Study guide
1.1 Exam Format, Provided References, Scoring & Scheduling
Minnesota Journeyman Electrician Study Guide Exam
Track your progress as you read
Finished sections get a check mark.
1 Minnesota Exam, Licensing & Electrical Law
1.1 Exam Format, Provided References, Scoring & Scheduling 1.2 The Minnesota Electrical Act, Board of Electricity & Code Adoption 1.3 Personal Licenses, Scope of Work & Electrical Contractors 1.4 Experience Credit, Registration, Reciprocity, Renewal & Continuing Education 1.5 Direct Supervision, Ratios & Licensing Exemptions 1.6 Electrical Permits, Inspections, Condemnation & Enforcement
2 Electrical Theory, Math & Power Calculations
2.1 Exam Math, Ohm's Law, Watt's Law & Series/Parallel Circuits 2.2 AC Fundamentals: Reactance, Impedance & Power Factor 2.3 Three-Phase Systems: Wye vs. Delta Calculations 2.4 Voltage Drop Calculations & Chapter 9 Conductor Properties 2.5 Transformer Ratios, Connections, Taps & Available Fault Current 2.6 Motor Connections, Control Circuits & Troubleshooting
3 NEC Structure & General Requirements
3.1 Navigating the 2026 NEC: Article 90, Code Structure & Article 100 Definitions 3.2 NEC Article 110: Working Clearances, Dedicated Space & Termination Ratings 3.3 Over-1000-Volt Installations, Guarding & Manholes (Article 110, Parts III–V)
4 Conductors, Identification & Ampacity
4.1 Conductor Insulation Types, Copper vs. Aluminum & Table 310.16 Allowable Ampacities 4.2 Ampacity Derating: Ambient Temperature Correction & Raceway Bundling Adjustments 4.3 Conductor Identification, Splices & Parallel Conductors
5 Branch Circuits, GFCI/AFCI & Required Outlets
5.1 Branch Circuit Sizing, Overcurrent Ratings & Multiwire Branch Circuits 5.2 GFCI & AFCI Protection Requirements (NEC 210.8 & 210.12) 5.3 Dwelling Receptacle Outlets, Required Circuits & Lighting Outlets (NEC 210.11, 210.52, 210.63 & 210.70)
6 Load Calculations (2026 NEC Article 120)
6.1 Article 120 Basics: Dwelling Lighting, Small-Appliance & Laundry Loads 6.2 Dwelling Standard Method: Appliances, Dryers, Ranges, Heating, EVSE & Neutral 6.3 Optional Methods: Single Dwelling, Existing Dwelling & Multifamily (2026 NEC 120.82–120.85) 6.4 Commercial Lighting, Receptacle, Sign & Show-Window Loads (Table 120.42(A) & 120.44) 6.5 Commercial Kitchens, Schools & Restaurants (2026 NEC 120.56, 120.86 & 120.88) 6.6 Farm Load Calculations (2026 NEC 120.102 & 120.103) 6.7 Feeder & Service Neutral Sizing (2026 NEC 120.61)
7 Feeders, Outside Wiring & Services
7.1 Feeder Design & Sizing Requirements (NEC Article 215) 7.2 Outside Feeders & Separate Buildings (Article 225 & 250.32) 7.3 Service Clearances, Overhead Drops & Underground Service Laterals 7.4 Service Equipment, Disconnecting Means, Surge Protection & GFPE (2026 NEC Article 230)
8 Overcurrent Protection
8.1 Overcurrent Protective Devices: Fuses, Breakers & Standard Ampere Ratings 8.2 Conductor Overcurrent Protection & Feeder Tap Rules (NEC 240.4 & 240.21) 8.3 OCPD Location, Breaker Voltage Ratings, Handle Ties & Arc Energy Reduction
9 System Grounding & Grounding Electrodes
9.1 Grounding vs. Bonding Principles & System Grounding (NEC Article 250 Parts I-II) 9.2 Grounding Electrode System: Permitted Electrodes & Installation (NEC 250.50 & 250.52) 9.3 Grounding Electrode Conductor (GEC) Sizing & Protection (NEC Table 250.66) 9.4 Main Bonding Jumper, System Bonding Jumper & Separately Derived Systems
10 Bonding & Equipment Grounding
10.1 Equipment Grounding Conductor (EGC) Types, Identification & Sizing (NEC Table 250.122) 10.2 Proportional Upsizing of EGC for Voltage Drop (NEC 250.122(B)) 10.3 Bonding of Interior Metal Piping, Structural Steel & Other Systems (NEC 250.104) 10.4 Bonding Methods, Equipment Requiring Grounding & Receptacle Grounding
11 General Wiring Methods & Underground Installations
