7.4 Material Takeoffs: Squares, Bundles, Waste, Underlayment, Ice Barrier, Metals & Fasteners

Michigan Roofing Contractor Exam

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: The Exam & Michigan Licensing Law

1.1 The Michigan Roofing License Exam: Format, Fees & Test-Day Rules 1.2 Who Must Be Licensed: Residential Builder vs. M&A Roofing & the Exemptions 1.3 Prelicensure Education, Application, Renewal & Continuing Competency 1.4 Company Licenses, Qualifying Officers, Salespersons & Reporting Changes 1.5 Rules of Conduct: Place of Business, Advertising, Written Agreements & Records 1.6 Complaints, Investigations, Hearings, Arbitration & Penalties

2 Chapter 2: Codes, Permits, Civil Rights & Environmental Rules

2.1 The State Construction Code, Permits & Inspections 2.2 Civil Rights, Fair Housing, ADA & Michigan Barrier-Free Design 2.3 EPA Hazardous-Materials Rules: Lead-Safe Renovation, Asbestos & Radon

3 Chapter 3: Business Organization, Contracts & In-Home Sales

3.1 Types of Business Organization: Sole Proprietorship, Partnership, LLC & Corporation 3.2 Contract Essentials: Requirements, Types, Terminology & When a Contract Binds 3.3 Addenda, Change Orders, Allowances, Schedules, Warranties, Financing & Breach 3.4 In-Home Sales: The Home Solicitation Sales Act & Door-to-Door Roofing Sales

4 Chapter 4: Project Management, Accounting, Taxes & Personnel

4.1 Project Management & Administration: Quality, Logistics, Schedules, Draws & Retainage 4.2 Accounting & Finance: Costs, Receivables, Cash Flow, Financial Statements & Ratios 4.3 Payroll & Tax Obligations: Federal, Michigan, Unemployment & Sales/Use Tax 4.4 Personnel: MIOSHA Administration, Recordkeeping, Wages, Minors & Benefits

5 Chapter 5: Insurance, Bonds & Construction Liens

5.1 Insurance for Roofing Contractors: Liability, Workers' Compensation, Vehicles, Property & Builders' Risk 5.2 Bonds, Public Works Bonding & the Building Contract Fund Act 5.3 Construction Lien Act I: Notices of Commencement & Furnishing, Sworn Statements & Waivers 5.4 Construction Lien Act II: Claims of Lien, Foreclosure, Priority & Residential Protections

6 Chapter 6: Roofing Safety & Public Protection (MIOSHA)

6.1 MIOSHA Part 45 Fall Protection & Personal Fall Arrest Systems 6.2 Guardrails, Safety Nets, Warning Lines, Safety Monitors, Covers & Fall Protection Plans 6.3 Ladders, Scaffolds, Roof Brackets & Aerial Lifts (MIOSHA Parts 11, 12 & 32) 6.4 Hazard Communication, SDS, Silica, Lead & Asbestos Exposure, Power Lines & Heat 6.5 Hoisting & Lift Equipment, Fire Prevention, PPE, Barricades, Debris & Recycling

7 Chapter 7: Planning, Structure & Estimating

7.1 Roof Types, Framing Terminology & Structural Loads 7.2 Pre-Job Walk-Through, Plans & Details, Permits & Selecting the Roof System 7.3 Roof Geometry, Slope, Pitch & Slope Factors for Measuring Roofs 7.4 Material Takeoffs: Squares, Bundles, Waste, Underlayment, Ice Barrier, Metals & Fasteners 7.5 Labor, Subcontractor & Access Costs and Preparing the Estimate

8 Chapter 8: Tear-Off, Deck Preparation & Underlayment

8.1 Roof Sheathing: Panel Grades, Spans, Edge Support & Nailing 8.2 Tear-Off vs. Recover, Reroofing Rules & Preparing the Site (MRC R908) 8.3 Michigan's Ice Barrier Requirement: Coverage, Materials & Detailing (R905.1.2) 8.4 Underlayment: Standards, Application by Slope & Attachment (R905.1.1) 8.5 Roof & Ceiling Insulation, Vapor Retarders, Air Sealing & Unvented Assemblies

