Study guide
7.3 Roof Geometry, Slope, Pitch & Slope Factors for Measuring Roofs
Michigan Roofing Contractor Exam
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: The Exam & Michigan Licensing Law
1.1 The Michigan Roofing License Exam: Format, Fees & Test-Day Rules 1.2 Who Must Be Licensed: Residential Builder vs. M&A Roofing & the Exemptions 1.3 Prelicensure Education, Application, Renewal & Continuing Competency 1.4 Company Licenses, Qualifying Officers, Salespersons & Reporting Changes 1.5 Rules of Conduct: Place of Business, Advertising, Written Agreements & Records 1.6 Complaints, Investigations, Hearings, Arbitration & Penalties
2 Chapter 2: Codes, Permits, Civil Rights & Environmental Rules
2.1 The State Construction Code, Permits & Inspections 2.2 Civil Rights, Fair Housing, ADA & Michigan Barrier-Free Design 2.3 EPA Hazardous-Materials Rules: Lead-Safe Renovation, Asbestos & Radon
3 Chapter 3: Business Organization, Contracts & In-Home Sales
3.1 Types of Business Organization: Sole Proprietorship, Partnership, LLC & Corporation 3.2 Contract Essentials: Requirements, Types, Terminology & When a Contract Binds 3.3 Addenda, Change Orders, Allowances, Schedules, Warranties, Financing & Breach 3.4 In-Home Sales: The Home Solicitation Sales Act & Door-to-Door Roofing Sales
4 Chapter 4: Project Management, Accounting, Taxes & Personnel
4.1 Project Management & Administration: Quality, Logistics, Schedules, Draws & Retainage 4.2 Accounting & Finance: Costs, Receivables, Cash Flow, Financial Statements & Ratios 4.3 Payroll & Tax Obligations: Federal, Michigan, Unemployment & Sales/Use Tax 4.4 Personnel: MIOSHA Administration, Recordkeeping, Wages, Minors & Benefits
5 Chapter 5: Insurance, Bonds & Construction Liens
5.1 Insurance for Roofing Contractors: Liability, Workers' Compensation, Vehicles, Property & Builders' Risk 5.2 Bonds, Public Works Bonding & the Building Contract Fund Act 5.3 Construction Lien Act I: Notices of Commencement & Furnishing, Sworn Statements & Waivers 5.4 Construction Lien Act II: Claims of Lien, Foreclosure, Priority & Residential Protections
6 Chapter 6: Roofing Safety & Public Protection (MIOSHA)
6.1 MIOSHA Part 45 Fall Protection & Personal Fall Arrest Systems 6.2 Guardrails, Safety Nets, Warning Lines, Safety Monitors, Covers & Fall Protection Plans 6.3 Ladders, Scaffolds, Roof Brackets & Aerial Lifts (MIOSHA Parts 11, 12 & 32) 6.4 Hazard Communication, SDS, Silica, Lead & Asbestos Exposure, Power Lines & Heat 6.5 Hoisting & Lift Equipment, Fire Prevention, PPE, Barricades, Debris & Recycling
7 Chapter 7: Planning, Structure & Estimating
7.1 Roof Types, Framing Terminology & Structural Loads 7.2 Pre-Job Walk-Through, Plans & Details, Permits & Selecting the Roof System 7.3 Roof Geometry, Slope, Pitch & Slope Factors for Measuring Roofs 7.4 Material Takeoffs: Squares, Bundles, Waste, Underlayment, Ice Barrier, Metals & Fasteners 7.5 Labor, Subcontractor & Access Costs and Preparing the Estimate
8 Chapter 8: Tear-Off, Deck Preparation & Underlayment
8.1 Roof Sheathing: Panel Grades, Spans, Edge Support & Nailing 8.2 Tear-Off vs. Recover, Reroofing Rules & Preparing the Site (MRC R908) 8.3 Michigan's Ice Barrier Requirement: Coverage, Materials & Detailing (R905.1.2) 8.4 Underlayment: Standards, Application by Slope & Attachment (R905.1.1) 8.5 Roof & Ceiling Insulation, Vapor Retarders, Air Sealing & Unvented Assemblies
9 Chapter 9: Steep-Slope Roof Systems
9.1 Asphalt Shingles: Types, ASTM D3462, Wind Classes, Impact & Fire Ratings 9.2 Installing Asphalt Shingles: Starter, Exposure, Nailing, Steep Slopes & Caps 9.3 Valleys: Linings, Open Metal, Closed-Cut & Woven Valleys 9.4 Metal Roof Systems, Tile, Slate & Wood Shingles and Shakes
10 Chapter 10: Low-Slope Roof Systems & Drainage
10.1 Single-Ply Membranes: EPDM, TPO & PVC 10.2 Built-Up Roofing & Modified Bitumen: Materials, Application, Kettles & Torch Safety 10.3 Low-Slope Drainage: Positive Drainage, Roof Drains, Overflow Scuppers & Correcting Ponding
11 Chapter 11: Flashings, Transitions & Penetrations
11.1 Drip Edge & Roof-Edge Metals (R905.2.8.5 and R903.2) 11.2 Sidewalls, Headwalls, Kick-Outs, Counterflashing & Pitch Transitions 11.3 Chimneys & Crickets, Skylights, Pipes, Flues, Exhaust Vents & Solar
12 Chapter 12: Ventilation, Inspection & Repair
12.1 Attic Ventilation Requirements & Net Free Vent Area Calculations (MRC R806) 12.2 Balanced Airflow, Vent Installation Practice & Preventing Ice Dams 12.3 Roof Inspections, Leak Diagnosis, Repairs & Roofovers
7.3 Roof Geometry, Slope, Pitch & Slope Factors for Measuring Roofs
Key Takeaways Explain This Topic AI
Slope is rise per 12 inches of run, such as 6:12, while pitch is total rise divided by total span, so 6:12 equals 1/4 pitch and 8:12 equals 1/3 pitch.