11.1 General Wiring Methods & Mechanical Protection (NEC Article 300) 11.2 Underground Wiring Cover Requirements (NEC Table 300.7) 11.3 Securing & Supporting, Plenums, Firestopping & Raceway Installation (Article 300)
12 Raceways, Cables & Conduit Fill
12.1 Metal (RMC, IMC, EMT) & Nonmetallic (PVC, RTRC, LFNC) Raceways 12.2 Flexible Conduits, ENT, Wireways, Auxiliary Gutters & Surface Raceways 12.3 Busways & Cable Tray Systems (Articles 368 & 392) 12.4 Cable Assemblies (NM, UF, MC) & Minnesota Cold-Weather Installation Rules 12.5 Conduit & Tubing Fill Calculations (Chapter 9 & Annex C)
13 Boxes, Conduit Bodies & Cabinets
13.1 Box Installation, Support, Accessibility & Luminaire and Fan Boxes (Article 314) 13.2 Outlet, Switch & Junction Box Fill Calculations (NEC 314.16) 13.3 Pull and Junction Box Sizing for Conductors 4 AWG & Larger (NEC 314.28) 13.4 Cabinets, Cutout Boxes & Wire Bending Space (NEC Article 312)
14 Cords, Wiring Devices, Panelboards, Luminaires & Appliances
14.1 Flexible Cords, Flexible Cables & Fixture Wires (Articles 400 & 402) 14.2 Switches, Receptacles & Wiring Devices (Articles 404 & 406) 14.3 Panelboards, Switchboards & Switchgear (NEC Article 408) 14.4 Luminaires, Lampholders, Lighting Track & Low-Voltage Lighting (Articles 410 & 411) 14.5 Appliances, Fixed Electric Space Heating & Deicing Equipment (Articles 422, 424 & 426)
15 Motors, Controllers & Air Conditioning
15.1 Motor Full-Load Current Determination & Conductor Sizing (NEC 430.6 & 430.22) 15.2 Motor Branch-Circuit Short-Circuit & Ground-Fault Protection (NEC Table 430.52) 15.3 Motor Overload Protection & Feeder Calculations for Multiple Motors (NEC 430.32 & 430.24) 15.4 Motor Controllers, Disconnecting Means, Drives & Motor Control Centers (Article 430 Parts VII–XI) 15.5 Air Conditioning & Refrigeration Equipment (NEC Article 440)
16 Transformers, Generators & Equipment Over 1000 Volts
16.1 Transformer Overcurrent Protection & Sizing (NEC Article 450) 16.2 Generators & Transfer Switches (NEC Article 445) 16.3 Capacitors, Transformers Over 1000 V & Medium-Voltage Equipment (Articles 460, 450 & 495)
17 Hazardous (Classified) Locations
17.1 Hazardous (Classified) Locations: Classes, Divisions & Zones (NEC Articles 500-506) 17.2 Class I Locations: Wiring Methods & Conduit Seal-Offs (NEC Article 501) 17.3 Class II & Class III Locations and the Zone System (Articles 502, 503, 505 & 506) 17.4 Commercial Garages & Motor Fuel Dispensing Facilities (NEC Articles 511 & 514) 17.5 Spray Areas, Aircraft Hangars, Hazardous-Location Bonding & Intrinsic Safety (Articles 500, 504, 513 & 516)
18 Health Care, Assembly, Agricultural & Mobile Occupancies
18.1 Health Care Facilities: Patient Care Spaces & Redundant Grounding (NEC Article 517) 18.2 Places of Assembly, Carnivals & Fairs, and Temporary Installations (Articles 518, 525 & 590) 18.3 Agricultural Buildings, Equipotential Planes & Farm Distribution Points (Article 547) 18.4 Mobile & Manufactured Homes, RV Parks, and Marinas & Docks (Articles 550, 551 & 555)
19 Signs, Elevators, Pools, Solar & Other Specific Equipment
19.1 Signs & Outline Lighting, Office Partitions, IT Rooms & Irrigation Machines (Articles 600, 605, 645 & 675) 19.2 Elevators, Escalators & Platform Lifts (Article 620) 19.3 Swimming Pools, Spas & Water Features: Equipotential Bonding & GFCI (NEC Article 680) 19.4 Spas, Hot Tubs, Hydromassage Bathtubs, Fountains & Natural Bodies of Water (Article 680 Parts IV–VII & Article 682) 19.5 Solar Photovoltaic Systems (Article 690) 19.6 Small Wind Systems, Fire Pumps & Electric Vehicle Charging (Articles 694, 695 & 625)
20 Emergency, Standby & Interconnected Power Sources
20.1 Emergency Systems vs. Legally Required vs. Optional Standby (NEC Articles 700, 701, 702) 20.2 Interconnected Power Sources, Energy Storage & Power Control Systems (Articles 705, 706, 480 & 130)
