7.5 Labor, Subcontractor & Access Costs and Preparing the Estimate
Michigan Roofing Contractor Exam
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: The Exam & Michigan Licensing Law
1.1 The Michigan Roofing License Exam: Format, Fees & Test-Day Rules 1.2 Who Must Be Licensed: Residential Builder vs. M&A Roofing & the Exemptions 1.3 Prelicensure Education, Application, Renewal & Continuing Competency 1.4 Company Licenses, Qualifying Officers, Salespersons & Reporting Changes 1.5 Rules of Conduct: Place of Business, Advertising, Written Agreements & Records 1.6 Complaints, Investigations, Hearings, Arbitration & Penalties
2 Chapter 2: Codes, Permits, Civil Rights & Environmental Rules
2.1 The State Construction Code, Permits & Inspections 2.2 Civil Rights, Fair Housing, ADA & Michigan Barrier-Free Design 2.3 EPA Hazardous-Materials Rules: Lead-Safe Renovation, Asbestos & Radon
3 Chapter 3: Business Organization, Contracts & In-Home Sales
3.1 Types of Business Organization: Sole Proprietorship, Partnership, LLC & Corporation 3.2 Contract Essentials: Requirements, Types, Terminology & When a Contract Binds 3.3 Addenda, Change Orders, Allowances, Schedules, Warranties, Financing & Breach 3.4 In-Home Sales: The Home Solicitation Sales Act & Door-to-Door Roofing Sales
4 Chapter 4: Project Management, Accounting, Taxes & Personnel
4.1 Project Management & Administration: Quality, Logistics, Schedules, Draws & Retainage 4.2 Accounting & Finance: Costs, Receivables, Cash Flow, Financial Statements & Ratios 4.3 Payroll & Tax Obligations: Federal, Michigan, Unemployment & Sales/Use Tax 4.4 Personnel: MIOSHA Administration, Recordkeeping, Wages, Minors & Benefits
5 Chapter 5: Insurance, Bonds & Construction Liens
5.1 Insurance for Roofing Contractors: Liability, Workers' Compensation, Vehicles, Property & Builders' Risk 5.2 Bonds, Public Works Bonding & the Building Contract Fund Act 5.3 Construction Lien Act I: Notices of Commencement & Furnishing, Sworn Statements & Waivers 5.4 Construction Lien Act II: Claims of Lien, Foreclosure, Priority & Residential Protections
6 Chapter 6: Roofing Safety & Public Protection (MIOSHA)
6.1 MIOSHA Part 45 Fall Protection & Personal Fall Arrest Systems 6.2 Guardrails, Safety Nets, Warning Lines, Safety Monitors, Covers & Fall Protection Plans 6.3 Ladders, Scaffolds, Roof Brackets & Aerial Lifts (MIOSHA Parts 11, 12 & 32) 6.4 Hazard Communication, SDS, Silica, Lead & Asbestos Exposure, Power Lines & Heat 6.5 Hoisting & Lift Equipment, Fire Prevention, PPE, Barricades, Debris & Recycling
7 Chapter 7: Planning, Structure & Estimating
7.1 Roof Types, Framing Terminology & Structural Loads 7.2 Pre-Job Walk-Through, Plans & Details, Permits & Selecting the Roof System 7.3 Roof Geometry, Slope, Pitch & Slope Factors for Measuring Roofs 7.4 Material Takeoffs: Squares, Bundles, Waste, Underlayment, Ice Barrier, Metals & Fasteners 7.5 Labor, Subcontractor & Access Costs and Preparing the Estimate
8 Chapter 8: Tear-Off, Deck Preparation & Underlayment
8.1 Roof Sheathing: Panel Grades, Spans, Edge Support & Nailing 8.2 Tear-Off vs. Recover, Reroofing Rules & Preparing the Site (MRC R908) 8.3 Michigan's Ice Barrier Requirement: Coverage, Materials & Detailing (R905.1.2) 8.4 Underlayment: Standards, Application by Slope & Attachment (R905.1.1) 8.5 Roof & Ceiling Insulation, Vapor Retarders, Air Sealing & Unvented Assemblies
