Study guide

12.3 Roof Inspections, Leak Diagnosis, Repairs & Roofovers

Michigan Roofing Contractor Exam

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: The Exam & Michigan Licensing Law

1.1 The Michigan Roofing License Exam: Format, Fees & Test-Day Rules 1.2 Who Must Be Licensed: Residential Builder vs. M&A Roofing & the Exemptions 1.3 Prelicensure Education, Application, Renewal & Continuing Competency 1.4 Company Licenses, Qualifying Officers, Salespersons & Reporting Changes 1.5 Rules of Conduct: Place of Business, Advertising, Written Agreements & Records 1.6 Complaints, Investigations, Hearings, Arbitration & Penalties

2 Chapter 2: Codes, Permits, Civil Rights & Environmental Rules

2.1 The State Construction Code, Permits & Inspections 2.2 Civil Rights, Fair Housing, ADA & Michigan Barrier-Free Design 2.3 EPA Hazardous-Materials Rules: Lead-Safe Renovation, Asbestos & Radon

3 Chapter 3: Business Organization, Contracts & In-Home Sales

3.1 Types of Business Organization: Sole Proprietorship, Partnership, LLC & Corporation 3.2 Contract Essentials: Requirements, Types, Terminology & When a Contract Binds 3.3 Addenda, Change Orders, Allowances, Schedules, Warranties, Financing & Breach 3.4 In-Home Sales: The Home Solicitation Sales Act & Door-to-Door Roofing Sales

4 Chapter 4: Project Management, Accounting, Taxes & Personnel

4.1 Project Management & Administration: Quality, Logistics, Schedules, Draws & Retainage 4.2 Accounting & Finance: Costs, Receivables, Cash Flow, Financial Statements & Ratios 4.3 Payroll & Tax Obligations: Federal, Michigan, Unemployment & Sales/Use Tax 4.4 Personnel: MIOSHA Administration, Recordkeeping, Wages, Minors & Benefits

5 Chapter 5: Insurance, Bonds & Construction Liens

5.1 Insurance for Roofing Contractors: Liability, Workers' Compensation, Vehicles, Property & Builders' Risk 5.2 Bonds, Public Works Bonding & the Building Contract Fund Act 5.3 Construction Lien Act I: Notices of Commencement & Furnishing, Sworn Statements & Waivers 5.4 Construction Lien Act II: Claims of Lien, Foreclosure, Priority & Residential Protections

6 Chapter 6: Roofing Safety & Public Protection (MIOSHA)

6.1 MIOSHA Part 45 Fall Protection & Personal Fall Arrest Systems 6.2 Guardrails, Safety Nets, Warning Lines, Safety Monitors, Covers & Fall Protection Plans 6.3 Ladders, Scaffolds, Roof Brackets & Aerial Lifts (MIOSHA Parts 11, 12 & 32) 6.4 Hazard Communication, SDS, Silica, Lead & Asbestos Exposure, Power Lines & Heat 6.5 Hoisting & Lift Equipment, Fire Prevention, PPE, Barricades, Debris & Recycling

7 Chapter 7: Planning, Structure & Estimating

7.1 Roof Types, Framing Terminology & Structural Loads 7.2 Pre-Job Walk-Through, Plans & Details, Permits & Selecting the Roof System 7.3 Roof Geometry, Slope, Pitch & Slope Factors for Measuring Roofs 7.4 Material Takeoffs: Squares, Bundles, Waste, Underlayment, Ice Barrier, Metals & Fasteners 7.5 Labor, Subcontractor & Access Costs and Preparing the Estimate

8 Chapter 8: Tear-Off, Deck Preparation & Underlayment

8.1 Roof Sheathing: Panel Grades, Spans, Edge Support & Nailing 8.2 Tear-Off vs. Recover, Reroofing Rules & Preparing the Site (MRC R908) 8.3 Michigan's Ice Barrier Requirement: Coverage, Materials & Detailing (R905.1.2) 8.4 Underlayment: Standards, Application by Slope & Attachment (R905.1.1) 8.5 Roof & Ceiling Insulation, Vapor Retarders, Air Sealing & Unvented Assemblies