21 Limited-Energy, Fire Alarm & Communications Systems
21.1 Remote-Control, Signaling & Power-Limited Circuits: Class 1, 2 & 3 (2026 Articles 206, 720–725) 21.2 Class 4 Fault-Managed Power, Tray Cables, Fire-Resistive Cable Systems & Limited-Energy Grounding (Articles 726, 727, 742, 750 & 772) 21.3 Fire Alarm Systems: NPLFA vs. PLFA Wiring & Overcurrent Protection (NEC Article 760) 21.4 Optical Fiber Cables & Communications Systems Entering Buildings (2026 Articles 720–723, 800, 810, 820)
1.1 Exam Format, Provided References, Scoring & Scheduling
Key Takeaways Explain This Topic AI
The Class A journeyworker exam has 80 questions, a 70% passing score (56 correct), and a 5½-hour time limit set by DLI's Electrical License Examination Guide.
Questions are written to the 2026 NEC, which took effect in Minnesota on August 17, 2026, and DLI's current exam format has applied since September 8, 2026.
DLI provides a soft-cover NEC with no tabs, a Laws and Rules Booklet (Minnesota Electrical Act plus Minnesota Rules chapters 3800 and 3801), and a basic desk calculator.
Results are emailed, generally within two weeks; a failed applicant may reapply 30 days after notice of failure with a new application and the $50 examination fee.
Copying questions, making notes about questions, getting help, or leaving the building during the exam is an automatic failure.
Last updated: October 2026
Why the format matters
The Minnesota journeyworker exam is not a vendor test. The Minnesota Department of Labor and Industry (DLI) writes it, approves who may sit for it, and grades it under Minnesota Statutes section 326B.33, subdivision 18 , which makes passing "a written or oral examination developed and administered by the commissioner" a precondition to any personal electrical license. DLI publishes the rules of the exam in its Electrical License Examination Guide . Knowing those rules lets you spend your preparation time on the right things: fast navigation of a clean code book, fluent arithmetic, and the knowledge areas DLI lists for the Class A journeyworker (AJ) license.
Exam facts at a glance
- Item Class A journeyworker (AJ) exam
- Number of questions 80 multiple-choice
- Point value Every question equal; full credit or zero, no partial credit
- Passing score 70% (at least 56 of 80)
- Time allowed 5½ hours (330 minutes)
St. Paul session Starts 8:15 a.m., ends 1:45 p.m.
- Code edition 2026 NEC (effective in Minnesota August 17, 2026)
- Units in questions Inch-pound units
- Results Emailed, generally within two weeks; never given by phone
- Application and examination fee $50 (Minn. Stat. 326B.092, subd. 1)
The 5½-hour limit gives you a little over 4 minutes per question ( 330 ÷ 80 = 4.125 330 \div 80 = 4.125 330 ÷ 80 = 4.125 ). That sounds generous, but multi-step load, motor, and box-fill questions can take 8–10 minutes each, so pacing still matters.
What DLI hands you at the exam
DLI provides every reference you are allowed to use:
The National Electrical Code in soft-cover format, "without tabs or other aids." The edition is the one adopted as part of the State Building Code when you test. Minnesota Rules part 1315.0200 now adopts ANSI/NFPA 70-2026 .
A Laws and Rules Booklet in DLI's current format, containing the Minnesota Electrical Act (Minn. Stat. 326B.31 to 326B.399) and Minnesota Rules chapters 3800 (licensing) and 3801 (electrical procedures).
An electronic calculator of the common desk type with addition, subtraction, multiplication, division, square root, and percentage keys.
No other materials or electronic devices, including cell phones, are allowed in the building. DLI also warns that "the majority of questions are intended to be answered without the applicant needing to refer to reference materials." Treat the book as a backup for tables and exact numbers, not as a substitute for knowing where rules live.
