11.1 Drip Edge & Roof-Edge Metals (R905.2.8.5 and R903.2)
Michigan Roofing Contractor Exam
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: The Exam & Michigan Licensing Law
1.1 The Michigan Roofing License Exam: Format, Fees & Test-Day Rules 1.2 Who Must Be Licensed: Residential Builder vs. M&A Roofing & the Exemptions 1.3 Prelicensure Education, Application, Renewal & Continuing Competency 1.4 Company Licenses, Qualifying Officers, Salespersons & Reporting Changes 1.5 Rules of Conduct: Place of Business, Advertising, Written Agreements & Records 1.6 Complaints, Investigations, Hearings, Arbitration & Penalties
2 Chapter 2: Codes, Permits, Civil Rights & Environmental Rules
2.1 The State Construction Code, Permits & Inspections 2.2 Civil Rights, Fair Housing, ADA & Michigan Barrier-Free Design 2.3 EPA Hazardous-Materials Rules: Lead-Safe Renovation, Asbestos & Radon
3 Chapter 3: Business Organization, Contracts & In-Home Sales
3.1 Types of Business Organization: Sole Proprietorship, Partnership, LLC & Corporation 3.2 Contract Essentials: Requirements, Types, Terminology & When a Contract Binds 3.3 Addenda, Change Orders, Allowances, Schedules, Warranties, Financing & Breach 3.4 In-Home Sales: The Home Solicitation Sales Act & Door-to-Door Roofing Sales
4 Chapter 4: Project Management, Accounting, Taxes & Personnel
4.1 Project Management & Administration: Quality, Logistics, Schedules, Draws & Retainage 4.2 Accounting & Finance: Costs, Receivables, Cash Flow, Financial Statements & Ratios 4.3 Payroll & Tax Obligations: Federal, Michigan, Unemployment & Sales/Use Tax 4.4 Personnel: MIOSHA Administration, Recordkeeping, Wages, Minors & Benefits
5 Chapter 5: Insurance, Bonds & Construction Liens
5.1 Insurance for Roofing Contractors: Liability, Workers' Compensation, Vehicles, Property & Builders' Risk 5.2 Bonds, Public Works Bonding & the Building Contract Fund Act 5.3 Construction Lien Act I: Notices of Commencement & Furnishing, Sworn Statements & Waivers 5.4 Construction Lien Act II: Claims of Lien, Foreclosure, Priority & Residential Protections
6 Chapter 6: Roofing Safety & Public Protection (MIOSHA)
6.1 MIOSHA Part 45 Fall Protection & Personal Fall Arrest Systems 6.2 Guardrails, Safety Nets, Warning Lines, Safety Monitors, Covers & Fall Protection Plans 6.3 Ladders, Scaffolds, Roof Brackets & Aerial Lifts (MIOSHA Parts 11, 12 & 32) 6.4 Hazard Communication, SDS, Silica, Lead & Asbestos Exposure, Power Lines & Heat 6.5 Hoisting & Lift Equipment, Fire Prevention, PPE, Barricades, Debris & Recycling
7 Chapter 7: Planning, Structure & Estimating
7.1 Roof Types, Framing Terminology & Structural Loads 7.2 Pre-Job Walk-Through, Plans & Details, Permits & Selecting the Roof System 7.3 Roof Geometry, Slope, Pitch & Slope Factors for Measuring Roofs 7.4 Material Takeoffs: Squares, Bundles, Waste, Underlayment, Ice Barrier, Metals & Fasteners 7.5 Labor, Subcontractor & Access Costs and Preparing the Estimate
8 Chapter 8: Tear-Off, Deck Preparation & Underlayment
8.1 Roof Sheathing: Panel Grades, Spans, Edge Support & Nailing 8.2 Tear-Off vs. Recover, Reroofing Rules & Preparing the Site (MRC R908) 8.3 Michigan's Ice Barrier Requirement: Coverage, Materials & Detailing (R905.1.2) 8.4 Underlayment: Standards, Application by Slope & Attachment (R905.1.1) 8.5 Roof & Ceiling Insulation, Vapor Retarders, Air Sealing & Unvented Assemblies
9 Chapter 9: Steep-Slope Roof Systems
9.1 Asphalt Shingles: Types, ASTM D3462, Wind Classes, Impact & Fire Ratings 9.2 Installing Asphalt Shingles: Starter, Exposure, Nailing, Steep Slopes & Caps 9.3 Valleys: Linings, Open Metal, Closed-Cut & Woven Valleys 9.4 Metal Roof Systems, Tile, Slate & Wood Shingles and Shakes
10 Chapter 10: Low-Slope Roof Systems & Drainage
10.1 Single-Ply Membranes: EPDM, TPO & PVC 10.2 Built-Up Roofing & Modified Bitumen: Materials, Application, Kettles & Torch Safety 10.3 Low-Slope Drainage: Positive Drainage, Roof Drains, Overflow Scuppers & Correcting Ponding
11 Chapter 11: Flashings, Transitions & Penetrations
11.1 Drip Edge & Roof-Edge Metals (R905.2.8.5 and R903.2) 11.2 Sidewalls, Headwalls, Kick-Outs, Counterflashing & Pitch Transitions 11.3 Chimneys & Crickets, Skylights, Pipes, Flues, Exhaust Vents & Solar
12 Chapter 12: Ventilation, Inspection & Repair
12.1 Attic Ventilation Requirements & Net Free Vent Area Calculations (MRC R806) 12.2 Balanced Airflow, Vent Installation Practice & Preventing Ice Dams 12.3 Roof Inspections, Leak Diagnosis, Repairs & Roofovers
11.1 Drip Edge & Roof-Edge Metals (R905.2.8.5 and R903.2)
Key Takeaways Explain This Topic AI
A drip edge is required at eaves and rake edges of shingle roofs, with adjacent pieces lapped at least 2 inches.