9 Chapter 9: Steep-Slope Roof Systems
9.1 Asphalt Shingles: Types, ASTM D3462, Wind Classes, Impact & Fire Ratings 9.2 Installing Asphalt Shingles: Starter, Exposure, Nailing, Steep Slopes & Caps 9.3 Valleys: Linings, Open Metal, Closed-Cut & Woven Valleys 9.4 Metal Roof Systems, Tile, Slate & Wood Shingles and Shakes
10 Chapter 10: Low-Slope Roof Systems & Drainage
10.1 Single-Ply Membranes: EPDM, TPO & PVC 10.2 Built-Up Roofing & Modified Bitumen: Materials, Application, Kettles & Torch Safety 10.3 Low-Slope Drainage: Positive Drainage, Roof Drains, Overflow Scuppers & Correcting Ponding
11 Chapter 11: Flashings, Transitions & Penetrations
11.1 Drip Edge & Roof-Edge Metals (R905.2.8.5 and R903.2) 11.2 Sidewalls, Headwalls, Kick-Outs, Counterflashing & Pitch Transitions 11.3 Chimneys & Crickets, Skylights, Pipes, Flues, Exhaust Vents & Solar
12 Chapter 12: Ventilation, Inspection & Repair
12.1 Attic Ventilation Requirements & Net Free Vent Area Calculations (MRC R806) 12.2 Balanced Airflow, Vent Installation Practice & Preventing Ice Dams 12.3 Roof Inspections, Leak Diagnosis, Repairs & Roofovers
7.5 Labor, Subcontractor & Access Costs and Preparing the Estimate
Key Takeaways Explain This Topic AI
Labor cost equals estimated hours times the wage rate plus labor burden (employer payroll taxes, workers' compensation, and benefits).
Access and "other" costs include dumpsters and disposal fees, hoists or boom delivery, fall protection setup, permits, and protection of landscaping and property.
Overhead is covered by pricing to a target gross margin. Selling price equals total direct cost divided by (1 minus the target margin).
Unit prices for concealed conditions, such as deck replacement per sheet, keep the base price firm and give the owner an agreed price for hidden damage.
The estimate becomes the contract only when it is written, signed, and states the specifications, cost, work, and materials under R 338.1533, with the licensing statement for lien rights.
Last updated: September 2026
Building the Labor Estimate
Break the job into tasks: tear-off (per layer), deck repair, dry-in (ice barrier and underlayment), drip edge, shingles, valleys, flashing (walls, chimney, penetrations), ventilation, ridge, and cleanup.
Apply production rates from your own job history, such as squares per crew-day for tear-off and for installation, adjusted for slope, height, access, cut-up areas, and weather season. Steep and high roofs slow production and need more fall-protection setup.
Convert to hours and multiply by the crew's wage rates.
Add labor burden: employer Social Security and Medicare (7.65%), FUTA, Michigan unemployment tax, workers' compensation (a large cost for roofing classifications), and benefits.
Example: A reroof is estimated at 96 crew-hours. The average wage is $26 per hour, and labor burden is 30% of wages.
Labor = 96 × 26 × 1.30 = 3,244.80 \text{Labor} = 96 \times 26 \times 1.30 = 3{,}244.80 Labor = 96 × 26 × 1.30 = 3 , 244.80
Factors That Change Production
Adjust your production rates for conditions the walk-through revealed:
Slope and height. Roofs steeper than about 8:12 need roof brackets or staging and slower, more careful movement. Two-story eaves add ladder and hoisting time.
Layers and deck. Each extra layer adds tear-off time and disposal weight. Board decks with gaps may need overlay sheathing.
