeder) |
  • | | |
  • | [ FINAL BRANCH-CIRCUIT OCPD ] |
  • | | |
  • | BRANCH CIRCUIT <-- Article 210 |
  • | | |
  • | [ Outlet ] |
  • +-------------------------------------------------------------------------+

Important

A feeder can pass through several panelboards. The tier does not change at a subpanel; it changes at the final overcurrent device protecting the circuit that reaches the outlet. A conductor from a main distribution panel to a 200 A subpanel is a feeder; a conductor from that subpanel to a second 100 A subpanel is still a feeder.

Sizing the Feeder Conductors — NEC 215.2(A)(1)

Feeder conductors must have an ampacity not less than the noncontinuous load plus 125 percent of the continuous load , determined before the application of any adjustment or correction factors. Minimum feeder ampacity = ( continuous load × 1.25 ) + noncontinuous load \text{Minimum feeder ampacity} = (\text{continuous load} \times 1.25) + \text{noncontinuous load} Minimum feeder ampacity = ( continuous load × 1.25 ) + noncontinuous load

They must also have an ampacity not less than the maximum load to be served after applying any adjustment or correction factors.

That is a two-part test, and both parts must pass:

Before derating: conductor ampacity from the appropriate column of Table 310.16 must meet the 125% calculation.

After derating: the ampacity adjusted for ambient temperature and conductor bundling must meet the actual calculated load.

Worked Example

A feeder supplies a panel with 90 A of continuous load and 40 A of noncontinuous load. The terminals at both ends are rated 75 °C.

( 90 × 1.25 ) + 40 = 112.5 + 40 = 152.5 A (90 \times 1.25) + 40 = 112.5 + 40 = 152.5\ \text{A} ( 90 × 1.25 ) + 40 = 112.5 + 40 = 152.5 A

Because the circuit exceeds 100 A, 110.14(C)(1)(b) permits the 75 °C column.

From Table 310.16, 1/0 AWG copper at 75 °C = 150 A (insufficient); 2/0 AWG copper at 75 °C = 175 A ✔

Feeder overcurrent device per 215.3 : not less than 152.5 A, so a 175 A standard device.

Feeder Overcurrent Protection — NEC 215.3

The feeder overcurrent protective device must have a rating not less than the noncontinuous load plus 125 percent of the continuous load . Where the assembly and the overcurrent device are listed for operation at 100 percent of their rating , the 125% multiplier is not applied to the continuous portion — a listing that in practice is limited to certain equipment rated 400 A and above.

Feeder taps that omit overcurrent protection at the point of supply are governed by 240.21(B) , covered in detail in Section 6.3.

Feeder Grounded Conductor and Equipment Grounding Conductor

Conductor Sizing Rule

Grounded (neutral) feeder conductor Sized to the maximum unbalanced load under 220.61, and never smaller than required by 250.102(C) where it also serves as the effective ground-fault current path for the feeder

Equipment grounding conductor Sized from Table 250.122 based on the rating of the feeder overcurrent device, and increased proportionally where the ungrounded conductors are increased in size for voltage drop (250.122(B))

Section 7.3 covers Table 250.122 and the proportional-increase rule in depth.

Feeder Ground-Fault Protection — NEC 215.10

GFPE is required for each feeder disconnect rated 1,000 amperes or more on a solidly grounded wye system of more than 150 volts to ground but not exceeding 1,000 volts phase-to-phase , mirroring the service rule at 230.95.

The important exception: GFPE is not required for a feeder disconnect where ground-fault protection is provided on the supply side of the feeder — you do not stack redundant GFPE at the service and again at the feeder. Continuous industrial processes and fire pumps are also excepted.

Identification and Documentation

Rule Requirement

215.12(A) Where a premises has feeders supplied from more than one nominal voltage system , each ungrounded feeder conductor must be identified by phase or line and system , using separate color coding, marking tape, tagging, or other approved means, and the method must be documented and readily available or permanently posted at each feeder distribution equipment location

215.12(B) Grounded conductors of more than one system in the same raceway or enclosure must be identified per 200.6

215.5 Feeder diagrams may be required by the AHJ prior to installation

215.6 Where a feeder supplies branch circuits requiring equipment grounding conductors , the feeder must include or provide an equipment grounding conductor

215.9 Feeders may be protected by a GFCI device in lieu of the provisions for GFCI protection specified in 210.8 and 590.6(A)

Michigan Overlay

Two Michigan-relevant feeder rules are covered elsewhere in this guide and should not be answered from the plain NEC text:

215.18 surge protection — required for feeders supplying dwelling units, dormitory units, hotel and motel guest rooms and guest suites, and nursing home and limited-care facility patient sleeping rooms. See Section 10.4.

225.41 feeder emergency disconnect — for a one- or two-family dwelling supplied by a feeder, the disconnect must be on or within sight of the dwelling unit. See Section 10.4.