Study guide
8.3 Michigan's Ice Barrier Requirement: Coverage, Materials & Detailing (R905.1.2)
Michigan Roofing Contractor Exam
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: The Exam & Michigan Licensing Law
1.1 The Michigan Roofing License Exam: Format, Fees & Test-Day Rules 1.2 Who Must Be Licensed: Residential Builder vs. M&A Roofing & the Exemptions 1.3 Prelicensure Education, Application, Renewal & Continuing Competency 1.4 Company Licenses, Qualifying Officers, Salespersons & Reporting Changes 1.5 Rules of Conduct: Place of Business, Advertising, Written Agreements & Records 1.6 Complaints, Investigations, Hearings, Arbitration & Penalties
2 Chapter 2: Codes, Permits, Civil Rights & Environmental Rules
2.1 The State Construction Code, Permits & Inspections 2.2 Civil Rights, Fair Housing, ADA & Michigan Barrier-Free Design 2.3 EPA Hazardous-Materials Rules: Lead-Safe Renovation, Asbestos & Radon
3 Chapter 3: Business Organization, Contracts & In-Home Sales
3.1 Types of Business Organization: Sole Proprietorship, Partnership, LLC & Corporation 3.2 Contract Essentials: Requirements, Types, Terminology & When a Contract Binds 3.3 Addenda, Change Orders, Allowances, Schedules, Warranties, Financing & Breach 3.4 In-Home Sales: The Home Solicitation Sales Act & Door-to-Door Roofing Sales
4 Chapter 4: Project Management, Accounting, Taxes & Personnel
4.1 Project Management & Administration: Quality, Logistics, Schedules, Draws & Retainage 4.2 Accounting & Finance: Costs, Receivables, Cash Flow, Financial Statements & Ratios 4.3 Payroll & Tax Obligations: Federal, Michigan, Unemployment & Sales/Use Tax 4.4 Personnel: MIOSHA Administration, Recordkeeping, Wages, Minors & Benefits
5 Chapter 5: Insurance, Bonds & Construction Liens
5.1 Insurance for Roofing Contractors: Liability, Workers' Compensation, Vehicles, Property & Builders' Risk 5.2 Bonds, Public Works Bonding & the Building Contract Fund Act 5.3 Construction Lien Act I: Notices of Commencement & Furnishing, Sworn Statements & Waivers 5.4 Construction Lien Act II: Claims of Lien, Foreclosure, Priority & Residential Protections
6 Chapter 6: Roofing Safety & Public Protection (MIOSHA)
6.1 MIOSHA Part 45 Fall Protection & Personal Fall Arrest Systems 6.2 Guardrails, Safety Nets, Warning Lines, Safety Monitors, Covers & Fall Protection Plans 6.3 Ladders, Scaffolds, Roof Brackets & Aerial Lifts (MIOSHA Parts 11, 12 & 32) 6.4 Hazard Communication, SDS, Silica, Lead & Asbestos Exposure, Power Lines & Heat 6.5 Hoisting & Lift Equipment, Fire Prevention, PPE, Barricades, Debris & Recycling
7 Chapter 7: Planning, Structure & Estimating
7.1 Roof Types, Framing Terminology & Structural Loads 7.2 Pre-Job Walk-Through, Plans & Details, Permits & Selecting the Roof System 7.3 Roof Geometry, Slope, Pitch & Slope Factors for Measuring Roofs 7.4 Material Takeoffs: Squares, Bundles, Waste, Underlayment, Ice Barrier, Metals & Fasteners 7.5 Labor, Subcontractor & Access Costs and Preparing the Estimate
8 Chapter 8: Tear-Off, Deck Preparation & Underlayment
8.1 Roof Sheathing: Panel Grades, Spans, Edge Support & Nailing 8.2 Tear-Off vs. Recover, Reroofing Rules & Preparing the Site (MRC R908) 8.3 Michigan's Ice Barrier Requirement: Coverage, Materials & Detailing (R905.1.2) 8.4 Underlayment: Standards, Application by Slope & Attachment (R905.1.1) 8.5 Roof & Ceiling Insulation, Vapor Retarders, Air Sealing & Unvented Assemblies
9 Chapter 9: Steep-Slope Roof Systems
9.1 Asphalt Shingles: Types, ASTM D3462, Wind Classes, Impact & Fire Ratings 9.2 Installing Asphalt Shingles: Starter, Exposure, Nailing, Steep Slopes & Caps 9.3 Valleys: Linings, Open Metal, Closed-Cut & Woven Valleys 9.4 Metal Roof Systems, Tile, Slate & Wood Shingles and Shakes
10 Chapter 10: Low-Slope Roof Systems & Drainage
10.1 Single-Ply Membranes: EPDM, TPO & PVC 10.2 Built-Up Roofing & Modified Bitumen: Materials, Application, Kettles & Torch Safety 10.3 Low-Slope Drainage: Positive Drainage, Roof Drains, Overflow Scuppers & Correcting Ponding
11 Chapter 11: Flashings, Transitions & Penetrations
11.1 Drip Edge & Roof-Edge Metals (R905.2.8.5 and R903.2) 11.2 Sidewalls, Headwalls, Kick-Outs, Counterflashing & Pitch Transitions 11.3 Chimneys & Crickets, Skylights, Pipes, Flues, Exhaust Vents & Solar
12 Chapter 12: Ventilation, Inspection & Repair
12.1 Attic Ventilation Requirements & Net Free Vent Area Calculations (MRC R806) 12.2 Balanced Airflow, Vent Installation Practice & Preventing Ice Dams 12.3 Roof Inspections, Leak Diagnosis, Repairs & Roofovers
8.3 Michigan's Ice Barrier Requirement: Coverage, Materials & Detailing (R905.1.2)
Key Takeaways Explain This Topic AI
The ice barrier must extend from the lowest edges of all roof surfaces to a point at least 24 inches inside the exterior wall line of the building.