9 Chapter 9: Steep-Slope Roof Systems

9.1 Asphalt Shingles: Types, ASTM D3462, Wind Classes, Impact & Fire Ratings 9.2 Installing Asphalt Shingles: Starter, Exposure, Nailing, Steep Slopes & Caps 9.3 Valleys: Linings, Open Metal, Closed-Cut & Woven Valleys 9.4 Metal Roof Systems, Tile, Slate & Wood Shingles and Shakes

10 Chapter 10: Low-Slope Roof Systems & Drainage

10.1 Single-Ply Membranes: EPDM, TPO & PVC 10.2 Built-Up Roofing & Modified Bitumen: Materials, Application, Kettles & Torch Safety 10.3 Low-Slope Drainage: Positive Drainage, Roof Drains, Overflow Scuppers & Correcting Ponding

11 Chapter 11: Flashings, Transitions & Penetrations

11.1 Drip Edge & Roof-Edge Metals (R905.2.8.5 and R903.2) 11.2 Sidewalls, Headwalls, Kick-Outs, Counterflashing & Pitch Transitions 11.3 Chimneys & Crickets, Skylights, Pipes, Flues, Exhaust Vents & Solar

12 Chapter 12: Ventilation, Inspection & Repair

12.1 Attic Ventilation Requirements & Net Free Vent Area Calculations (MRC R806) 12.2 Balanced Airflow, Vent Installation Practice & Preventing Ice Dams 12.3 Roof Inspections, Leak Diagnosis, Repairs & Roofovers

12.3 Roof Inspections, Leak Diagnosis, Repairs & Roofovers

Key Takeaways Explain This Topic AI

Water travels along the deck and framing before it drips, so trace a leak upslope from the stain, and water-test from the bottom of the suspected area upward.

When replacing a damaged shingle, remove the nails in the damaged shingle and in the course above that pass through it, then nail the new shingle in the manufacturer's pattern and hand-seal it.

A roofover is not allowed over water-soaked or deteriorated roofing, over slate, clay, cement, or asbestos-cement tile, or over two or more existing applications (R908.3.1.1).

Before LARA acts on a workmanship complaint, the complainant must show they gave the licensee notice of access times and that repairs were not made within 60 days (MCL 339.2411(4)(f)).

Failure or refusal to correct a structural matter that is materially deficient, dangerous, or hazardous is presumed to be dishonest or unfair dealing (R 338.1551(4)).

Last updated: September 2026

A Roof Inspection Routine

Always work safely. Use a ladder set up per MIOSHA Part 11 (Section 6.3), and use fall protection when working at 6 feet or more. Walk the roof only when it is dry and the covering allows foot traffic. Inspect from the ground and ladder first.

From the Ground and Eaves

Sagging ridges or a wavy deck (possible rafter damage, overloaded framing, or deck delamination).

Stains, rot, or peeling paint on fascia and soffits (a missing drip edge, gutter overflow, or ice damming).

Gutters full of granules. Heavy loss means the shingles are near the end of their life.

Streaks or moss on north slopes.

On the Roof

Area What to Look For

Field Curling (cupping or clawing), cracking, blisters, missing or creased tabs from wind, hail bruises, exposed or popped nails

Valleys Worn shingles, cut edges too close to the centerline, debris dams, rusted metal

Flashings Loose counterflashing, open reglets, missing kick-outs, rusted step flashing, cracked pipe boots, dried-out sealant

  • Penetrations Missing storm collars, loose skylight flashing, failed boots, unflashed satellite or solar mounts
  • Ridge and hips Cracked caps, blown-off caps, snow-infiltration signs at ridge vents

Low-slope areas Ponding more than 48 hours after rain, open seams, blisters, splits, clogged drains, missing overflows

In the Attic

Water stains on sheathing and rafters, daylight at penetrations, and frost or rusty nail tips (air leakage and poor ventilation).