9 Chapter 9: Steep-Slope Roof Systems

9.1 Asphalt Shingles: Types, ASTM D3462, Wind Classes, Impact & Fire Ratings 9.2 Installing Asphalt Shingles: Starter, Exposure, Nailing, Steep Slopes & Caps 9.3 Valleys: Linings, Open Metal, Closed-Cut & Woven Valleys 9.4 Metal Roof Systems, Tile, Slate & Wood Shingles and Shakes

10 Chapter 10: Low-Slope Roof Systems & Drainage

10.1 Single-Ply Membranes: EPDM, TPO & PVC 10.2 Built-Up Roofing & Modified Bitumen: Materials, Application, Kettles & Torch Safety 10.3 Low-Slope Drainage: Positive Drainage, Roof Drains, Overflow Scuppers & Correcting Ponding

11 Chapter 11: Flashings, Transitions & Penetrations

11.1 Drip Edge & Roof-Edge Metals (R905.2.8.5 and R903.2) 11.2 Sidewalls, Headwalls, Kick-Outs, Counterflashing & Pitch Transitions 11.3 Chimneys & Crickets, Skylights, Pipes, Flues, Exhaust Vents & Solar

12 Chapter 12: Ventilation, Inspection & Repair

12.1 Attic Ventilation Requirements & Net Free Vent Area Calculations (MRC R806) 12.2 Balanced Airflow, Vent Installation Practice & Preventing Ice Dams 12.3 Roof Inspections, Leak Diagnosis, Repairs & Roofovers

7.4 Material Takeoffs: Squares, Bundles, Waste, Underlayment, Ice Barrier, Metals & Fasteners

Key Takeaways Explain This Topic AI

A square is 100 square feet. Most standard shingles are packaged 3 bundles per square, but always use the manufacturer's coverage per bundle.

Waste factors rise with complexity, from roughly 10% on simple gables to 15% or more on hips and cut-up roofs, and bundle counts always round up.

Drip edge covers every eave and rake, with 2-inch laps. Estimate it by perimeter plus a lap allowance, divided by the stick length.

Ice barrier must reach at least 24 inches inside the exterior wall line, measured on the slope (overhang plus 24 inches, times the slope factor), so a 12-inch overhang on a 4:12 roof needs more than one 36-inch course.

The code requires at least 4 nails per strip shingle, so about 320 nails per square for 80 strips, with more where the manufacturer's high-wind or steep-slope pattern applies.

Last updated: September 2026

From Area to Bundles

Net squares = true roof area ÷ 100.

Gross squares = net squares × (1 + waste factor).

Bundles = gross squares × bundles per square. Always round up , because suppliers do not break bundles.

Typical waste allowances (use experience and the roof's shape):

  • Roof type Typical waste
  • Simple gable, few penetrations About 10%
  • Hip roof About 15%
  • Cut-up roof with dormers, valleys, turrets 15% to 20% or more

Hip roofs waste more because each course is cut at an angle at every hip. On gables, rake cut-offs can often start the next course.

Packaging: Most standard 3-tab and laminated shingles come 3 bundles per square . Some heavyweight designer shingles come 4 or 5 bundles per square. Always read the manufacturer's stated coverage.

Example: True area 2,482 square feet on a hip roof at 15% waste. Net = 24.82 squares. Gross = 24.82 × 1.15 = 28.54 squares. Bundles = 28.54 × 3 = 85.6, so order 86 bundles .