Complexity. Valleys, dormers, skylights, and short runs between hips cut production far more than open planes do.
Access. Long carries from the truck, landscaping that blocks the drop zone, or no boom-truck access all add labor.
Season. Michigan's cold months slow self-adhered membrane and sealant work, and daylight is shorter. Summer heat needs more breaks.
Subcontractors
List each subcontracted scope as its own line, such as gutter replacement, chimney masonry repair, skylight replacement by a glazing contractor, or a PV removal and reinstall by a licensed electrician. Get written quotes. Confirm licenses where the work requires them, and collect insurance certificates, because an uninsured subcontractor's injured worker can become your workers' compensation claim (MCL 418.171).
Access, Equipment, and Other Direct Costs
Item Examples
Access and loading Rooftop boom delivery, ladder hoist or conveyor rental, extra ladders, scaffold or roof jacks
- Fall protection Anchors (often left in place or replaced), lifelines, guardrail systems, and setup time
- Disposal Dumpster rental, hauling, and landfill fees by weight. Lead or asbestos debris is handled separately
- Permits and inspections Local permit fee
- Protection Tarps, plywood for condensers and driveways, and magnetic sweeping
Materials From the takeoff (Section 7.4), including sales or use tax, which in Michigan is the contractor's cost
- Warranty costs Manufacturer registration fees and a reserve for workmanship callbacks
- Overhead and Profit
Overhead is the cost of running the business: office, vehicles, insurance, estimator time, licensing, advertising. Price each job to recover its share of overhead and a profit.
Selling price = Total direct cost 1 − target gross margin \text{Selling price} = \frac{\text{Total direct cost}}{1 - \text{target gross margin}} Selling price = 1 − target gross margin Total direct cost
Example: Direct costs are materials $7,800, labor $3,245, disposal and delivery $950, and permit $180, a total of $12,175 . The company targets a 30% gross margin to cover 20% overhead and 10% net profit.
12,175 1 − 0.30 = 12,175 0.70 = 17,392.86 \frac{12{,}175}{1 - 0.30} = \frac{12{,}175}{0.70} = 17{,}392.86 1 − 0.30 12 , 175 = 0.70 12 , 175 = 17 , 392.86
Marking up the cost by 30% instead would give $15,827.50, only a 23.1% margin. That is enough for overhead but leaves just 3.1% profit.
Presenting the Estimate
A professional proposal lists:
the exact scope : layers removed, deck inspection, ice barrier coverage past the wall line, underlayment type, drip edge, flashing replacement, ventilation, cleanup;
specifications : shingle brand and line, ASTM wind and impact ratings, nail count and type, metal types and gauges;
- unit prices for concealed conditions, such as "$85 per 4-by-8 sheet of 7/16-inch OSB replaced, installed";
- allowances , if any, and exclusions such as interior repairs, chimney masonry, and gutters unless listed;
the price , the payment schedule (a deposit, progress payments, and final, never the full job in advance), and the start and completion window;
permits, insurance, and warranty statements.
When accepted, the proposal must become a written, signed agreement that clearly states the specifications, cost, type and amount of work, and type and quality of materials ( R 338.1533 ). It must include your license information (MCL 339.2404a) and, for lien rights on a home, the statement that residential builders and M&A contractors must be licensed, with your license number (MCL 570.1114). For in-home sales, attach the Home Solicitation Sales Act notices (Section 3.4).
Checking the Estimate
Before sending the proposal:
Compare the price per square to your recent similar jobs. Check the slope factor, waste, and layer count. Confirm the ice barrier courses for the overhang and slope.
Confirm the crew size and schedule are realistic for the season.
After the job, compare actual labor hours and material use with the estimate, and update your production rates. Job costing is how estimates improve.
One Business and Law Estimating Question
PSI assigns one Business and Law question to "estimating pertaining to residential building." Expect it to test the same skills as this chapter: quantities, unit conversions, and the difference between markup and margin.