Study guide
4.1 Project Management & Administration: Quality, Logistics, Schedules, Draws & Retainage
Michigan Roofing Contractor Exam
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: The Exam & Michigan Licensing Law
1.1 The Michigan Roofing License Exam: Format, Fees & Test-Day Rules 1.2 Who Must Be Licensed: Residential Builder vs. M&A Roofing & the Exemptions 1.3 Prelicensure Education, Application, Renewal & Continuing Competency 1.4 Company Licenses, Qualifying Officers, Salespersons & Reporting Changes 1.5 Rules of Conduct: Place of Business, Advertising, Written Agreements & Records 1.6 Complaints, Investigations, Hearings, Arbitration & Penalties
2 Chapter 2: Codes, Permits, Civil Rights & Environmental Rules
2.1 The State Construction Code, Permits & Inspections 2.2 Civil Rights, Fair Housing, ADA & Michigan Barrier-Free Design 2.3 EPA Hazardous-Materials Rules: Lead-Safe Renovation, Asbestos & Radon
3 Chapter 3: Business Organization, Contracts & In-Home Sales
3.1 Types of Business Organization: Sole Proprietorship, Partnership, LLC & Corporation 3.2 Contract Essentials: Requirements, Types, Terminology & When a Contract Binds 3.3 Addenda, Change Orders, Allowances, Schedules, Warranties, Financing & Breach 3.4 In-Home Sales: The Home Solicitation Sales Act & Door-to-Door Roofing Sales
4 Chapter 4: Project Management, Accounting, Taxes & Personnel
4.1 Project Management & Administration: Quality, Logistics, Schedules, Draws & Retainage 4.2 Accounting & Finance: Costs, Receivables, Cash Flow, Financial Statements & Ratios 4.3 Payroll & Tax Obligations: Federal, Michigan, Unemployment & Sales/Use Tax 4.4 Personnel: MIOSHA Administration, Recordkeeping, Wages, Minors & Benefits
5 Chapter 5: Insurance, Bonds & Construction Liens
5.1 Insurance for Roofing Contractors: Liability, Workers' Compensation, Vehicles, Property & Builders' Risk 5.2 Bonds, Public Works Bonding & the Building Contract Fund Act 5.3 Construction Lien Act I: Notices of Commencement & Furnishing, Sworn Statements & Waivers 5.4 Construction Lien Act II: Claims of Lien, Foreclosure, Priority & Residential Protections
6 Chapter 6: Roofing Safety & Public Protection (MIOSHA)
6.1 MIOSHA Part 45 Fall Protection & Personal Fall Arrest Systems 6.2 Guardrails, Safety Nets, Warning Lines, Safety Monitors, Covers & Fall Protection Plans 6.3 Ladders, Scaffolds, Roof Brackets & Aerial Lifts (MIOSHA Parts 11, 12 & 32) 6.4 Hazard Communication, SDS, Silica, Lead & Asbestos Exposure, Power Lines & Heat 6.5 Hoisting & Lift Equipment, Fire Prevention, PPE, Barricades, Debris & Recycling
7 Chapter 7: Planning, Structure & Estimating
7.1 Roof Types, Framing Terminology & Structural Loads 7.2 Pre-Job Walk-Through, Plans & Details, Permits & Selecting the Roof System 7.3 Roof Geometry, Slope, Pitch & Slope Factors for Measuring Roofs 7.4 Material Takeoffs: Squares, Bundles, Waste, Underlayment, Ice Barrier, Metals & Fasteners 7.5 Labor, Subcontractor & Access Costs and Preparing the Estimate
8 Chapter 8: Tear-Off, Deck Preparation & Underlayment
8.1 Roof Sheathing: Panel Grades, Spans, Edge Support & Nailing 8.2 Tear-Off vs. Recover, Reroofing Rules & Preparing the Site (MRC R908) 8.3 Michigan's Ice Barrier Requirement: Coverage, Materials & Detailing (R905.1.2) 8.4 Underlayment: Standards, Application by Slope & Attachment (R905.1.1) 8.5 Roof & Ceiling Insulation, Vapor Retarders, Air Sealing & Unvented Assemblies
9 Chapter 9: Steep-Slope Roof Systems
9.1 Asphalt Shingles: Types, ASTM D3462, Wind Classes, Impact & Fire Ratings 9.2 Installing Asphalt Shingles: Starter, Exposure, Nailing, Steep Slopes & Caps 9.3 Valleys: Linings, Open Metal, Closed-Cut & Woven Valleys 9.4 Metal Roof Systems, Tile, Slate & Wood Shingles and Shakes
10 Chapter 10: Low-Slope Roof Systems & Drainage
10.1 Single-Ply Membranes: EPDM, TPO & PVC 10.2 Built-Up Roofing & Modified Bitumen: Materials, Application, Kettles & Torch Safety 10.3 Low-Slope Drainage: Positive Drainage, Roof Drains, Overflow Scuppers & Correcting Ponding
11 Chapter 11: Flashings, Transitions & Penetrations
11.1 Drip Edge & Roof-Edge Metals (R905.2.8.5 and R903.2) 11.2 Sidewalls, Headwalls, Kick-Outs, Counterflashing & Pitch Transitions 11.3 Chimneys & Crickets, Skylights, Pipes, Flues, Exhaust Vents & Solar
12 Chapter 12: Ventilation, Inspection & Repair
12.1 Attic Ventilation Requirements & Net Free Vent Area Calculations (MRC R806) 12.2 Balanced Airflow, Vent Installation Practice & Preventing Ice Dams 12.3 Roof Inspections, Leak Diagnosis, Repairs & Roofovers
4.1 Project Management & Administration: Quality, Logistics, Schedules, Draws & Retainage
Key Takeaways Explain This Topic AI
Quality assurance is the planned system that prevents defects, and quality control is inspecting and testing the work to catch defects.