Mold or dark sheathing near the eaves (blocked soffits or no baffles).

Bath or kitchen fans venting into the attic (M1501.1 violation).

Soft or delaminated sheathing.

Record everything with dated photos and notes. Give the owner a written report that separates what must be fixed from what is optional.

Tracing Leaks

Water enters at one point, then runs down the deck, rafters, or underlayment before dripping. Start at the stain and follow the path upslope .

Common sources are flashings at walls and chimneys, pipe boots, valleys, skylights, exposed nails, and ice dams, not the open field of shingles.

Water testing: have one person run a garden hose on a limited area, starting low and working upward , while another watches inside. Starting high wets everything below it and hides the source.

Consider condensation too. A winter "leak" that appears without rain is often frost melting in the attic.

  • Repair Methods
  • Asphalt Shingles

Work in mild weather if possible. Cold shingles crack, so warm them or wait.

Break the sealant bond of the damaged shingle and the course above with a flat bar.

Remove the nails in the damaged shingle and the nails in the course above that pass through it.

Slide in a matching shingle, and nail it in the manufacturer's nailing pattern , including high-wind patterns where required.

Hand-seal the tabs with asphalt roofing cement where the factory strip cannot seal right away, as the manufacturer directs.

Flashings

Replace cracked pipe boots , and slip the upper flange under the shingles above.

Re-set loose step flashing by lifting the shingles, and replace rusted pieces.

Re-cut and re-set counterflashing into mortar joints, and seal the reglet. Surface sealant alone is a short-term fix.

Add a missing kick-out . This means removing the lowest siding pieces, so coordinate with the siding trade.

Low-Slope Membranes

EPDM: clean and prime the area, apply a peel-and-stick patch or seam tape with rounded corners, roll it, and seal the edges with lap sealant, per the membrane maker.

TPO and PVC: clean and prepare the area, then heat-weld a patch and probe the seams. Aged TPO may need special cleaning before it will weld.

BUR and modified bitumen: cut out blisters and patch with compatible plies or cap sheet, or use cold adhesive. Torch work requires a hot-work permit and a fire watch (Section 6.5).

Wet insulation under a membrane loses its R-value and adds weight. Find it by core cuts or moisture surveys, such as infrared, and replace it before patching.

Repair, Recover, or Replace?

  • Choose When
  • Repair Damage is local, the roof has useful life left, and matching materials are available

Recover The roof is not prohibited under R908.3.1.1, the structure can carry the added load, and the manufacturer allows it (Section 8.2)

Replace (tear-off) Any R908.3.1.1 prohibition applies: the roof is water-soaked or deteriorated, is slate, clay, cement, or asbestos-cement tile, or has two or more existing applications. Also choose replacement where the deck needs repair or the owner wants a full warranty

A recover or replacement must meet Chapter 9 (R908.1), including drip edge and the Michigan ice barrier. Rusted or deteriorated flashings, edgings, outlets, and vents must be replaced (R908.5). Reroofing is not on the R105.2 list of work exempt from permits, so plan on a permit. Small repairs may be ordinary repairs that need no application under R105.2.2, but check with the local building department (Section 2.1).

When a Customer Calls About a Defect

Respond promptly. Under MCL 339.2411(4)(f) , a complainant must show that they gave the licensee notice of reasonable times and dates the home was accessible for repairs, and that the repairs were not made within 60 days after the notice was sent. The department can skip this if safety or the structure is at risk.

R 338.1551(4): failure or refusal to correct a structural matter that is materially deficient, dangerous, or hazardous is presumed to be dishonest or unfair dealing .

R 338.1551(5): all construction, renovations, alterations, and repairs must comply with the Michigan construction code.

Complaints may be filed within 18 months after the latest of completion, occupancy, or purchase (Section 1.6).

Keep written records of calls, visits, and repairs. Well-documented repairs protect the owner and the license.