Important
Because your own tabbed code book is not allowed, practice with an untabbed 2026 NEC. Learn the index, the table of contents, and the location of high-use tables such as 310.16, 250.66, 250.122, 314.16(B), 430.52, 430.250, and Chapter 9 Tables 1, 4, 5, and 8.
How DLI writes questions
The guide describes four formats. A single correct answer item has one right statement. A negative-response item asks which choice does not state a rule; DLI says it uses these only in limited instances. An absolute item asks for a number, usually after a calculation, such as the minimum feeder conductor for a group of motors. A common item tests a general rule, such as how to size one equipment grounding conductor run with several circuits.
DLI also tells you how it builds distractors:
Wrong choices are written to be plausible , not silly.
Questions may include extraneous information you must ignore.
Unless a question says otherwise, assume a unity power factor .
Some questions target code violations installers repeatedly make .
You are expected to understand the question before reading the choices.
Degree of difficulty
Each question carries a difficulty rating from 1 to 5. Single-rule and definition questions rate low; questions that combine several rules or require several calculations rate high. DLI assigns each license type a target range. Exams for licenses that can serve as the responsible licensed person (Class A master, maintenance electrician, power limited technician) average 2.5 to 3.5 . The Class A journeyworker and elevator constructor exams, whose holders work under general supervision of those license holders, average 1.5 to 2.5 . Expect mostly direct code application with a steady share of calculations rather than master-level design problems.
Exam-day conduct rules
These rules come straight from DLI and cause automatic failures every year:
Bring a picture ID and arrive at least 30 minutes before your start time.
You must schedule ahead; walk-ins are not permitted , and you may reschedule only once .
Food and drink are permitted. You may use the restroom, but you may not leave the building ; leaving before you finish is an automatic failure.
Giving or receiving help , or copying questions or making notes about questions , is an automatic failure. You must then submit a new application with new fees.
The room may be electronically monitored, and you may not ask the proctor questions about the exam content.
Exam materials and scoring keys are nonpublic data under Minn. Stat. 13.34. You will not get a written or oral review of your exam. You may send DLI written comments about specific questions.
Applying, scheduling, and retaking
You apply online through DLI's iMS system, upload any work-experience verification forms not already on file, and pay the $50 application and examination fee. Once DLI approves the application, you receive an email with instructions to schedule. DLI's St. Paul office at 443 Lafayette Road North tests on Tuesdays, Wednesdays, and Thursdays , except in weeks with a state holiday. Regional sites listed by DLI include Bemidji, Detroit Lakes, Duluth, Mankato, Moorhead, Rochester, St. Cloud, Virginia, Willmar, and Winona. Available dates appear under your application in iMS.
If you fail, you may submit a new application 30 days after notification of the failure. Applicants who fail, or who miss a rescheduled exam, must pay a new application and examination fee. After you pass, DLI's result letter explains how to pay the separate license fee and obtain the license.
Applicants with disabilities may request alternative arrangements under the Americans with Disabilities Act with the application. The statute also allows an oral examination for an applicant who provides a written statement from a certified teacher or other qualified professional that a specific reading disability would prevent satisfactory performance on a written test.
Knowledge areas DLI lists for the AJ exam
DLI's knowledge-area table marks the Class A journeyworker column for essentially the entire NEC: Article 90; Chapter 1 general rules; Chapter 2 wiring and protection (branch circuits, feeders, load calculations, services, overcurrent protection, grounding and bonding); Chapter 3 wiring methods; Chapter 4 equipment (cords, devices, panelboards, luminaires, appliances, heating, motors, air conditioning, generators, transformers, capacitors); Chapter 5 occupancies; Chapter 6 equipment; Chapter 7 systems; Chapter 8 communications; Chapter 9 tables; and applied theory (math, Ohm's law, voltage drop, single- and three-phase power, transformer and motor connections, fault current, motor controls, power factor, and troubleshooting). The rest of this guide follows that list.
A practical pacing plan
First pass (about 90 minutes): answer definition, single-rule, and one-table questions. Flag anything that needs more than two minutes.
Second pass (about 2½ hours): work standard calculations such as ampacity correction, box fill, conduit fill, motor branch circuits, and transformer currents. Write every step on scratch paper.
Final pass: finish the longest calculations, then confirm that no question is blank. With no partial credit and no stated guessing penalty, a reasoned answer always beats a blank.