Linear Accessories

Item Where it goes How to estimate

Starter strip All eaves, and rakes where the manufacturer calls for it Eave (and rake) length ÷ coverage per bundle

Hip and ridge cap All hips and ridges (less any ridge vent coverage if the cap is part of the vent system) Total hip + ridge length ÷ linear feet per bundle

Drip edge Every eave and rake (R905.2.8.5), lapped 2 inches (Eaves + rakes) × a lap allowance, commonly about 10%, ÷ stick length (often 10 feet)

  • Valley metal or lining Valley centerlines Valley length from the plan run × valley factor, plus laps
  • Step flashing Sidewalls One piece per shingle course. Wall length on the slope ÷ exposure
  • Ridge vent Ridge From the ventilation calculation (Section 12.1)

Drip edge example: A gable roof has two 48-foot eaves and four 16.77-foot rakes. Perimeter = 96 + 67.1 = 163.1 feet. With a 10% allowance, that is 179.4 feet. At 10 feet per stick, order 18 pieces .

Ice Barrier (MRC R905.1.2)

Michigan requires an ice barrier on shingle-type coverings statewide. It extends from the lowest edge of the roof to a point at least 24 inches inside the exterior wall line . On slopes 8:12 or steeper , it must also reach at least 36 inches along the slope from the eave edge.

Coverage needed along the slope = (horizontal overhang measured to the outside face of the wall + 24 inches) × common slope factor.

  • Overhang Slope Horizontal distance Along the slope 36-inch courses needed
  • 12 in 4:12 36 in 36 × 1.054 = 37.9 in 2
  • 6 in 6:12 30 in 30 × 1.118 = 33.5 in 1
  • 18 in 6:12 42 in 42 × 1.118 = 47.0 in 2
  • 24 in 8:12 48 in 48 × 1.202 = 57.7 in (at least 36 in) 2

Allow for the manufacturer's side laps between courses. Add valleys, and add areas around chimneys and skylights if you plan to line them. Divide the total linear feet of each course by the usable roll length, taking end laps into account.

Underlayment

On 4:12 and steeper, one layer lapped at least 2 inches at the head and 4 inches at the ends, with end laps offset 6 feet (Table R905.1.1(2)).

From 2:12 to less than 4:12 , two layers: a 19-inch starter strip, then 36-inch sheets lapped 19 inches. This roughly doubles the underlayment quantity for those areas. Self-adhered ASTM D1970 underlayment over the whole deck is an alternative (R905.1.1 exception).

Deduct the area covered by ice barrier if the underlayment will not run under it, and add laps. Synthetic roll coverage varies by product, so use the manufacturer's net coverage.

Decking

Include a unit price for replacing damaged sheathing, such as per 4-by-8 sheet installed, or an allowance. On older homes with board decks, budget for overlaying spaced boards if needed. Asphalt shingles require a solidly sheathed deck (R905.2.1).

Nails

The code (R905.2.5 and R905.2.6) requires:

  • corrosion-resistant roofing nails at least 12 gauge (0.105 inch) shank with a 3/8-inch head (ASTM F1667);
  • penetration at least 3/4 inch into the sheathing, or through sheathing thinner than 3/4 inch;

at least 4 nails per strip shingle (2 per individual shingle), or more if the manufacturer requires.

A square of 12-by-36-inch 3-tab strips at 5-inch exposure uses about 80 strips, so 4 nails each is 320 nails per square . A 6-nail pattern is 480. Metric-size laminated shingles cover more per piece (about 64 to 66 per square), so count by the manufacturer's pieces per square. Reroofing over an existing layer, where allowed, needs longer nails to reach full penetration.

Putting It Together: Sample Order

A gable roof has a true area of 1,610 square feet, 96 feet of eaves, 67 feet of rakes, 48 feet of ridge, 12-inch overhangs, and a 6:12 slope.

  • Item Calculation Order
  • Shingles 16.1 squares × 1.10 = 17.7 squares × 3 54 bundles
  • Ice barrier (12 + 24) × 1.118 = 40.2 in, so 2 courses on 96 feet 192 linear feet plus laps
  • Drip edge (96 + 67) × 1.10 ÷ 10 18 sticks
  • Ridge cap 48 feet ÷ coverage per bundle Per product
  • Nails 17.7 squares × 320 About 5,700 nails