The critical path is the longest chain of dependent tasks, and any delay on it delays project completion unless the schedule is recovered.
Retainage is a percentage of each payment withheld until completion, and under the Construction Lien Act it is not due until the stated condition occurs.
MIOSHA prohibits storing roofing materials and equipment within 6 feet of a roof edge while roofing work is performed unless guardrails are erected.
In an M&A contract, the licensee must give the lender the purchaser's signed completion certificate when the work is finished.
Last updated: September 2026
Quality Assurance and Quality Control
Quality assurance (QA) is the system that prevents defects. It includes written specifications, manufacturer installation instructions on site, a pre-job meeting with the crew, trained installers, and correct materials delivered.
Quality control (QC) is checking the work: deck inspection after tear-off, nail-placement spot checks, flashing inspections before shingles cover them, and a final punch-list walk.
A simple roofing QC checklist covers deck condition and fastening, ice barrier coverage past the exterior wall line, drip edge sequence, underlayment laps, nail line and count, valley method, step and counterflashing, ventilation openings, and cleanup. Document it with dated photos. The photos also help in a workmanship complaint, because the licensee must refute the evidence under MCL 339.2411(4)(b).
Materials and Logistics
Order by the takeoff (Chapter 7) and check deliveries against the order: product line, color, and quantities.
Stage and load safely. Under R 408.40810(7) (MIOSHA Part 8), while roofing work is performed, materials and equipment may not be stored within 6 feet of a roof edge unless guardrails are erected at the edge. Spread bundles over framing lines rather than stacking them in the middle of a rafter bay, and never overload the structure (MRC R908.2).
Protect materials. Store rolls on end if the manufacturer requires, keep bundles flat and dry, and keep self-adhered membranes within their temperature limits.
Plan debris handling. Position the dumpster, set up a chute or barricaded drop zone (Section 6.5), and arrange disposal of any lead or asbestos debris separately.
Cost Management
Compare actual costs with the estimate on every job. Track labor hours by task, material overages, disposal weights, and change orders. A job-cost report shows whether the job is on budget while there is still time to correct course. Each change order should adjust both the contract price and the job budget.
Subcontractors
Before a subcontractor starts:
Confirm whether the work needs its own license. An electrician for a PV disconnect needs one. A labor crew working solely for you does not need a builder license under MCL 339.2403(e).
Collect certificates of insurance for liability and workers' compensation . If an uninsured subcontractor's worker is hurt, you may be liable as the statutory employer (MCL 418.171; Section 5.1).
Use a written subcontract with scope, schedule, safety duties, and payment terms.
Pay against a sworn statement and lien waivers so that lower-tier liens do not reach the owner (Section 5.3).
Inspections
Schedule the building official's inspections the permit requires. Keep the permit on site (R105.7). Correct any failed items before covering the work. An inspection report can also support or defeat a workmanship complaint (MCL 339.2411(4)(c)).
Scheduling
A bar (Gantt) chart shows each task on a timeline.
The critical path method (CPM) links tasks in sequence. The critical path is the longest chain of dependent tasks, and any delay on it delays completion. Float is the time a noncritical task can slip without delaying completion.
Weather drives roofing schedules. Plan tear-offs so the roof can be dried in the same day, and watch temperature limits for sealants and self-adhered membranes.
Example: The sequence is tear-off (1 day), deck repair (0.5 day), dry-in (0.5 day), shingles (2 days), flashing and ridge (1 day), and cleanup (0.5 day), in that order. That is 5.5 days, all on the critical path. Gutter replacement by a subcontractor (1 day), which can happen any time after shingles and before cleanup, has float.
Draws, Progress Payments, and Retainage
Term Meaning
Deposit Initial payment at signing or delivery. LARA advises homeowners never to pay the entire job in advance and to pay by check to the company name
Progress payment Payment tied to milestones or percentage complete, such as materials delivered, tear-off and dry-in complete, and final
Draw A lender releases loan funds for completed work, often through a title company, and usually requires a sworn statement and lien waivers
- Retainage A percentage of each payment, commonly 5% to 10%, withheld until final completion or acceptance
- Schedule of values Breakdown of the contract price by work item, used to compute progress payments
Retainage calculation: Contract price $40,000, work 60% complete, retainage 10%.
Earned = 0.60 × 40,000 = 24,000 \text{Earned} = 0.60 \times 40{,}000 = 24{,}000 Earned = 0.60 × 40 , 000 = 24 , 000
Payment due = 24,000 × ( 1 − 0.10 ) = 21,600 \text{Payment due} = 24{,}000 \times (1 - 0.10) = 21{,}600 Payment due = 24 , 000 × ( 1 − 0.10 ) = 21 , 600
The owner holds $2,400 in retainage. Under the Construction Lien Act, retainage that is not payable until a stated event occurs, beyond providing the improvement, is not due until that event (MCL 570.1115(5)).
Closeout and Customer Service
Completion certificate. In an M&A contract, failing to give the lender the purchaser's signed completion certificate when the work is done is a ground for discipline (MCL 339.2411(2)(f)).
Final documents: full unconditional lien waivers from you and your suppliers and subcontractors, manufacturer warranty registration, the workmanship warranty, and any inspection approvals.
Communication: Tell the owner the schedule, what to expect during tear-off (noise, debris, driveway access), and how to reach you.
Complaints: Respond quickly. If LARA forwards a complaint, you must reply within 15 days (R 338.1551). If a structural matter is materially deficient or dangerous, fix it. Refusing is presumed dishonest or unfair dealing (R 338.1551(4)).