The drip edge must extend at least 1/4 inch below the roof sheathing and at least 2 inches back onto the roof deck.
Drip edge is mechanically fastened to the deck at no more than 12 inches on center, using roofing nails that meet R905.2.5.
Underlayment goes over the drip edge at eaves and under the drip edge at rakes.
Where roof flashing is metal, R903.2.1 requires corrosion-resistant metal at least 0.019 inch thick (No. 26 galvanized sheet).
Last updated: September 2026
Why Edges Need Metal
Water running off a roof edge clings to the edge and can wick back behind the shingles, soaking the sheathing edge and fascia. Wind also drives rain under rake edges. A drip edge supports the shingle overhang, directs water clear of the fascia, and protects the deck edge. In Michigan, the eave detail must also work with the ice barrier (Section 8.3).
The Code Rule (R905.2.8.5)
A drip edge shall be provided at eaves and rake edges of shingle roofs. Adjacent segments of drip edge shall be overlapped not less than 2 inches. Drip edges shall extend not less than 1/4 inch below the roof sheathing and extend up back onto the roof deck not less than 2 inches. Drip edges shall be mechanically fastened to the roof deck at not more than 12 inches o.c. with fasteners as specified in Section R905.2.5. Underlayment shall be installed over the drip edge along eaves and under the drip edge along rake edges.
- Requirement Value
- Where All eaves and rake edges of shingle roofs
- End laps between pieces At least 2 inches
- Below the sheathing At least 1/4 inch
- Deck flange At least 2 inches onto the deck
- Fastening Mechanically fastened, 12 inches on center maximum , with roofing nails meeting R905.2.5
- Sequence Underlayment over the drip edge at eaves . Under the drip edge at rakes
- General Flashing Rules (R903.2)
R903.2: flashings must keep moisture out of walls and roofs through joints in copings, through moisture-permeable materials, and at intersections with parapet walls and other penetrations.
R903.2.1 locations: flashing is required at wall and roof intersections , wherever there is a change in roof slope or direction , and around roof openings . It also requires a flashing that diverts water away where the eave of a sloped roof meets a vertical sidewall , which is the kick-out (Section 11.2).
Metal thickness: where flashing is metal, it must be corrosion-resistant and at least 0.019 inch (No. 26 galvanized sheet) .
R903.3: parapet walls need noncombustible, weatherproof coping at least as wide as the wall.
The code sets drip edge dimensions and fastening but does not give a separate drip edge gauge table. Choose a durable, corrosion-resistant product, such as galvanized, prefinished steel, aluminum, or copper, compatible with the gutters and other metals. Use the shingle manufacturer's accepted profiles where a system warranty is involved.
Common Profiles
- Profile Use
- L-style (angle) Basic eave or rake edge
- Drip-style (D or T) Has a kick-out lip that throws water clear of the fascia. Common at eaves
- Gutter apron A longer flange that directs water into the gutter, often used at eaves with gutters
- Rake edge or gable trim Covers the rake board, and sometimes has a hem to lock the edge
- Vented drip edge Combines edge metal with an intake vent, for eaves without soffits (Section 12.2)
- Installing Drip Edge
- At the Eave
Install the drip edge directly on the deck along the eave. Set the face tight to the fascia, and extend it at least 1/4 inch below the sheathing.
Nail through the deck flange at no more than 12 inches on center , into the deck. Don't nail through the face into the fascia, because face-nailing can buckle the metal as it moves with temperature.
Lap pieces at least 2 inches . Many installers lap in the direction that sheds water away from prevailing winds.
Apply the ice barrier and underlayment over the drip edge flange (R905.2.8.5).
At the Rake
Install the underlayment first , running it to the rake edge.
Install the rake drip edge over the underlayment, and nail at no more than 12 inches on center.
At the bottom of the rake, lap the rake piece over the eave piece so water running down the rake flows onto the eave metal, not behind it.
At the top of a gable, lap the lower piece under the upper piece so water sheds downslope, or miter it neatly per the manufacturer.
Shingle Overhang
Shingles overhang the drip edge slightly, commonly about 1/4 to 3/4 inch, as the manufacturer specifies. The starter course's sealant near the edge keeps the first course from lifting.
Gutters and Drip Edge
The drip edge or gutter apron should shed water into the gutter, not behind it. Set gutters so the drip edge extends past the gutter's back edge.
In Michigan, ice and snow load gutters heavily. Use strong hangers at close spacing, per the gutter manufacturer. Keep downspouts discharging away from foundations.
Gutters are a separate M&A trade (siding and gutters). A roofer may do incidental gutter work related to the roof, such as removing and reinstalling gutters (MCL 339.2404(3)).
Material Compatibility
Don't mix copper with galvanized steel or aluminum where runoff or contact causes galvanic corrosion. Copper runoff also stains and corrodes aluminum gutters.
Use fasteners of a compatible metal: galvanized with galvanized, stainless or copper with copper. The code requires compatible materials (R904.2).
Prime metal before adhering bituminous products where required (R908.6 for reroofing flashings).
Reroofing
On a reroof, replace rusted, damaged, or deteriorated edgings and flashings (R908.5). Installing new drip edge on a tear-off lets you set the ice barrier over the flange properly. On a legal recover, the new roof must still meet Chapter 9, including drip edge (R908.1).