On roofs of 8:12 or steeper, the ice barrier must also extend at least 36 inches measured along the roof slope from the eave edge.
An approved ice barrier is at least two layers of underlayment cemented together, or a self-adhering polymer-modified bitumen sheet, used in place of normal underlayment.
Detached accessory structures that contain no conditioned floor area are exempt.
At eaves, underlayment and ice barrier go over the drip edge, and at rakes, they go under the drip edge (R905.2.8.5).
Last updated: September 2026
Why Every Michigan Roof Needs It
Ice dams form when heat from the house melts snow on the upper roof and the meltwater refreezes at the cold eave. Water then backs up behind the ice and under the shingles, which shed water but do not seal against it. The IRC leaves the ice barrier decision to each jurisdiction's climate table. Michigan's Table R301.2(1) marks "Ice Barrier Underlayment Required: Yes" (R 408.30516). Footnote (h) ties that entry to areas where the average daily January temperature is 25°F or less, or where there is a history of ice-dam damage. For Michigan homes, treat the ice barrier as required.
The Rule (R905.1.2)
In areas where there has been a history of ice forming along the eaves causing a backup of water as designated in Table R301.2(1), an ice barrier shall be installed for asphalt shingles, metal roof shingles, mineral-surfaced roll roofing, slate and slate-type shingles, wood shingles and wood shakes. The ice barrier shall consist of not fewer than two layers of underlayment cemented together, or a self-adhering polymer-modified bitumen sheet shall be used in place of normal underlayment and extend from the lowest edges of all roof surfaces to a point not less than 24 inches inside the exterior wall line of the building. On roofs with slope equal to or greater than 8 units vertical in 12 units horizontal, the ice barrier shall also be applied not less than 36 inches measured along the roof slope from the eave edge of the building.
Exception: Detached accessory structures not containing conditioned floor area.
The individual covering sections repeat the requirement, including R905.2.7 for asphalt shingles, R905.4.3.1 for metal shingles, R905.5.3.1 for roll roofing, R905.6.3.1 for slate, R905.7.3.1 for wood shingles, and R905.8.3.1 for shakes. Photovoltaic shingles have their own version in R905.16.4.1.
Measuring the Coverage
The code measures to a point 24 inches inside the exterior wall line . The exterior wall line is the outside face of the wall where it meets the roof. A practical method:
Measure the horizontal eave overhang from the fascia (or drip edge) back to the exterior face of the wall.
Add 24 inches to get the horizontal distance.
Multiply by the common slope factor to get the distance along the deck.
On 8:12 and steeper roofs, use the larger of that result and 36 inches along the slope.
Divide by the membrane's usable width, subtracting side laps, and round up to whole courses.
- Overhang Slope Along the slope Rule that controls 36-inch courses
- 8 in 4:12 (8 + 24) × 1.054 = 33.7 in 24 in inside the wall 1
- 12 in 4:12 (12 + 24) × 1.054 = 37.9 in 24 in inside the wall 2
- 12 in 6:12 (12 + 24) × 1.118 = 40.2 in 24 in inside the wall 2
- 0 in (no overhang) 10:12 24 × 1.302 = 31.2 in 36 in along the slope (8:12 or steeper) 1, and must reach 36 in
- 18 in 12:12 (18 + 24) × 1.414 = 59.4 in 24 in inside the wall 2
Going past the minimum costs little. Many Michigan contractors run two courses at eaves as standard practice and add membrane in valleys, around chimneys and skylights, and at low-slope transitions.
Approved Materials
Self-adhering polymer-modified bitumen sheet (ASTM D1970 is the standard for these underlayments, and the R905.1.1 exception allows D1970 membranes). This is the common modern choice. It seals around nail shanks.
Two layers of underlayment cemented together , the traditional method of solid-mopping or cementing two felt plies.
Either one is installed in place of normal underlayment in the ice barrier area.
Valleys and Other Details
Valley lining rules are in R905.2.8.2 (Section 9.3). ASTM D1970 self-adhering membrane may be used in place of the listed valley linings.
For metal valley flashing under tile or metal shingles, R905.3.8 and R905.4.6 add a rule for areas where the average January temperature is 25°F or less. There, the metal valley flashing underlayment must be solid-cemented to the roofing underlayment on slopes under 7:12, or be self-adhering polymer-modified bitumen.
Wood shingle and shake roofs in those cold areas need solid sheathing under the ice barrier portion of the roof (R905.7.1.1, R905.8.1.1).
Drip Edge Sequence
R905.2.8.5 : underlayment goes over the drip edge along eaves and under the drip edge along rake edges . At the eave, install the drip edge on the deck, then run the ice barrier over its flange. Water that backs up behind an ice dam then flows over the metal instead of behind it. At the rake, install the underlayment first and the drip edge over it.
Cold-Weather Application
Self-adhered membranes depend on temperature for adhesion. Follow the manufacturer's minimum application temperature and any primer, storage, or back-nailing instructions. Keep rolls warm before use, and do not apply over frost, snow, or wet decks. Never use an open flame to warm a self-adhered membrane on a wood deck.
Replacement Jobs
On a replacement, an existing ice barrier bonded to the deck may stay if it is covered with a new layer (R908.3 exception). On a legal recover, the new covering must still meet Chapter 9, including the ice barrier requirement (R908.1).