The common slope factor is the square root of (rise² + 144) divided by 12. Examples: 1.054 at 4:12, 1.118 at 6:12, 1.202 at 8:12, and 1.414 at 12:12.
When all planes share one slope, true roof area equals the horizontal projected area, including overhangs, times the common slope factor.
Hip and valley lengths equal the common run times the hip or valley factor, the square root of (rise² + 288) divided by 12. Examples: 1.453 at 4:12 and 1.500 at 6:12.
A roof's slope can be measured with a level and tape as the rise in 12 inches of horizontal run, or by dividing total rise by run and multiplying by 12.
Last updated: September 2026
Basic Terms
- Term Definition
- Span Horizontal distance between the outside of the bearing walls
- Run Horizontal distance one rafter covers, usually half the span
- Rise Vertical height from the top plate line to the ridge line
- Slope Rise in inches per 12 inches of run, written 6:12 or "6 in 12"
- Pitch Total rise divided by total span , written as a fraction
Since span is twice the run, pitch = slope rise ÷ 24 :
- Slope 3:12 4:12 6:12 8:12 12:12
- Pitch 1/8 1/6 1/4 1/3 1/2
- Measuring Slope on Site
Hold a level horizontally against the roof or rafter. Measure 12 inches along the level, then measure straight up to the roof. That measurement is the rise per foot. From drawings or known dimensions: slope = (rise ÷ run) × 12. A 14-foot run with a 7-foot rise is (7 ÷ 14) × 12 = 6:12 .
The Common Slope Factor
The slope factor converts a horizontal distance to the distance along the slope:
Common factor = rise 2 + 12 2 12 \text{Common factor} = \frac{\sqrt{\text{rise}^2 + 12^2}}{12} Common factor = 12 rise 2 + 1 2 2
- Slope Factor Slope Factor
- 3:12 1.031 8:12 1.202
- 4:12 1.054 9:12 1.250
- 5:12 1.083 10:12 1.302
- 6:12 1.118 12:12 1.414
- 7:12 1.158
True area of a roof plane = horizontal (plan) area × common factor.
Rafter length (horizontal run including overhang) = run × common factor.
The Projection Rule
When every plane on a roof has the same slope , gable, hip, and cut-up roofs alike, the total roof area equals the total horizontal projected area, including overhangs, times the common factor . Measure the building footprint plus overhangs, multiply, and apply the factor. With different slopes, compute each area separately.
Hip and Valley Factors
On a regular roof, where planes of equal slope meet at 90-degree corners, hips and valleys run diagonally in plan. They travel about 16.97 inches horizontally for each 12 inches of common run:
Hip or valley factor = rise 2 + 288 12 \text{Hip or valley factor} = \frac{\sqrt{\text{rise}^2 + 288}}{12} Hip or valley factor = 12 rise 2 + 288
- Slope 4:12 5:12 6:12 8:12 10:12 12:12
- Hip or valley factor 1.453 1.474 1.500 1.563 1.641 1.732
Hip or valley length = common run × hip or valley factor. You use these lengths to estimate ridge and hip caps, valley metal, and valley ice barrier.
Worked Problem 1: Gable Roof
A house is 28 feet by 46 feet, with 1-foot overhangs at both eaves and both rakes and a 6:12 slope.
Projected plan: (28 + 2) × (46 + 2) = 30 × 48 = 1,440 square feet .
True area: 1,440 × 1.118 = 1,609.9 square feet , or about 16.1 squares before waste.
Check with rafter length: run = 30 ÷ 2 = 15 feet, and 15 × 1.118 = 16.77 feet. Two planes: 2 × 48 × 16.77 = 1,609.9 square feet.
Rake length (each of 4 rakes) = 16.77 feet. Eave length = 48 feet × 2 = 96 feet.
Worked Problem 2: Hip Roof
A house is 32 feet by 56 feet, with 1.5-foot overhangs all around and an 8:12 slope.
Projected plan: 35 × 59 = 2,065 square feet .
True area: 2,065 × 1.202 = 2,482 square feet , or about 24.8 squares .
Common run = 35 ÷ 2 = 17.5 feet. Each hip = 17.5 × 1.563 = 27.4 feet . Four hips = about 109.4 feet.
Ridge length on a regular hip roof = length − width = 59 − 35 = 24 feet .
Hip plus ridge cap = 109.4 + 24 = about 133.4 linear feet .
Worked Problem 3: Converting a Measured Slope Length
From the eave, you measure 22 feet up a 10:12 slope to the ridge. The horizontal run is 22 ÷ 1.302 = 16.9 feet . The vertical rise is 16.9 × (10 ÷ 12) = 14.1 feet . Use this to check a drone report or plan against field measurements.
Measuring Existing Roofs
PSI lists three ways to measure: from blueprints and plans , from satellite imaging tools , and from the existing roof . For field measurement:
Measure eaves, rakes, and each plane's slope length, and sketch the roof.
Measure the slope of each plane. Dormers and porches often differ from the main roof.
Note penetrations, valleys, hips, ridges, and wall lengths for flashing.
Compare against the satellite or drone report. If they differ, trust careful field measurements.
Common Errors
Forgetting the slope factor and ordering by plan area, which undercounts by 11.8% at 6:12 and 20.2% at 8:12.
Using span instead of run for rafter or hip length.
Leaving out overhangs.
Applying the common factor to hip lengths. Use the hip or valley factor.